Spreadsheet Woes – Burden in SOX Compliance and Other Regulations

End User Computing (EUC) or end User Developed Application (UDA) systems like spreadsheets used to be ideal ad-hoc solutions for data processing and financial reporting. But those days are long gone.

Today, due to regulations like the:

  • Sarbanes-Oxley (SOX) Act,
  • Dodd-Frank Act,
  • IFRS (International Financial Reporting Standards),
  • E.U. Data Protection Directive,
  • Basel II,
  • NAIC Model Audit Rules,
  • FAS 157,
  • yes, there?s more ? and counting

a company can be bogged down when it tries to comply with such regulations while maintaining spreadsheet-reliant financial and information systems.

In an age where regulatory compliance have become part of the norm, companies need to enforce more stringent control measures like version control, access control, testing, reconciliation, and many others, in order to pass audits and to ensure that their spreadsheets are giving them only accurate and reliable information.

Now, the problem is, these control measures aren’t exactly tailor-made for a spreadsheet environment. While yes, it is possible to set up a spreadsheet and EUC control environment that utilises best practices, this is a potentially expensive, laborious, and time-consuming exercise, and even then, the system will still not be as foolproof or efficient as the regulations call for.

Testing and reconciliation alone can cost a significant amount of time and money to be effective:

  1. It requires multiple testers who need to test spreadsheets down to the cell level.
  2. Testers will have to deal with terribly disorganized and complicated spreadsheet systems that typically involve single cells being fed information by other cells in other sheets, which in turn may be found in other workbooks, or in another folder.
  3. Each month, an organisation may have new spreadsheets with new links, new macros, new formulas, new locations, and hence new objects to test.
  4. Spreadsheets rarely come with any kind of supporting documentation and version control, further hampering the verification process.
  5. Because Windows won’t allow you to open two Excel files with the same name simultaneously and because a succession of monthly-revised spreadsheets separated by mere folders but still bearing the same name is common in spreadsheet systems, it would be difficult to compare one spreadsheet with any of its older versions.

But testing and reconciliation are just two of the many activities that make regulatory compliance terribly tedious for a spreadsheet-reliant organisation. Therefore, the sheer intricacy of spreadsheet systems make examining and maintaining them next to impossible.

On the other hand, you can’t afford not to take these regulations seriously. Non-compliance with regulatory mandates can have dire consequences, not the least of which is the loss of investor confidence. And when investors start to doubt the management’s capability, customers will start to walk away too. Now that is a loss your competitors will only be too happy to gain.

Learn more about our server application solutions and discover a better way to comply with regulations.

More Spreadsheet Blogs


Spreadsheet Risks in Banks


Top 10 Disadvantages of Spreadsheets


Disadvantages of Spreadsheets – obstacles to compliance in the Healthcare Industry


How Internal Auditors can win the War against Spreadsheet Fraud


Spreadsheet Reporting – No Room in your company in an age of Business Intelligence


Still looking for a Way to Consolidate Excel Spreadsheets?


Disadvantages of Spreadsheets


Spreadsheet woes – ill equipped for an Agile Business Environment


Spreadsheet Fraud


Spreadsheet Woes – Limited features for easy adoption of a control framework


Spreadsheet woes – Burden in SOX Compliance and other Regulations


Spreadsheet Risk Issues


Server Application Solutions – Don’t let Spreadsheets hold your Business back


Why Spreadsheets can send the pillars of Solvency II crashing down

?

Advert-Book-UK

amazon.co.uk

?

Advert-Book-USA

amazon.com

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Check our similar posts

2015 ESOS Guidelines Chapter 1 ? Who Qualifies

The base criteria are any UK undertaking that employs more than 250 people and/or has a turnover in excess of ?50 million and/or has a balance sheet total greater than ?43 million. There is little point in attempting to separate off high polluting areas. If one corporate group qualifies for ESOS, then all the others are obligated to take part too. The sterling equivalents of ?38,937,777 and ?33,486,489 were set on 31 December 2014 and apply to the first compliance period.

Representatives of Overseas Entities

UK registered branches of foreign entities are treated as if fully UK owned. They also have to sign up if any overseas corporate element meets the threshold no matter where in the world. The deciding factor is common ownership throughout the ESOS system. ecoVaro appreciates this. We have seen European companies dumping pollution in under-regulated countries for far too long.

Generic Undertakings that Could Comply

The common factor is energy consumption and the organisation’s type of work is irrelevant. The Environmental Agency has provided the following generic checklist of undertakings that could qualify:

Limited Companies Public Companies Trusts
Partnerships Private Equity Companies Limited Liability Partnerships
Unincorporated Associations Not-for-Profit Bodies Universities (Per Funding)

Organisations Close to Thresholds

Organisations that come close to, but do not quite meet the qualification threshold should cast their minds back to previous accounting periods, because ESOS considers current and previous years. The exact wording in the regulations states:

?Where, in any accounting period, an undertaking is a large undertaking (or a small or medium undertaking, as the case may be), it retains that status until it falls within the definition of a small or medium undertaking (or a large undertaking, as the case may be) for two consecutive accounting periods.?

Considering the ?50,000 penalty for not completing an assessment or making a false or misleading statement, it makes good sense for close misses to comply.

Joint Ventures and Participative Undertakings

If one element of a UK group qualifies for ESOS, then the others must follow suit with the highest one carrying responsibility. Franchisees are independent undertakings although they may collectively agree to participate. If trusts receive energy from a third party that must do an ESOS, then so must they. Private equity firms and private finance initiatives receive the same treatment as other enterprises. De-aggregations must be in writing following which separated ESOS accountability applies.

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Matrix Management: Benefits and Pitfalls

Matrix management brings together managers and employees from different departments to collaborate with each other towards the accomplishment of the organizational goals. As much as it is beneficial, matrix management also has limitations. Hence, companies should understand its benefits and pitfalls before implementing this management technique.

Benefits

The following are some of the advantages of matrix management:

Effective Communication of Information

Because of the hybrid nature of the matrix structure, it enables different departments to closely work together and communicate frequently in order to solve project issues. This leads to a proficient information exchange among leaders and subordinates. Consequently, it results to developed strategies, enhanced performance and quick productivity.

Efficient Use of Resources

Resources can be used efficiently in the organisation since it can be shared among functions and projects. As the communication line is more open, the valuable knowledge and highly skilled resources are easily distributed within the organisation.

Increased Motivation

The matrix structure promotes democracy. And with the employees working on a team, they are motivated to perform their duties better. The opinions and expertise of the employees are brought to the table and considered by the managers before they make decisions. This leads to employee satisfaction, empowerment and improved performance.

Flexibility

Since the employees communicate with each other more frequently, decision making becomes speedy and response is adaptive. They can easily adjust with diverse situations that the company encounters.

Skills Development

Matrix employees are pooled out for work assignments, even to projects that are not necessarily in line with their skill background. With this approach to management, employees have the chance to widen their skills and expertise.

Discipline Retention

One significant advantage of matrix management is that it enables the employees to maintain their skills in functional areas while working with multidisciplinary projects. Once the project is completed and the team wraps up, the members remain sharp in their discipline technically and return to their home functions.

Pitfalls

Here are some disadvantages of matrix management:

Power Struggle

In the matrix structure, there is always tension between the functional and project manager. Although their intent is polite, their conflicting demands and competition for control over the same resources make it more difficult.

Internal Complexity

Having more than one manager, the employees might become confused to who their immediate leader is. The dual authority can lead to internal complexity and possible communication problems. Worst, employee dissatisfaction and high employee turnover.

Heightened Conflict

In any given situation where people and resources are shared across projects, there would always be competition and conflict. When these issues are prolonged, conflicts will heightened and will lead to more internal problems.

Increased Stress

For the employees, being part of a matrix structure can be stressful. Their commitment is divided among the projects and their relationship with multiple managers requires various adjustments. Increased stress can negatively affect their performance in the long run.

Excessive Overhead Expenses

Overhead administrative costs, such as salaries, increase in a matrix structure. More expenses, more burden to the organisation. This is a challenge to matrix management that leaders should consider carefully.

These are just some of the advantages and disadvantages of matrix management. The list could go on, depending on the unique circumstances that organisations have. The key is that when you decide to implement matrix management, you should recognise how to take full advantage of its benefits and understand how to lessen, if not eradicate, the pitfalls of this approach to management.

Ready to work with Denizon?