What Sub-Metering did for Nissan in Tennessee

When Nissan built its motor manufacturing plant in Smyrna 30 years ago, the 5.9 million square-foot factory employing over 8,000 people was state of art. After the 2005 hurricane season sky-rocketed energy prices, the energy team looked beyond efficient lighting at the more important aspect of utility usage in the plant itself. Let’s examine how they went about sub-metering and what it gained for them.

The Nissan energy team faced three challenges as they began their study. They had a rudimentary high-level data collection system (NEMAC) that was so primitive they had to transfer the data to spread-sheets to analyse it. To compound this, the engineering staff were focused on the priority of getting cars faster through the line. Finally, they faced the daunting task of making modifications to reticulation systems without affecting manufacturing throughput. But where to start?

The energy team chose the route of collaboration with assembly and maintenance people as they began the initial phase of tracking down existing meters and detecting gaps. They installed most additional equipment during normal service outages. Exceptions were treated as minor jobs to be done when convenient. Their next step was to connect the additional meters to their ageing NEMAC, and learn how to use it properly for the first time.

Although this was a cranky solution, it had the advantage of not calling for additional funding which would have caused delays. However operations personnel were concerned that energy-saving shutdowns between shifts and over weekends could cause false starts. ?We’ve already squeezed the lemon dry,? they seemed to say. ?What makes you think there?s more to come??

The energy team had a lucky break when they stumbled into an opportunity to prove their point early into implementation. They spotted a four-hourly power consumption spike they knew was worth examining. They traced this to an air dryer that was set to cyclical operation because it lacked a dew-point sensor. The company recovered the $1,500 this cost to fix, in an amazing 6 weeks.

Suitably encouraged and now supported by the operating and maintenance departments, the Smyrna energy team expanded their project to empower operating staff to adjust production schedules to optimise energy use, and maintenance staff to detect machines that were running without output value. The ongoing savings are significant and levels of shop floor staff motivation are higher.

Let’s leave the final word to the energy team facilitator who says, ?The only disadvantage of sub-metering is that now we can’t imagine doing without it.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Check our similar posts

Scrumming Down to Complete Projects

Everybody knows about rugby union scrums. For our purposes, perhaps it is best to view them as mini projects where the goal is to get the ball back to the fly-half no matter what the opposition does. Some scrums are set pieces where players follow planned manoeuvres. Loose / rolling scrums develop on the fly where the team responds as best according to the situation. If that sounds to you like software project management then read on, because there are more similarities?.

Isn’t Scrum Project Management the Same as Agile?

No it’s not, because Scrum is disinterested in customer liaison or project planning, although the team members may be happy to receive the accolades following success. In the same way that rugby players let somebody else decide the rules and arrange the fixtures, a software Scrum team just wants the action.

Scrum does however align closely ? dare I say interchangeably with Agile?s sprints. Stripping it of all the other stages frees the observer up to analyse it more closely in the context of a rough and tumble project, where every morning can begin with a backlog of revised requirements to back fit.

The 3 Main Phases of a Scrum

A Scrum is a single day in the life of a project, building onto what went before and setting the stage for what will happen the following day. The desired output is a block of component software that can be tested separately and inserted later. Scrumming is also a useful technique for managing any project that can be broken into discreet phases. The construction industry is a good example.

Phase 1 – Define the Backlog. A Scrum Team?s day begins with a 15 minute planning meeting where team members agree individual to-do lists called ?backlogs?.

Phase 2 – Sprint Towards the Goal. The team separates to allow each member to complete their individual lines of code. Little or no discussion is needed as this stage.

Phase 3 – Review Meeting. At the end of each working day, the team reconvenes to walk down what has been achieved, and check the interconnected functionality.

The 3 Main Phases of a Scrum ? Conclusions and Thoughts

Scrum is a great way to liberate a competent project team from unnecessary constraints that liberate creativity. The question you need to ask yourself as manager is, are you comfortable enough to watch proceedings from the side lines without rushing onto the field to grab the ball.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
ESOS What is the Truth?

When the UK administration introduced its ESOS Energy Savings Opportunity Scheme reactions from business people followed a familiar theme.

  • Do nothing it will go away
  • The next Westminster will drop this
  • Another stealth tax. I don’t have time for this
  • Give the problem to admin and tell them to fix it

ecovaro decided to share three facts with you. These are

(1) ESOS is not a government money spinner

(2) all major political parties support it, and

(3) it is a cost-effective way to put money back in your pocket while feeling better about what business pumps into the environment.

Four More ESOS Facts

1. You Cannot Give the Problem to Admin ? Energy is technical. The lead belongs with your operations staff because they understand how your systems work. Some things are best outsourced though. ecovaro is here to help.

2. ESOS is Not Going to Go Away ? A company inside the regulation net must submit its first report by 6 December 2015. Non-compliance risks the following penalties:

  • ?5,000 for not maintaining adequate records
  • ?50,000 for not completing the assessment
  • ?50,000 for making a false or misleading statement

3. The Employee Count is the Annual Average – The employment criteria (unlike balance sheet and turnover) is the monthly average of full and part-time employees taken across the full financial year. The fact you have <250 employees in December 2015 when the first report is due does not necessarily let you off the hook.

4. The 6 December 2014 Report is No Big Deal ? When you think about it the administration is hardly likely to spend years wading through 9,000 detailed company energy plans. It has no authority to comment in any case. All that is required is for a senior director to confirm reading the document, and a lead assessor to agree it complies with the law.

Does this mean that ESOS is a damp squib? We do not think so, although some firms may take the low road. ecovaro believes the financial benefits will carry the process forward, and that the imperative to make the world a better place will do the rest.

What ISO 14001 Status did for Cummins Inc.

Cummins manufactures engines and power generation products, and has been a household name almost since inception in 1919. It sells its products in over 300 countries, through approximately 6,000 dealerships employing 40,000 people. Because its product line runs off fossil fuel it is under steady pressure to display a cleaner carbon footprint.

Cummins decided to go for the big one by qualifying for ISO 14001 certification. This is a subset of a family of standards relating to managing environmental impact while complying with all applicable legislation. In this sense, it is similar to the ISO 9000 quality management system, because it focuses on how products are produced (as opposed to how those products perform). Compliance with ISO 14001 was a doubly important goal, because it is part of the European Union?s Eco Management and Audit Scheme and fast becoming mandatory on suppliers to governments.

The qualification process follows the well-established principle of plan, do, check, act. It begins with gap analysis to detect materials and processes that affect the environment. This is followed by implementation of necessary changes affecting operations, documentation, emergency strategies and employee education. The third step involves measuring and monitoring performance. Finally, the project moves into a phase of ongoing maintenance, and continuous improvement as circumstances change.

In Cummins case, the project was almost worldwide and called for environmental, health and safety reporting throughout the organisation. The information was shared via a globally accessible document repository, and then processed centrally at the head office in Columbia, Indiana USA.

Measuring environmental performance almost inevitably has other benefits that make it doubly worthwhile. Speaking at the 2014 National Safety Council Congress after receiving the top award for excellence, Cummins chairman and ceo Tom Linebarger commented on a journey that was ?nothing short of amazing? yet wasn’t even a ?pathway to the finish line?.

?All of us feel like we have way more to do to make sure that our environment is as safe as it could be,? he added, ?so that our sustainability footprint is as good as it can be and that we continue to set more aggressive goals every year. That’s just how we think about it.? Linebarger concluded.

If you are taking your company on a journey to new heights of environmental excellence, then you should consider choosing ecoVaro as your travelling companion. We are environmental management specialists and have proprietary software geared to process your data. We also have a wealth of experience, and a treasure chest of roadmaps to help you achieve your goal.

Ready to work with Denizon?