Will UK Retailers Skim the Cream with ESOS?

The British Retail Consortium (BRC) was quick out on the starting blocks with an ambitious plan to cut energy costs by 25% in 5 years. Their ?25-in-5? initiative is chasing a target of ?4.4 billion savings during the duration. Part of this program involves ?cutting a path through a complex and inaccessible policy landscape?. BRC believes this drawback is making its members think twice about making energy efficiency investments.

The UK?s sprawling network of grocers, department stores and malls is the nation?s second most hungry energy customer, having spent ?3.3 billion on it in 2013 when it accounted for almost 20% of carbon released. If you think that sounds bad, it purchased double that amount in 2005. However the consortium believes there is still more to come.

It bases this assumption on the push effect of UK energy rates increasing by a quarter during the duration of the project. ?So it makes sense to be investing in energy efficiency rather than paying bills,? Andrew Bolitho (property, energy, and transport policy adviser) told Business Green. The numbers mentioned exclude third party transport and distribution networks not under the British Retail Consortium umbrella.

The ?complex and inaccessible policy landscape? is the reflection of UK legislators not tidying up as they go along. BRC cites a ?vast number of policies ? spreading confusion, undermining investment and making it harder to raise capital?. The prime culprits are Britain?s CRC Energy Efficient Scheme (previously Carbon Reduction Commitment) which publishes league tables and ESOS. Andrew Bolitho believes this duality is driving confused investors away.

The British Retail Consortium is at pains to point out that this is not about watering things down, but making it simpler for participating companies to report on energy matters at a single point. It will soon go live with its own information hub providing information for retailers wishing to measure consumption at critical points, assemble the bigger picture and implement best practice.

Ecovaro agrees with Andrew Bolitho that lowering energy demand and cutting carbon is not just about technology. We can do much in terms of changing attitudes and providing refresher training and this does not have to cost that much. Studies have shown repeatedly that there is huge benefit in inviting employees to cross over to our side. In fact, they may already be on board to an extent that may surprise.

Check our similar posts

How Small Irish Businesses Avoid the GDPR Sting

Accountants providing chartered accounting services and tax advice are alerting smaller Irish companies to the consequences of the pending General Data Protection Regulation (GDPR). They believe these are going to feel the most pain come 25 May 2018, if they do not implement GDPR by then. We are trying our best to help avoid this situation by providing advice.

How to Kick the GDPR Ball into Play

The Irish Information Commissioner?s Office has produced a toolkit regarding where?s best to start. They suggest beginning with an information security assessment to determine the gaps companies need to close. Once quantified, this leads naturally to a plan of action, and resources needed to fulfil it. Here?s how to go about it:

1. Start by assessing your current ability to identify, assess, and manage threats to customer data security. Have you done anything at all to date? You must be holding some customer information surely, and it is highly likely the GDPR applies to you.

2. Next, review your company?s current customer data security policies. Are they documented and approved, or do new employees discover them sitting next to Nellie? Rate yourself on a scale where ten is successful implementation.

3. Now consider how well you have pinned responsibilities on individuals to implement policies and take the lead on GDPR. The latter should be the business owner, or a board member with clout to make things happen.

4. By now, you should have a grasp of the scale of work ahead of you, remembering the EU deadline is 25 May 2018. If this sounds overwhelming, consider outsourcing to your accountant or a specialist provider.

5. Under the General Data Protection Regulation you have only 72 hours to report a breach of customer data security to the Information Commissioner?s Office. Do you have a quality assurance mechanism to oversee this?

Tangible Things to Bring Your Own People on Board

With all the changes going on, there is a risk of your employees regarding GDPR as ?another management idea going nowhere.? Thus, it is important to incorporate the new EU regulations in staff training, particularly with regard to data security generally. They may fully come on board only once they see tangible signs of progress. You should in any case put the following measures in place unless you already have them:

1. A secure area for your servers and for any paperwork your customers provided. This implies access control on a need-to-know basis to protect the information against loss, damage, and theft.

2. A protocol for storage media and record disposal when you no longer require them or something supersedes them. You are the custodian of other people?s information and they deserve nothing less.

3. Procedures to secure customer data on employee mobile devices and computers: This must extend to work done at home, at consultant sites, and by remote workers.

4. Secure configuration of all existing and new hardware to minimise vulnerability and storage media crashes. These quality assurance measures should extend to removable media and remote backups.

So Is This the Worst of the Pain?

We are at the heart of the matter, although there is more to tell in future articles. You may be almost there, if you already protect your proprietary information. If not, you may have key company information already open to malware.We should welcome the EU General Data Protection Regulation as a notice that it is time to face up to the challenges of data protection and security generally. The age of hacking and malware is upon us. The offender could be a disgruntled employee, or your competition just down the street. It is time to take precautions.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

When Carrefour Pushed the Right Buttons

Retail giant Carrefour based in Boulogne Billancourt, France is big business in anybody?s numbers. Europe?s #1 retailer opened its first store in 1958 near a crossroads (Carrefour means ?crossroad? in French) and has largely not looked back since then. The slogan for the hypermarket chain with more than 1,500 outlets and close to a half million employees is ?choice and quality for everyone?. Our story begins when Carrefour decided these things belong at home too.

The company implemented a worldwide universal responsibility program firmly anchored on a tripod of goals for environmental, economic and social progress. Its first step was to appoint a five-person project team tasked with liaising with program delegates in all thirty countries in which it operates, and who had responsibility for driving these goals.

The team?s job was to make sure that policies, standards, procedures and key performance areas were common visions throughout Carrefour. By contrast, the local managers? were tasked with aligning these specifics to local conditions in terms of environmental, political and social issues. The project team checked the fit quarterly via video conferences.

The Triple Bottom Line Goals were woven through with Carrefour?s Seven Core Values, namely Freedom, Responsibility, Sharing, Respect, Integrity, Solidarity and Progress. Constant contact was maintained with staff and other stakeholders through ?awareness training? seminars and other dialogues. As the program took hold and flourished, it became evident that the retail giant needed help with managing the constant stream of metrics flowing in.

After reviewing options, Carrefour appointed a software provider to monitor progress against its primary focuses on energy, water, waste, refrigeration, paper, disposable checkout bags, hygiene & quality, management gender parity, disabled people and logistics. This enabled it to track progress online against past performance, and produce meaningful reports.

The Environmental Manager in the Corporate Sustainability Department waxed lyrical when he said, ?We believe that our sustainability strategy and software solution have powerfully improved collaboration, innovation, and overall performance?. He went on to describe how it was helping drive cost down and profitability up, while simultaneously growing brand.

Non-conformance costs can be high and run counter to the imperative to make a profit – while simultaneously ensuring a better world for our children?s children. In Carrefour?s case, having a consultant to measure progress was the key that unblocked the administrative bottleneck. Irish company Ecovaro does this for companies around the world. Click here. Discover what we will do for you.

Ready to work with Denizon?