Is Your Project Agile, a Scrum or a Kanban?

Few projects pan out the way we expect when starting out. This is normal in any creative planning phase. We half suspect the ones that follow a straight line are the exceptions to the rule. Urban legend has it; Edison made a thousand prototypes before his first bulb lit up, and then went on to comment, ?genius is 1% inspiration, 99% perspiration?. Later, he added that many of life’s failures are people who did not realise just how close they were to success when they gave up.

So be it to this day, and so be it with project planning too. There is no one size fits all approach when it comes to it. Agile, Scrum and Kanban each have their supporters and places where they do well. Project planning often works best when we use a sequential combination of them, appropriate to what is currently happening on the ground.

Of the three, Agile is by far the most comprehensive. It provides a structure that begins with project vision / conceptualisation, and goes as far as celebration when the job is over, and retrospective discussion afterwards. However, the emphasis on daily planning meetings may dent freethinking, and even smother it.

Scrum on the other hand says ?forget all that bureaucracy?. There is a job to do and today is the day we are going to do it. Although the core Agile teamwork is still there it ignores macro project planning, and could not be bothered with staying in touch with customers. If using Scrum, it is best to give those jobs to someone else.

The joker in the pack is Kanban, It believes that rules are there to substitute for thought, and that true progress only comes from responsible freedom. It belongs in mature organisations that have passed through Scrum and Agile phases and have embarked on a voyage towards perfection.

That said, there can be no substitute for human leadership, especially when defined as the social influence that binds the efforts of others towards a single task.

Check our similar posts

2015 ESOS Guidelines Chapter 1 ? Who Qualifies

The base criteria are any UK undertaking that employs more than 250 people and/or has a turnover in excess of ?50 million and/or has a balance sheet total greater than ?43 million. There is little point in attempting to separate off high polluting areas. If one corporate group qualifies for ESOS, then all the others are obligated to take part too. The sterling equivalents of ?38,937,777 and ?33,486,489 were set on 31 December 2014 and apply to the first compliance period.

Representatives of Overseas Entities

UK registered branches of foreign entities are treated as if fully UK owned. They also have to sign up if any overseas corporate element meets the threshold no matter where in the world. The deciding factor is common ownership throughout the ESOS system. ecoVaro appreciates this. We have seen European companies dumping pollution in under-regulated countries for far too long.

Generic Undertakings that Could Comply

The common factor is energy consumption and the organisation’s type of work is irrelevant. The Environmental Agency has provided the following generic checklist of undertakings that could qualify:

Limited Companies Public Companies Trusts
Partnerships Private Equity Companies Limited Liability Partnerships
Unincorporated Associations Not-for-Profit Bodies Universities (Per Funding)

Organisations Close to Thresholds

Organisations that come close to, but do not quite meet the qualification threshold should cast their minds back to previous accounting periods, because ESOS considers current and previous years. The exact wording in the regulations states:

?Where, in any accounting period, an undertaking is a large undertaking (or a small or medium undertaking, as the case may be), it retains that status until it falls within the definition of a small or medium undertaking (or a large undertaking, as the case may be) for two consecutive accounting periods.?

Considering the ?50,000 penalty for not completing an assessment or making a false or misleading statement, it makes good sense for close misses to comply.

Joint Ventures and Participative Undertakings

If one element of a UK group qualifies for ESOS, then the others must follow suit with the highest one carrying responsibility. Franchisees are independent undertakings although they may collectively agree to participate. If trusts receive energy from a third party that must do an ESOS, then so must they. Private equity firms and private finance initiatives receive the same treatment as other enterprises. De-aggregations must be in writing following which separated ESOS accountability applies.

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

2015 ESOS Guidelines Chapter 3 ? The ESOS Assessment

ESOS operates in tandem with the ISO 50001 (Energy Management) system that encourages continual improvement in the efficient use of energy. Any UK enterprise qualifying for ESOS that has current ISO 50001 certification on the compliance date by an approved body (and that covers the entire UK corporate group) may present this as evidence of having completed its ESOS assessment. It does however still require board-level certification, following which it must notify the Environment Agency accordingly.

The Alternate ESOS Route

In the absence of an ISO 50001 energy management certificate addressing comprehensive energy use, a qualifying UK enterprise must:

  1. Measure Total Energy Consumption in either kWh or energy spend in pounds sterling, and across the entire operation including buildings, industrial processes and transport.
  2. Identify Areas of Significant Energy Consumption that account for at least 90% of the total. The balance falls into a de minimis group that is officially too trivial to merit consideration.
  3. Consider Available Routes to Compliance. These could include ISO 500001 part-certification, display energy certificates, green deal assessments, ESOS compliant energy audits, self-audits and independent assessments
  4. Do an Internal Review to make sure that you have covered every area of significant consumption. This is an important strategic step to avoid the possibility of failing to comply completely.
  5. Appoint an Approved Lead Assessor who may be internal or external to your enterprise, but must have ESOS approval. This person confirms you have met all ESOS requirements (unless you have no de minimis exceptions).
  6. Obtain Internal Certification by one of more board-level directors. They must certify they are satisfied with the veracity of the reports. They must also confirm that the enterprise is compliant with the scheme.
  7. Notify the Environment Agency of Compliance within the deadline using the online notification system at snapsurveys.com as soon as the enterprise believes is fully compliant.
  8. Assemble your ESOS Evidential Pack and back it up in a safe place. Remember, it is your responsibility to provide proof of the above. Unearthing evidence a year later it not something to look forward to.

The ESOS assessment process is largely self-regulatory, although there are checks and balances in place including lead assessor and board-level certifications. As you work through what may seem to be a nuisance remember the primary objectives. These are saving money and reducing carbon emissions. Contact Ecovaro if we can assist in any way.

Ready to work with Denizon?