User-Friendly RASCI Accountability Matrices

Right now, you’re probably thinking that’s a statement of opposites. Something dreamed up by a consultant to impress, or just to fill a blog page. But wait. What if I taught you to create order in procedural chaos in five minutes flat? ?Would you be interested then?

The first step is to create a story line ?

Let’s imagine five friends decide to row a boat across a river to an island. Mary is in charge and responsible for steering in the right direction. John on the other hand is going to do the rowing, while Sue who once watched a rowing competition will be on hand to give advice. James will sit up front so he can tell Mary when they have arrived. Finally Kevin is going to have a snooze but wants James to wake him up just before they reach the island.

That’s kind of hard to follow, isn’t it ?

Let’s see if we can make some sense of it with a basic RASCI diagram ?

Responsibility Matrix: Rowing to the Island
Activity Responsible Accountable Supportive Consulted Informed
Person John Mary Sue James Kevin
Role Oarsman Captain Consultant Navigator Sleeper

?

Now let’s add a simple timeline ?

Responsibility Matrix: Rowing to the Island
? Sue John Mary James Kevin
Gives Direction ? ? A ? ?
Rows the Boat ? R ? ? ?
Provides Advice S ? ? ? ?
Announces Arrival ? ? A C ?
Surfaces From Sleep ? ? ? C I
Ties Boat to Tree ? ? A ? ?

?

Things are more complicated in reality ?

Quite correct. Although if I had jumped in at the detail end I might have lost you. Here?s a more serious example.

rasci

?

There?s absolutely no necessity for you so examine the diagram in any detail, other to note the method is even more valuable in large, corporate environments. This one is actually a RACI diagram because there are no supportive roles (which is the way the system was originally configured).

Other varieties you may come across include PACSI (perform, accountable, control, suggest, inform), and RACI-VS that adds verifier and signatory to the original mix. There are several more you can look at Wikipedia if you like.

Check our similar posts

Denizon’s Business Continuity Services

Disruptions to business operations can be as catastrophic as a Hurricane Katrina or a 9/11 or as relatively trivial as a minor power outage or a planned shutdown. What ever the gravity, scope and duration the disruption has, your company should be able to handle each situation so that you can declare “business as usual” and really mean it. (more…)

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Operational Efficiency Initiatives

When was the last time you checked your technology spending against your IT infrastructure’s contribution to the bottom line?

Chances are, what’s happening underneath all those automated processes, expensive hardware, and fancy graphical user interfaces is not doing your bottom line any good.

If you don’t keep a watchful eye, your IT operations can easily nurture a lot of wastage and unnecessary costs. Underutilised servers, duplicate processes, poorly managed bandwidths, and too much complexity are among the common culprits.

For minor problems, we can eliminate wastage by setting up some technology enhancements, instilling best practices, and performing a few tweaks. However, if you’re not adequately trained on how to go about with it, your band-aid solutions can add more complexity to the mix.

Of course, there will always come a time when you will have to spend on new technologies to maintain the overall efficiency of your IT infrastructure. Whether you intend to purchase new hardware or software applications or build an entirely new infrastructure, the sheer cost of such undertakings warrants seeking expert advice.

Failure to do so can result in fragmented resources lacking in cohesiveness, which don’t contribute to efficiency at all.

Our solutions for improving operational efficiencies cover the entire spectrum: from planning what to buy, optimising what you’ve already bought, to making your team comfortable with them all. Please find time to view our solutions below and uncover ways to drive those profits up even as you work within your budget.

 

More Operational Review Blogs

 

Carrying out an Operational Review

 

Operational Reviews

 

Operational Efficiency Initiatives

 

Operational Review Defined

 

Ready to work with Denizon?