Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Transformation to a process based organisation

Today’s global marketplace rewards nimble organisations that learn and reinvent themselves faster than their competition. Employees at all levels of these organisations see themselves as members of teams responsible for specific business processes, with performance measures tied to the success of the enterprise. As team members, they are “owners” of the process (or processes) to which they are assigned. They are responsible for both the day to day functioning of their process(s), and also for continuously seeking sustainable process improvements.

Transforming a traditionally designed “top down control” enterprise to a process-based organisation built around empowered teams actively engaged in business process re-engineering (BPR) has proven more difficult than many corporate leaders have expected. Poorly planned transformation efforts have resulted in both serious impacts to the bottom line, and even more serious damage to the organisation’s fabric of trust and confidence in leadership.

Tomislav Hernaus, in a publication titled “Generic Process Transformation Model: Transition to Process-based Organisation” has presented an overview of existing approaches to organisational transformation. From the sources reviewed, Heraus has synthesised a set of steps that collectively represent a framework for planning a successful organisational change effort. Key elements identified by Hernaus include:

Strategic Analysis:

The essential first step in any transformation effort must be development of a clear and practical vision of a future organisation that will be able to profitably compete under anticipated market conditions. That vision must be expected to flex and adjust as understanding of future market conditions change, but it must always be stated in terms that all organisational members can understand.

Identifying Core Business Processes:

With the strategic vision for the organisation in mind, the next step is to define the core business processes necessary for the future organisation to function. These processes may exist across the legacy organisation’s organisational structures.

Designing around Core Processes:

The next step is development of a schematic representation of the “end state” company, organised around the Core Business Processes defined in the previous step.

Transitional Organisational Forms/ Developing Support Systems:

In his transformation model, Hernaus recognises that information management systems designed for the legacy organisation may not be able to meet the needs of the process management teams in the new organisation. Interim management structures (that can function with currently available IT system outputs) may be required to allow IT professionals time to redesign the organisation’s information management system to be flexible enough to meet changing team needs.

Creating Awareness, Understanding, and Acceptance of the Process-based Organisation:

Starting immediately after the completion of the Strategic Analysis process described above, management must devote sufficient resources to assure that all organisation members, especially key managers, have a full understanding of how a process-based organisation functions. In addition, data based process management skills need to be provided to future process team members. It is not enough to schedule communication and training activities, and check them off the list as they are completed. It is critical that management set behavioural criteria for communication and training efforts that allow objective evaluation of the results of these efforts. Management must commit to continuing essential communication and training efforts until success criteria are achieved. During this effort, it may be determined that some members of the organisation are unlikely to ever accept the new roles they will be required to assume in a process-based organization. Replacement of these individuals should be seen as both an organisational necessity and a kindness to the employees affected.

Implementation of Process Teams:

After the completion of required training AND the completion of required IT system changes, process teams can be formally rolled out in a planned sequence. Providing new teams with part time support by qualified facilitators during the firsts weeks after start-up can pay valuable long term dividends.

Team Skill Development and Continuous Process Improvement:

Providing resources for on-going skill development and for providing timely and meaningful recognition of process team successes are two keys for success in a process-based organisation. Qualified individuals with responsibility for providing training and recognition must be clearly identified and provided with sufficient budgetary resources.

The Hernaus model for transformation to a process based organisation is both well thought out and clear. His paper provides an ample resource of references for further study.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
How Armstrong World Industries is going Cradle-to-Cradle

The Cradle-to-Cradle concept holds that human effort must be biometric, in other words enrich the environment within which it functions as opposed to breaking it down. This means manufacturing must be holistic in the sense that everything is reusable and nothing is destroyed. Armstrong World Industries was the first global mineral ceiling tile manufacturer to achieve Cradle-to-Cradle certification. We decided to take a closer look at how they achieved this.

Armstrong Worldwide Industries has five plants in the UK alone. These produce an annual turnover of ?2.7 billion. They have been making ceilings for more than 150 years. Fifteen years ago and way ahead of the curve it started recycling, and has maintained a policy of not charging contractors for waste ever since. Along the way, it developed a product that can be re-used indefinitely.

The Challenge

Going green must also be commercially sustainable. In Armstrong?s case, it faced a rise in landfill tax from ?8 per tonne per year to ?80 per tonne per year. This turned the financial cost of waste from a nuisance to a threat. It calculated that recycling one tonne of ceiling materials would:

  • Eliminate 456kg of CO2 equivalents by saving 1,390 kWh of electricity
  • Preserve 11 tons of virgin material and save 1,892 gallons of potable water

They hoped to extend their own recycling project by asking demolition and strip-out contractors to join it, so they could reprocess their scrap as new batches of tiles too.

The Achievement

As things stand today, an Armstrong ceiling tile now contains an average of 82% recycled content. Indeed, if they could find more ceilings to recycle this could reach 100%. In the past two years alone, Armstrong Worldwide Industries UK has saved 130,399m? of greenfield from landfill, being the equivalent of 520 skips that would otherwise have cost contractors over ?88,000 to dispose of.

The Broader Context

Armstrong Worldwide Industries is a global leader in water management, and is bent on minimising its reliance on fossil for energy. It has implemented online measurement systems that feed data to its corporate environmental, health and safety system. This empowers it to produce reports, track corrective actions and measure progress towards its overall goal of being carbon neutral.

Next time you sit beneath an Armstrong Worldwide Industries panelled ceiling, spare a thought for how much ecoVaro consumption analytics could contribute to your bottom line (and how it would feel to be lighter on carbon too).

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Energy efficiency demystified

Energy bills are all about Energy efficiency but energy efficiency management is not all about bills. Energy efficiency means reducing carbon emissions, lowering energy costs and improving the quality of life. Energy efficiency is therefore about conservation of energy in a broader perspective; in fact energy efficiency is almost becoming a moral obligation.

Through adoption of appropriate energy efficiency measures, companies can significantly bring down the overhead costs making hundreds of dollars in savings. Energy efficiency is also synonymous with a better quality of life. Taking appropriate measures to ensure proper insulation protects your premises against extreme weather conditions leading to more productivity and an improvement in the bottom line.

Improved energy efficiency means a smaller amount of carbon emissions, less pollution and a better environment.

It is now easier than ever to visually identify where your facility is wasting energy, how much energy is being wasted while tracking the progress made in reducing energy consumption by turning that detailed, raw energy-consumption data into useful charts and figures.

Having visibility of your Energy usage gives you knowledge of what power you are consuming. This helps you change energy usage behaviours and this can have significant savings and reduction in your electricity bills. Real-time electricity consumption tracking is enough prodding for you to be on the lookout for inefficient energy consumption unit’s e.g.? Heating and cooling equipment, ducts insulation of your premises or a failure of one of these components to perform as intended. Pin-pointing the problem areas is not a walk in the park but fixing it can make your building more energy-efficient and comfortable.

A wide range of solutions are now available for charting and analysing energy consumption that helps energy managers, facilities managers, energy consultants and building-services engineers. These will not only offer advice but will enable you provide tailor made solutions for your organisation by assisting you in developing a sustainable energy strategy. Our energy monitoring software is one example.?

Ready to work with Denizon?