Energy Cooperation Mechanisms in the EU

While the original mission of the European Union was to bring countries together to prevent future wars, this has spun out into a variety of other cooperative mechanisms its founders may never have dreamed of. Take energy for example, where the European Energy Directive puts energy cooperation mechanisms in place to help member states achieve the collective goal.

This inter-connectivity is essential because countries have different opportunities. For example, some may easily meet their renewable targets with an abundance of suitable rivers, while others may have a more regular supply of sunshine. To capitalise on these opportunities the EU created an internal energy market to make it easier for countries to work together and achieve their goals in cost-effective ways. The three major mechanisms are

  • Joint Projects
  • Statistical Transfers
  • Joint Support Schemes

Joint Projects

The simplest form is where two member states co-fund a power generation, heating or cooling scheme and share the benefits. This could be anything from a hydro project on their common border to co-developing bio-fuel technology. They do not necessarily share the benefits, but they do share the renewable energy credits that flow from it.

An EU country may also enter into a joint project with a non-EU nation, and claim a portion of the credit, provided the project generates electricity and this physically flows into the union.

Statistical Transfers

A statistical transfer occurs when one member state has an abundance of renewable energy opportunities such that it can readily meet its targets, and has surplus credits it wishes to exchange for cash. It ?sells? these through the EU accounting system to a country willing to pay for the assistance.

This aspect of the cooperative mechanism provides an incentive for member states to exceed their targets. It also controls costs, because the receiver has the opportunity to avoid more expensive capital outlays.

Joint Support Schemes

In the case of joint support schemes, two or more member countries combine efforts to encourage renewable energy / heating / cooling systems in their respective territories. This concept is not yet fully explored. It might for example include common feed-in tariffs / premiums or common certificate trading and quota systems.

Conclusion

A common thread runs through these three cooperative mechanisms and there are close interlinks. The question in ecoVaro?s mind is the extent to which the system will evolve from statistical support systems, towards full open engagement.

Check our similar posts

Is Your Project Agile, a Scrum or a Kanban?

Few projects pan out the way we expect when starting out. This is normal in any creative planning phase. We half suspect the ones that follow a straight line are the exceptions to the rule. Urban legend has it; Edison made a thousand prototypes before his first bulb lit up, and then went on to comment, ?genius is 1% inspiration, 99% perspiration?. Later, he added that many of life’s failures are people who did not realise just how close they were to success when they gave up.

So be it to this day, and so be it with project planning too. There is no one size fits all approach when it comes to it. Agile, Scrum and Kanban each have their supporters and places where they do well. Project planning often works best when we use a sequential combination of them, appropriate to what is currently happening on the ground.

Of the three, Agile is by far the most comprehensive. It provides a structure that begins with project vision / conceptualisation, and goes as far as celebration when the job is over, and retrospective discussion afterwards. However, the emphasis on daily planning meetings may dent freethinking, and even smother it.

Scrum on the other hand says ?forget all that bureaucracy?. There is a job to do and today is the day we are going to do it. Although the core Agile teamwork is still there it ignores macro project planning, and could not be bothered with staying in touch with customers. If using Scrum, it is best to give those jobs to someone else.

The joker in the pack is Kanban, It believes that rules are there to substitute for thought, and that true progress only comes from responsible freedom. It belongs in mature organisations that have passed through Scrum and Agile phases and have embarked on a voyage towards perfection.

That said, there can be no substitute for human leadership, especially when defined as the social influence that binds the efforts of others towards a single task.

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Convert visits to sales to repeat purchases

The moment you start seeing more than a thousand unique visitors in just one day, we won’t be surprised if you’d be grinning ear to ear the entire week. But when weeks turn into months, you’ll then remember why you started off on this venture in the first place … and it wasn’t about just owning an immensely popular website.

People, like you, who’ve chosen to invest in eCommerce were most likely thinking along the lines of great ROI, revenues, and profits. Now that you have thousands of visitors, how would you like to have, say for a start, 1% of them buying the products on your site?

You know more about your own product prices; you do the math. But what might really interest you is that a slight change in that 1% conversion rate can already spell a big difference in your profits. Now imagine bringing that 1% up to at least 10%. That’s possible, but not if you simply rely on guesswork.

We rely on tests applicable to complex multi-variable systems, just like today’s typical eCommerce websites, in determining which combination of copy text, landing page images, form layouts, and background colours generate higher conversion rates.

Here’s how we’ll convert your visitors into buyers:

  • We’ll conduct A/B or even multivariate tests on your eCommerce website, thus eliminating guesswork in determining how to increase those conversion rates.
  • We’ll perform on-site and off-site web analytics to gain a deeper understanding of web usage to aid in our optimisation operations.
  • Through our expertise in copywriting, graphics and web designing, UI designing, and website QA, we can enhance and fine tune your site to give each visitor a uniquely engaging browsing experience.
  • We can also integrate CRM (Customer Relationship Management) systems so that you’ll have the technical advantage to turn one-time buyers into repeat customers.

Ready to work with Denizon?