Denizon’s Business Continuity Services

Disruptions to business operations can be as catastrophic as a Hurricane Katrina or a 9/11 or as relatively trivial as a minor power outage or a planned shutdown. What ever the gravity, scope and duration the disruption has, your company should be able to handle each situation so that you can declare “business as usual” and really mean it.

By implementing a business continuity plan, your enterprise will not just be able to resume business after a disaster strikes. Rather, your enterprise will be able to deliver goods and services continuously.

One of the major factors that prevent businesses from resuming immediately after a disaster is the loss of data. That is why you’ll want to keep your data in the most secure places.

At Denizon, we won’t just ensure that all your data stays protected at all times, we’ll also put up the appropriate procedures to guarantee their availability in the shortest possible time whenever an interruption happens. That way, all your stakeholders – customers, suppliers, regulators, investors, and everyone in your team – can get back to business right away.

To achieve this, we’ll work with you to plan for and set up the necessary infrastructure, IT solutions, organisation, and practices. We’ll assess your risks, identify the threats and vulnerabilities, then come up with ways to control them.

Ironically, the very act of laying down the foundations of business continuity is a major disruption by itself. Now, both disruptions and even the act of preventing them cost money. That is why we’ve devised a system to reduce interruptions to the most acceptable levels as well as forgo all unnecessary costs.

Do find time to view our service offerings and we’ll show you how to bring down those downtimes.

We can assist you with the following:

Check our similar posts

UK Government Updates ESOS Guidelines

Britain?s Environment Agency has produced an update to the ESOS guidelines previously published by the Department of Energy and Climate Change. Fortunately for businesses much of it has remained the same. Hence it is only necessary to highlight the changes here.

  1. Participants in joint ventures without a clear majority must assess themselves individually against criteria for participation, and run their own ESOS programs if they comply.
  2. If a party supplying energy to assets held in trust qualifies for ESOS then these assets must be included in its program.
  3. Total energy consumption applies only to assets held on both the 31 December 2014 and 5 December 2015 peg points. This is relevant to the construction industry where sites may exchange hands between the two dates. The definition of ?held? includes borrowed, leased, rented and used.
  4. Energy consumption while travelling by plane or ship is only relevant if either (or both) start and end-points are in the UK. Foreign travel may be voluntarily included at company discretion. The guidelines are silent regarding double counting when travelling to fellow EU states.
  5. The choice of sites to sample is at the discretion of the company and lead assessor. The findings of these audits must be applied across the board, and ?robust explanations? provided in the evidence pack for selection of specific sites. This is a departure from traditional emphasis on random.

The Environment Agency has provided the following checklist of what to keep in the evidence pack

  1. Contact details of participating and responsible undertakings
  2. Details of directors or equivalents who reviewed the assessment
  3. Written confirmation of this by these persons
  4. Contact details of lead assessor and the register they appear on
  5. Written confirmation by the assessor they signed the ESOS off
  6. Calculation of total energy consumption
  7. List of identified areas of significant consumption
  8. Details of audits and methodologies used
  9. Details of energy saving opportunities identified
  10. Details of methods used to address these opportunities / certificates
  11. Contracts covering aggregation or release of group members
  12. If less than twelve months of data used why this was so
  13. Justification for using this lesser time frame
  14. Reasons for including unverifiable data in assessments
  15. Methodology used for arriving at estimates applied
  16. If applicable, why the lead assessor overlooked a consumption profile

Check out: Ecovaro ? energy data analytics specialist 

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

How Internal Auditors can win The War against Spreadsheet Fraud

To prevent another round of million dollar scandals due to fraudulent manipulations on spreadsheets, regulatory bodies have launched major offensives against these well-loved User Developed Applications (UDAs). Naturally, internal auditors are front and center in carrying out these offensives.

While regulations like the Sarbanes-Oxley Act, Dodd-Frank Act, and Solvency II can only be effective if end users are able to carry out the activities and practices required of them, auditors need to ascertain that they have. Sad to say, when it comes to spreadsheets, that is easier said than done.

Because spreadsheets are loosely distributed by nature, internal auditors always find it hard to: locate them, identify ownership, and trace their relationships with other spreadsheets. Now, we’re still talking about naturally occurring spreadsheets. How much more with files that have been deliberately tampered?

Spreadsheets can be altered in a variety of ways, especially if the purpose is to conceal fraudulent activities. Fraudsters can, for instance:

  • hide columns or rows,
  • perform conditional formatting, which changes the appearance of cells depending on certain values
  • replace cell entries with false values either through direct input or by linking to other spreadsheet sources
  • apply small, incremental changes in multiple cells or even spreadsheets to avoid detection
  • design macros and user defined functions to carry out fraudulent manipulations automatically

Recognising the seemingly insurmountable task ahead, the Institute of Internal Auditors released a guide designed specifically for the task of auditing user-developed applications, which of course includes spreadsheets.

But is this really the weapon internal auditors should be wielding in their quest to bring down spreadsheet fraud? Our answer is no. In fact, we believe no such weapon has to be wielded at all?because the only way to get rid of spreadsheet fraud is to eliminate spreadsheets once and for all.

Imagine how easy it would be for internal auditors to conduct their audits if data were kept in a centralised server instead of being scattered throughout the organisation in end-user hard drives.

And that’s not all. Because a server-based solution can be configured to have its own built-in controls, all your data will be under lock and key; unlike spreadsheet-based systems wherein storing a spreadsheet file inside a password-protected workstation does not guarantee equal security for all the other spreadsheets scattered throughout your company.

Learn more about Denizon’s server application solutions and discover a more efficient way for your internal auditors to carry out their jobs.

More Spreadsheet Blogs

 

Spreadsheet Risks in Banks

 

Top 10 Disadvantages of Spreadsheets

 

Disadvantages of Spreadsheets – obstacles to compliance in the Healthcare Industry

 

How Internal Auditors can win the War against Spreadsheet Fraud

 

Spreadsheet Reporting – No Room in your company in an age of Business Intelligence

 

Still looking for a Way to Consolidate Excel Spreadsheets?

 

Disadvantages of Spreadsheets

 

Spreadsheet woes – ill equipped for an Agile Business Environment

 

Spreadsheet Fraud

 

Spreadsheet Woes – Limited features for easy adoption of a control framework

 

Spreadsheet woes – Burden in SOX Compliance and other Regulations

 

Spreadsheet Risk Issues

 

Server Application Solutions – Don’t let Spreadsheets hold your Business back

 

Why Spreadsheets can send the pillars of Solvency II crashing down

?

Advert-Book-UK

amazon.co.uk

?

Advert-Book-USA

amazon.com

 

Ready to work with Denizon?