Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

The Rights of Individuals Under The General Data Protection Regulation

The General Data Protection Regulation or GDPR is a European Union law reinforcing the rights of citizens concerning the confidentiality of their information, and confirming that they own it. We thought it would be interesting to examine the GDPR effective 25 May 2018 from an Irish citizen?s perspective. This article is a summary of information on the Data Protection Commissioner?s website, but as viewed through a businessperson?s lens.

How the Office Defines Data Protection

The Office believes that organisations receiving personal details have a duty to keep them private and safe. This applies inter alia to information that individuals supply to government, financial institutions, insurance companies, medical providers, telecoms services, and lenders. It also applies to information provided when they open accounts.

This information may be on paper, on computers, or in video, voice, or photographic records. The true owners of this information, the individuals have a right:

  • To make sure that it is factually correct
  • To the assurance that it is shared responsibly
  • That all with access only use it for stated purposes

Any organisation requesting personal information must state who they are, what the information is for, why they need to have it, and to whom else they may provide it.

Consumer Rights to Access Their Personal Information

Private persons have a right under the GDPR to a copy of all their information held or processed by a business. The regulation refers to such businesses as ?data controllers? as opposed to owners, which is interesting. They have to provide both paper and digital data, and ‘related information?.

Data controller fees for this are discretionary within limits. The request may be denied under certain circumstances. The data controller may release information about children to parents and guardians, only if it considers a minor too young to understand its significance. Other third parties such as attorneys must prove they have consent.

Consumer Rights to Port Their Data to Different Services

Since the personal information belongs to the individual, they have a right not only to access it, but also to copy or move it from one digital environment to another. The GDPR requires this be ?in a safe way, without hindrance to usability?. An application could be a banking client that wants to upload their transaction history to a third party price comparison website.

However, the right to data portability only applies to data originally provided by the consumer. Moreover, an automated method must be available for porting. Data controllers must release the information in an open format, and may not charge for the porting service.

Consumer Rights to Complain About Personal Data Abuse

Individuals have a right under the General Data Protection Regulation to have their information rectified if they discover errors. This right extends to an assurance that third parties know about the changes – and who these third party entities are. Data controllers must respond within one month. If they decline the request, they must inform the complainant of their right to further remedial action.

If a data controller refuses to release personal information to the owner, or to correct errors, then the Data Protection Office has legal power to enforce the consumer?s rights. The complainant must make full disclosure of the history of their complaint, and the steps they have taken themselves to attempt to set things right.

Further Advice on Getting Things Ready for 25 May 2018

The General Data Protection Regulation has the full force of law from 25 May 2018 onward, and supersedes all applicable Irish laws, regulations, and policies from that date. We recommend incorporating rights of data owners who are also your customers into your immediate plans. We doubt that forgetting to do so will cut much sway with the Data Commissioner. Remember, you have one month to respond to consumer requests, and only one more month to close things out subject to the matter being complex.

How Bombardier Inc. scored a Bulls Eye

When travelling anywhere in the world on land, sea or air, chances are, you will travel courtesy of something made by aerospace and transportation company Bombardier based in Montreal, Canada. In 2009, it set itself the goal of carbon neutrality by 2020. In other words, it hoped to remove as much carbon dioxide from the atmosphere as it was putting in.

By 2012, Bombardier concluded it was not going to become carbon neutral by 2020 at its current rate of progress. It discounted purchasing carbon offsets because it believed it would serve its interests better by introducing new energy-saving products to market faster. That way, it would achieve its objectives vicariously through the decisions of its customers. But that was not all that forward-thinking Bombardier did. It also set itself the following inward-facing objectives:

  • Reduce carbon footprint through efficient use of energy and less emissions
  • Involve the Bombardier workforce to raise awareness of behaving responsibly
  • Implement sustainable initiatives to further reduce the company carbon footprint

Specific Examples

At its Wichita site, Bombardier (a) fitted a white roof and insulation reducing summer energy consumption by 40%, (b) added an energy recovery wheel to balance air circulation, and (c) introduced skylights with integrated controllers to lower energy consumption by lighting.

At Mirabel, it enhanced the flue-gas management system by adding a pressure differential damper.

At Belfast, Bombardier (a) optimised HVAC systems to reduce pressure on chilling and air-handling plants, (b) installed solar panels on the roof, and (c) obtained approval for a waste-to-energy plant that will convert 120,000 tonnes of non-recyclable waste material annually.

By the end of 2013, Bombardier had already beaten its immediate targets by:

  • Reducing energy consumption by 11% against 2009
  • Reducing greenhouse gas emission by 23% against 2009
  • Reducing water consumption by 6% against 2012

Future Plans

Bombardier will never stop striving to reach its goal of carbon neutrality by 2020. It has a number of other projects in the pipeline waiting for scarce resources to fund them. During 2014, it continued with energy efficient upgrades at its French, Hungarian, Polish, Swiss, and UK plants.

These include consumption monitoring systems, LEDs for workshop lighting, new heating systems, and outdoor energy-saving tower lighting. The monitoring is important because it helps Bombardier focus effort, and provides measured proof of progress.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Is Your Project Agile, a Scrum or a Kanban?

Few projects pan out the way we expect when starting out. This is normal in any creative planning phase. We half suspect the ones that follow a straight line are the exceptions to the rule. Urban legend has it; Edison made a thousand prototypes before his first bulb lit up, and then went on to comment, ?genius is 1% inspiration, 99% perspiration?. Later, he added that many of life’s failures are people who did not realise just how close they were to success when they gave up.

So be it to this day, and so be it with project planning too. There is no one size fits all approach when it comes to it. Agile, Scrum and Kanban each have their supporters and places where they do well. Project planning often works best when we use a sequential combination of them, appropriate to what is currently happening on the ground.

Of the three, Agile is by far the most comprehensive. It provides a structure that begins with project vision / conceptualisation, and goes as far as celebration when the job is over, and retrospective discussion afterwards. However, the emphasis on daily planning meetings may dent freethinking, and even smother it.

Scrum on the other hand says ?forget all that bureaucracy?. There is a job to do and today is the day we are going to do it. Although the core Agile teamwork is still there it ignores macro project planning, and could not be bothered with staying in touch with customers. If using Scrum, it is best to give those jobs to someone else.

The joker in the pack is Kanban, It believes that rules are there to substitute for thought, and that true progress only comes from responsible freedom. It belongs in mature organisations that have passed through Scrum and Agile phases and have embarked on a voyage towards perfection.

That said, there can be no substitute for human leadership, especially when defined as the social influence that binds the efforts of others towards a single task.

Ready to work with Denizon?