What Sub-Metering did for Nissan in Tennessee

When Nissan built its motor manufacturing plant in Smyrna 30 years ago, the 5.9 million square-foot factory employing over 8,000 people was state of art. After the 2005 hurricane season sky-rocketed energy prices, the energy team looked beyond efficient lighting at the more important aspect of utility usage in the plant itself. Let’s examine how they went about sub-metering and what it gained for them.

The Nissan energy team faced three challenges as they began their study. They had a rudimentary high-level data collection system (NEMAC) that was so primitive they had to transfer the data to spread-sheets to analyse it. To compound this, the engineering staff were focused on the priority of getting cars faster through the line. Finally, they faced the daunting task of making modifications to reticulation systems without affecting manufacturing throughput. But where to start?

The energy team chose the route of collaboration with assembly and maintenance people as they began the initial phase of tracking down existing meters and detecting gaps. They installed most additional equipment during normal service outages. Exceptions were treated as minor jobs to be done when convenient. Their next step was to connect the additional meters to their ageing NEMAC, and learn how to use it properly for the first time.

Although this was a cranky solution, it had the advantage of not calling for additional funding which would have caused delays. However operations personnel were concerned that energy-saving shutdowns between shifts and over weekends could cause false starts. ?We’ve already squeezed the lemon dry,? they seemed to say. ?What makes you think there?s more to come??

The energy team had a lucky break when they stumbled into an opportunity to prove their point early into implementation. They spotted a four-hourly power consumption spike they knew was worth examining. They traced this to an air dryer that was set to cyclical operation because it lacked a dew-point sensor. The company recovered the $1,500 this cost to fix, in an amazing 6 weeks.

Suitably encouraged and now supported by the operating and maintenance departments, the Smyrna energy team expanded their project to empower operating staff to adjust production schedules to optimise energy use, and maintenance staff to detect machines that were running without output value. The ongoing savings are significant and levels of shop floor staff motivation are higher.

Let’s leave the final word to the energy team facilitator who says, ?The only disadvantage of sub-metering is that now we can’t imagine doing without it.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Check our similar posts

2015 – What’s ahead for UK Business?

According to reports just in, the global environment industry is down. Less money is available for what some CEO?s still see as grudge expenditure, and many U.S. agencies are seeking soft budget cuts. The UK is proving to be an exception following the announcement of ESOS, and EcoVaro does not expect the May elections will have much impact in this regard.

ESOS calls for mandatory energy assessments in companies above a certain size, and requires specific proposals to cut consumption. There is no indication of compulsory follow-through, although it is clear the Environment Agency hopes rising electricity prices and the prospect of monetary savings will do the trick.

It is an open question whether the Tory government would have interfered with commerce to this extent, were it not for the European directive that enforced it. The overall goal is to cut EU energy consumption across the board by 20% by 2020. Energy consultants are rubbing their hands in glee. EcoVaro?s response is to provide cloud-based software.

We will be interested to see how many UK companies make the first deadline of 5 December 2015, in the light of reports that half the 9,000 firms affected appear not to even know that ESOS exists. Some will no doubt pay last-minute lip service. Those with an eye on their own sustainability will grasp the Energy Saving Opportunity Scheme with both hands.

The initial ESOS deadline was always going to be a challenge. Some big corporates have stolen a march albeit egged on by green stakeholders. The next challenge comes in June 2015 with the implementation of the European Union?s ?Waste Catalogue? of hazardous substances, and rules for their disposal. We hope a new ISO 14001 will arrive soon and pull the loose threads together.

The introduction of carbon trading late this year brings further opportunities to increase profits through wise stewardship. Auditable metrics are essential for this.

EcoVaro can assist by processing your raw data. We provide this service on a virtual cloud. In return, you can get advice on optimising the quality of your graphs for presentations. 

What Energy Management Software did for CDC

Chrome Deposit Corporation ? that’s CDC for short ? reconditions giant rollers used to finish steel and aluminium sheets in Portage, Indiana by applying grinding, texturing and plating methods. While management was initially surprised when the University of Delaware singled their plant out for energy assessment, this took them on a journey to bring energy consumption down despite being in an expansion phase.

Metal finishing and refinishing is an energy-intensive business where machines mainly do the work while workforces as small as 50 individuals tend them. Environmental impacts also need countering within a challenging environment of burgeoning natural gas and electricity prices.

The Consultant’s Recommendations

The University of Delaware was fortunate that Chrome Deposit Corporation had consistently measured its energy consumption since inception in 1986. This enabled it to pinpoint six strategies as having potential for technological and process improvements.

  • Insulate condensate tanks and pipes
  • Analyse flue gas air-fuel ratios
  • Lower compressed air pressures
  • Install stack dampers on boilers
  • Replace belts with pulleys and cogs
  • Fit covers on plant exhaust fans

CDC implemented only four of the six recommendations. This was because the boiler manufacturer did not recommend stack dampers, and the company was unable to afford certain process automation and controls.

Natural Gas Savings

The project team began by analysing stack gases from boilers used to heat chrome tanks and evaporate wastewater. They found the boilers were burning rich and that several joints in gas lines were leaking. Correcting these issues achieved an instant gas saving of 12% despite increased production.

Reduced Water Consumption

The team established that city water was used to cool the rectifiers. It reduced this by an astonishing 85% by implementing a closed-loop system and adding two chillers. This also helped the water company spend less on chemicals, and energy to drive pumps, purifiers and fans.

Summary of Benefits

Electricity consumption reduced by 18% in real terms, and natural gas by 35%. When these two savings are merged they represent an overall 25% energy saving. These benefits were implemented across the company?s six other plants, resulting in benefits CDC management never dreamed of when the University of Delaware approached them.

ecoVaro offers a similar data analytics service that is available online worldwide. We have helped other companies slash their energy bills with similarly exciting results. We?ll be delighted to share ideas that only data analytics can reveal.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
A Business Case for Sharing

We blogged about sharing services in a decentralised business context recently, and explained why we think why these should be IT-Based for speedy delivery. This is not to say that all shared services projects worldwide have been resounding successes. This is often down to the lack of a solid business case up front. We decided to lay out the logic behind this process.

Management Overview ? The overview includes a clear definition of why the current situation is unacceptable, the anticipated benefits of sharing, and an implementation plan were it to go ahead. The project should not proceed until the stakeholders have considered and agreed on this.

Alternatives Considered ? The next stage is to get closer to the other options in order to determine whether an alternative might perhaps be preferable. Substitutes for shared services are often doing nothing, improving the current method, and outsourcing the service to a third party.

The Bottom Line in Business ? Sharing services comes at an initial cost of infrastructure changes, and the impact on human capital (the latter deserves its own blog). The following need careful consideration from the financial angle:

Numbers to Work Through

  • Manpower to design and roll the project out in parallel with the existing organisation.
  • Capital for creating facilities at the central point including civil works, furniture and equipment and IT infrastructure.
  • The costs of travel, feeding and accommodation. These can be significant depending on the time that implementation takes.
  • The opportunity loss of diverting key staff – and the cost of temporary replacements – if appointing line staff to the project team.
  • Crystal-clear project metrics including (a) the direct, realisable savings (b) the medium and long-term effects on profit and (c) where to deploy the savings

Risk Management

Shared services projects don’t go equally smoothly, although planning should reduce the risk to manageable levels. Nonetheless it is important to imagine potential snags, decide how to mitigate them and what the cost might be.

We believe in implementing shared services on a pilot basis in the business unit that eventually provides them. We recommend building these out to other branches only when new processes are working smoothly.

Moving On From a Decision

We recommend you revisit your management overview, the logic behind it, the assumptions you made, and the costs and benefits you envisage before deciding to go ahead

The final step in proving a business case is doable should be fleshing out your roadmap into a detailed operations plan with dependencies on a spreadsheet.

Ready to work with Denizon?