Scrumming Down to Complete Projects

Everybody knows about rugby union scrums. For our purposes, perhaps it is best to view them as mini projects where the goal is to get the ball back to the fly-half no matter what the opposition does. Some scrums are set pieces where players follow planned manoeuvres. Loose / rolling scrums develop on the fly where the team responds as best according to the situation. If that sounds to you like software project management then read on, because there are more similarities?.

Isn’t Scrum Project Management the Same as Agile?

No it’s not, because Scrum is disinterested in customer liaison or project planning, although the team members may be happy to receive the accolades following success. In the same way that rugby players let somebody else decide the rules and arrange the fixtures, a software Scrum team just wants the action.

Scrum does however align closely ? dare I say interchangeably with Agile?s sprints. Stripping it of all the other stages frees the observer up to analyse it more closely in the context of a rough and tumble project, where every morning can begin with a backlog of revised requirements to back fit.

The 3 Main Phases of a Scrum

A Scrum is a single day in the life of a project, building onto what went before and setting the stage for what will happen the following day. The desired output is a block of component software that can be tested separately and inserted later. Scrumming is also a useful technique for managing any project that can be broken into discreet phases. The construction industry is a good example.

Phase 1 – Define the Backlog. A Scrum Team?s day begins with a 15 minute planning meeting where team members agree individual to-do lists called ?backlogs?.

Phase 2 – Sprint Towards the Goal. The team separates to allow each member to complete their individual lines of code. Little or no discussion is needed as this stage.

Phase 3 – Review Meeting. At the end of each working day, the team reconvenes to walk down what has been achieved, and check the interconnected functionality.

The 3 Main Phases of a Scrum ? Conclusions and Thoughts

Scrum is a great way to liberate a competent project team from unnecessary constraints that liberate creativity. The question you need to ask yourself as manager is, are you comfortable enough to watch proceedings from the side lines without rushing onto the field to grab the ball.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Check our similar posts

UK Government Updates ESOS Guidelines

Britain?s Environment Agency has produced an update to the ESOS guidelines previously published by the Department of Energy and Climate Change. Fortunately for businesses much of it has remained the same. Hence it is only necessary to highlight the changes here.

  1. Participants in joint ventures without a clear majority must assess themselves individually against criteria for participation, and run their own ESOS programs if they comply.
  2. If a party supplying energy to assets held in trust qualifies for ESOS then these assets must be included in its program.
  3. Total energy consumption applies only to assets held on both the 31 December 2014 and 5 December 2015 peg points. This is relevant to the construction industry where sites may exchange hands between the two dates. The definition of ?held? includes borrowed, leased, rented and used.
  4. Energy consumption while travelling by plane or ship is only relevant if either (or both) start and end-points are in the UK. Foreign travel may be voluntarily included at company discretion. The guidelines are silent regarding double counting when travelling to fellow EU states.
  5. The choice of sites to sample is at the discretion of the company and lead assessor. The findings of these audits must be applied across the board, and ?robust explanations? provided in the evidence pack for selection of specific sites. This is a departure from traditional emphasis on random.

The Environment Agency has provided the following checklist of what to keep in the evidence pack

  1. Contact details of participating and responsible undertakings
  2. Details of directors or equivalents who reviewed the assessment
  3. Written confirmation of this by these persons
  4. Contact details of lead assessor and the register they appear on
  5. Written confirmation by the assessor they signed the ESOS off
  6. Calculation of total energy consumption
  7. List of identified areas of significant consumption
  8. Details of audits and methodologies used
  9. Details of energy saving opportunities identified
  10. Details of methods used to address these opportunities / certificates
  11. Contracts covering aggregation or release of group members
  12. If less than twelve months of data used why this was so
  13. Justification for using this lesser time frame
  14. Reasons for including unverifiable data in assessments
  15. Methodology used for arriving at estimates applied
  16. If applicable, why the lead assessor overlooked a consumption profile

Check out: Ecovaro ? energy data analytics specialist 

2015 ESOS Guidelines Chapter 2 – Deadlines and Status Changes

The ESOS process is deadline driven and meeting key dates is a non-negotiable. The penalties for not complying / providing false or misleading information are ?50,000 each. Simply not maintaining adequate records could cost you ?5,000. The carrot on the end of the stick is the financial benefits you stand to gain.

Qualifying for inclusion under the ESOS umbrella depends on the status of your company in terms of employee numbers, turnover and balance sheet on 31 December 2014. Regardless of whether you meet the 2014 threshold or not, you must reconsider your situation on 31 December 2018, 2022 and 2026.

Compliance PeriodQualification Date Compliance Period Compliance Date
131 December 2014From 17 July 2014* to 5 December 20155 December 2015
231 December 2018From 6 December 2015 to 5 December 20195 December 2019
331 December 2022From 6 December 2019 to 5 December 20235 December 2023
431 December 2026From 6 December 2023 to 5 December 20275 December 2027

Notes:

1. The first compliance period begins on the date the regulations became effective

2. Energy audits from 6 December 2011 onward may go towards the first compliance report

Changes in Organisation Status

If your organisation status changes after a qualification date when you met compliance thresholds, you are still bound to complete your ESOS assessment for that compliance period. This is regardless of any change in size or structure. Your qualification status then remains in force until the next qualification date when you must reconsider it.

Migrating from CRM to Big Data

Big data moved to centre stage from being just another fad, and is being punted as the latest cure-all for information woes. It may well be, although like all transitions there are pitfalls. Denizon decided to highlight the major ones in the hope of fostering better understanding of what is involved.

Accurate data and interpretation of it have become increasingly critical. Ideas Laboratory reports that 84% of managers regard understanding their clients and predicting market trends essential, with accelerating demand for data savvy people the inevitable result. However Inc 5000 thinks many of them may have little idea of where to start. We should apply the lessons learned from when we implemented CRM because the dynamics are similar.

Be More Results Oriented

Denizon believes the key is focusing on the results we expect from Big Data first. Only then is it appropriate to apply our minds to the technology. By working the other way round we may end up with less than optimum solutions. We should understand the differences between options before committing to a choice, because it is expensive to switch software platforms in midstream. data lakes, hadoop, nosql, and graph databases all have their places, provided the solution you buy is scalable.

Clean Up Data First

The golden rule is not to automate anything before you understand it. Know the origin of your data, and if this is not reliable clean it up before you automate it. Big Data projects fail when executives become so enthused by results that they forget to ask themselves, ?Does this make sense in terms of what I expected??

Beware First Impressions

Big Data is just that. Many bits of information aggregated into averages and summaries. It does not make recommendations. It only prompts questions and what-if?s. Overlooking the need for the analytics that must follow can have you blindly relying on algorithms while setting your business sense aside.

Hire the Best Brains

Big Data?s competitive advantage depends on what human minds make with the processed information it spits out. This means tracing and affording creative talent able to make the shift from reactive analytics to proactive interaction with the data, and the customer decisions behind it.

If this provides a d?j? vu moment then you are not alone. Every iteration of the software revolution has seen vendors selling while the fish were running, and buyers clamouring for the opportunity. Decide what you want out first, use clean data, beware first impressions and get your analytics right. Then you are on the way to migrating successfully from CRM to Big Data.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?