Energy Cooperation Mechanisms in the EU

While the original mission of the European Union was to bring countries together to prevent future wars, this has spun out into a variety of other cooperative mechanisms its founders may never have dreamed of. Take energy for example, where the European Energy Directive puts energy cooperation mechanisms in place to help member states achieve the collective goal.

This inter-connectivity is essential because countries have different opportunities. For example, some may easily meet their renewable targets with an abundance of suitable rivers, while others may have a more regular supply of sunshine. To capitalise on these opportunities the EU created an internal energy market to make it easier for countries to work together and achieve their goals in cost-effective ways. The three major mechanisms are

  • Joint Projects
  • Statistical Transfers
  • Joint Support Schemes

Joint Projects

The simplest form is where two member states co-fund a power generation, heating or cooling scheme and share the benefits. This could be anything from a hydro project on their common border to co-developing bio-fuel technology. They do not necessarily share the benefits, but they do share the renewable energy credits that flow from it.

An EU country may also enter into a joint project with a non-EU nation, and claim a portion of the credit, provided the project generates electricity and this physically flows into the union.

Statistical Transfers

A statistical transfer occurs when one member state has an abundance of renewable energy opportunities such that it can readily meet its targets, and has surplus credits it wishes to exchange for cash. It ?sells? these through the EU accounting system to a country willing to pay for the assistance.

This aspect of the cooperative mechanism provides an incentive for member states to exceed their targets. It also controls costs, because the receiver has the opportunity to avoid more expensive capital outlays.

Joint Support Schemes

In the case of joint support schemes, two or more member countries combine efforts to encourage renewable energy / heating / cooling systems in their respective territories. This concept is not yet fully explored. It might for example include common feed-in tariffs / premiums or common certificate trading and quota systems.

Conclusion

A common thread runs through these three cooperative mechanisms and there are close interlinks. The question in ecoVaro?s mind is the extent to which the system will evolve from statistical support systems, towards full open engagement.

Check our similar posts

A Business Case for Sharing

We blogged about sharing services in a decentralised business context recently, and explained why we think why these should be IT-Based for speedy delivery. This is not to say that all shared services projects worldwide have been resounding successes. This is often down to the lack of a solid business case up front. We decided to lay out the logic behind this process.

Management Overview ? The overview includes a clear definition of why the current situation is unacceptable, the anticipated benefits of sharing, and an implementation plan were it to go ahead. The project should not proceed until the stakeholders have considered and agreed on this.

Alternatives Considered ? The next stage is to get closer to the other options in order to determine whether an alternative might perhaps be preferable. Substitutes for shared services are often doing nothing, improving the current method, and outsourcing the service to a third party.

The Bottom Line in Business ? Sharing services comes at an initial cost of infrastructure changes, and the impact on human capital (the latter deserves its own blog). The following need careful consideration from the financial angle:

Numbers to Work Through

  • Manpower to design and roll the project out in parallel with the existing organisation.
  • Capital for creating facilities at the central point including civil works, furniture and equipment and IT infrastructure.
  • The costs of travel, feeding and accommodation. These can be significant depending on the time that implementation takes.
  • The opportunity loss of diverting key staff – and the cost of temporary replacements – if appointing line staff to the project team.
  • Crystal-clear project metrics including (a) the direct, realisable savings (b) the medium and long-term effects on profit and (c) where to deploy the savings

Risk Management

Shared services projects don’t go equally smoothly, although planning should reduce the risk to manageable levels. Nonetheless it is important to imagine potential snags, decide how to mitigate them and what the cost might be.

We believe in implementing shared services on a pilot basis in the business unit that eventually provides them. We recommend building these out to other branches only when new processes are working smoothly.

Moving On From a Decision

We recommend you revisit your management overview, the logic behind it, the assumptions you made, and the costs and benefits you envisage before deciding to go ahead

The final step in proving a business case is doable should be fleshing out your roadmap into a detailed operations plan with dependencies on a spreadsheet.

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Spreadsheet Fraud

To any company executive or business owner, the mere possibility of fraud can be enough to send alarm bells ringing – for good reason. In a prolonged recession, the last thing investors would want to discover is a huge, gaping hole where supposedly a neat profit should have been. Also to find out that such loss was brought about by deliberately falsified accounting and poor spreadsheet controls only makes the situation even more regrettable.

Why?

Because these losses would not have occurred had there been a stronger risk management program in place and more stringent quality control on critical data to begin with.

But given the nature of a spreadsheet system i.e. its sheer flexibility and easy accessibility, plus the fact that they were never intended to be enterprise-level tools, there are no hard and fast rules for auditing spreadsheets. Also because of the lack of internal controls for end user computing (EUC) applications, in this case spreadsheets, you can’t expect these systems to yield consistently accurate results.

In fact, most managers assume that major spreadsheet errors should result in figures that are blatantly out of touch with how things stand in the real world, making these errors easily detectable.

Well they assumed wrong. You’ll find cases where the losses ran to millions of dollars without anyone being the wiser.

In instances of fraud, the problem becomes more complicated as these errors are deliberately hidden and cleverly disguised, perhaps one erroneous cell at a time. Even if these cover-ups started out with smaller figures that may have had negligible impact on a company?s operation, the cumulative costs of these ?insignificant? errors multiply exponentially as the spreadsheets are reused and utilised as bases for other related reports.

While there is no generally accepted definition of the term ?spreadsheet fraud?, its quite easy to identify one when a case crops up. Fraud arising from spreadsheets are typically characterised by:

Fallacious inputs – correct figures are deliberately replaced with false values.

Erroneous outputs owing to data alteration – hyperlinks are linking to the wrong spreadsheets or cells; use of macros or special lines of code which are understandable only to the person who developed the code.

Concealment of critical information – can be done with easy ?tweaks? such as hidden rows and columns, using the same colour for both the font and the background, or hard coding additional values into a cell.

There is nothing really highly-sophisticated or technical in any of these methodologies. But without internal spreadsheet controls in place, it would take a discerning eye and a thorough review to catch the inconsistencies contained in a spreadsheet fraught with errors. Also, if these errors are knowingly placed there, the chances of finding them are close to nil.

Learn more about our server application solutions and discover a better way to protect your company from spreadsheet fraud.

More Spreadsheet Blogs


Spreadsheet Risks in Banks


Top 10 Disadvantages of Spreadsheets


Disadvantages of Spreadsheets – obstacles to compliance in the Healthcare Industry


How Internal Auditors can win the War against Spreadsheet Fraud


Spreadsheet Reporting – No Room in your company in an age of Business Intelligence


Still looking for a Way to Consolidate Excel Spreadsheets?


Disadvantages of Spreadsheets


Spreadsheet woes – ill equipped for an Agile Business Environment


Spreadsheet Fraud


Spreadsheet Woes – Limited features for easy adoption of a control framework


Spreadsheet woes – Burden in SOX Compliance and other Regulations


Spreadsheet Risk Issues


Server Application Solutions – Don’t let Spreadsheets hold your Business back


Why Spreadsheets can send the pillars of Solvency II crashing down

?

Advert-Book-UK

amazon.co.uk

?

Advert-Book-USA

amazon.com

Ready to work with Denizon?