User-Friendly RASCI Accountability Matrices

Right now, you’re probably thinking that’s a statement of opposites. Something dreamed up by a consultant to impress, or just to fill a blog page. But wait. What if I taught you to create order in procedural chaos in five minutes flat? ?Would you be interested then?

The first step is to create a story line ?

Let’s imagine five friends decide to row a boat across a river to an island. Mary is in charge and responsible for steering in the right direction. John on the other hand is going to do the rowing, while Sue who once watched a rowing competition will be on hand to give advice. James will sit up front so he can tell Mary when they have arrived. Finally Kevin is going to have a snooze but wants James to wake him up just before they reach the island.

That’s kind of hard to follow, isn’t it ?

Let’s see if we can make some sense of it with a basic RASCI diagram ?

Responsibility Matrix: Rowing to the Island
Activity Responsible Accountable Supportive Consulted Informed
Person John Mary Sue James Kevin
Role Oarsman Captain Consultant Navigator Sleeper

?

Now let’s add a simple timeline ?

Responsibility Matrix: Rowing to the Island
? Sue John Mary James Kevin
Gives Direction ? ? A ? ?
Rows the Boat ? R ? ? ?
Provides Advice S ? ? ? ?
Announces Arrival ? ? A C ?
Surfaces From Sleep ? ? ? C I
Ties Boat to Tree ? ? A ? ?

?

Things are more complicated in reality ?

Quite correct. Although if I had jumped in at the detail end I might have lost you. Here?s a more serious example.

rasci

?

There?s absolutely no necessity for you so examine the diagram in any detail, other to note the method is even more valuable in large, corporate environments. This one is actually a RACI diagram because there are no supportive roles (which is the way the system was originally configured).

Other varieties you may come across include PACSI (perform, accountable, control, suggest, inform), and RACI-VS that adds verifier and signatory to the original mix. There are several more you can look at Wikipedia if you like.

Check our similar posts

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

2015 ESOS Guidelines Chapter 1 ? Who Qualifies

The base criteria are any UK undertaking that employs more than 250 people and/or has a turnover in excess of ?50 million and/or has a balance sheet total greater than ?43 million. There is little point in attempting to separate off high polluting areas. If one corporate group qualifies for ESOS, then all the others are obligated to take part too. The sterling equivalents of ?38,937,777 and ?33,486,489 were set on 31 December 2014 and apply to the first compliance period.

Representatives of Overseas Entities

UK registered branches of foreign entities are treated as if fully UK owned. They also have to sign up if any overseas corporate element meets the threshold no matter where in the world. The deciding factor is common ownership throughout the ESOS system. ecoVaro appreciates this. We have seen European companies dumping pollution in under-regulated countries for far too long.

Generic Undertakings that Could Comply

The common factor is energy consumption and the organisation’s type of work is irrelevant. The Environmental Agency has provided the following generic checklist of undertakings that could qualify:

Limited Companies Public Companies Trusts
Partnerships Private Equity Companies Limited Liability Partnerships
Unincorporated Associations Not-for-Profit Bodies Universities (Per Funding)

Organisations Close to Thresholds

Organisations that come close to, but do not quite meet the qualification threshold should cast their minds back to previous accounting periods, because ESOS considers current and previous years. The exact wording in the regulations states:

?Where, in any accounting period, an undertaking is a large undertaking (or a small or medium undertaking, as the case may be), it retains that status until it falls within the definition of a small or medium undertaking (or a large undertaking, as the case may be) for two consecutive accounting periods.?

Considering the ?50,000 penalty for not completing an assessment or making a false or misleading statement, it makes good sense for close misses to comply.

Joint Ventures and Participative Undertakings

If one element of a UK group qualifies for ESOS, then the others must follow suit with the highest one carrying responsibility. Franchisees are independent undertakings although they may collectively agree to participate. If trusts receive energy from a third party that must do an ESOS, then so must they. Private equity firms and private finance initiatives receive the same treatment as other enterprises. De-aggregations must be in writing following which separated ESOS accountability applies.

Virtualisation

Using an IT solution that can provide the fastest (but still reliable) disaster recovery process is essential for the success of any business continuity plan. Although virtualisation is still considered leading edge technology by many business continuity specialists, it definitely brings a promise that, once fulfilled, can result in the cheapest, fastest, and most comprehensive solution for business continuity.

One great advantage of virtualisation over traditional BC (Business Continuity) methods is the relatively cheaper cost needed to achieve a certain level of business continuity assurance. Thus, more companies will find it easier to reach their required minimum for BC assurance. By contrast, some BCPs (Business Continuity Plan) based on a physical environment require companies to invest more than what they are willing to in order to reach the same minimum level of assurance.

Virtual machines, which can already encapsulate your operating systems and their corresponding applications, can be transported as a file from one machine running a compatible hypervisor to another. This makes the business continuity tasks of backup, replication, and restoration simpler and faster.

As of 2008, about 54% of IT professionals in Europe were willing to implement virtualisation within a maximum of two years. Furthermore, the expected compound annual growth rate of installed virtualised servers from 2008 to 2012 is already pegged at 33%.

If you want your organisation to take advantage of the benefits of this revolutionary technology, we’d be more than willing to help you discover what it can do for you. Then once you decide to make that transition to virtualisation, we can guide you every step of the way.

  • As not all applications are suited for virtualisation (e.g. some are too demanding on I/O and memory access), we’ll start by reviewing your entire IT system to see which portions can be implemented on a virtualized environment.
  • Using virtualisation and replication, we can conduct disaster recovery tests using up-to-date data without interrupting operations in your main IT site. Running these tests will increase your team’s preparedness and will allow you to discover possible weak points.
  • Provide a simple but comprehensive protection and backup system that encapsulates not only data, but also system configurations and application installations. This kind of setup allows for faster and easier disaster recovery operations. Because of these same characteristics, you can enjoy zero downtime while performing scheduled maintenance operations.
  • Since virtual machines are hardware-independent and transparent to operating systems, we can help you run a mix of legacy and new systems as well as open source and proprietary systems, allowing for more flexibility in your BCP budgeting.

We can also assist you with the following:

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?