Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

2015 ESOS Guidelines Chapter 2 – Deadlines and Status Changes

The ESOS process is deadline driven and meeting key dates is a non-negotiable. The penalties for not complying / providing false or misleading information are ?50,000 each. Simply not maintaining adequate records could cost you ?5,000. The carrot on the end of the stick is the financial benefits you stand to gain.

Qualifying for inclusion under the ESOS umbrella depends on the status of your company in terms of employee numbers, turnover and balance sheet on 31 December 2014. Regardless of whether you meet the 2014 threshold or not, you must reconsider your situation on 31 December 2018, 2022 and 2026.

Compliance Period Qualification Date Compliance Period Compliance Date
1 31 December 2014 From 17 July 2014* to 5 December 2015 5 December 2015
2 31 December 2018 From 6 December 2015 to 5 December 2019 5 December 2019
3 31 December 2022 From 6 December 2019 to 5 December 2023 5 December 2023
4 31 December 2026 From 6 December 2023 to 5 December 2027 5 December 2027

Notes:

1. The first compliance period begins on the date the regulations became effective

2. Energy audits from 6 December 2011 onward may go towards the first compliance report

Changes in Organisation Status

If your organisation status changes after a qualification date when you met compliance thresholds, you are still bound to complete your ESOS assessment for that compliance period. This is regardless of any change in size or structure. Your qualification status then remains in force until the next qualification date when you must reconsider it.

FUJIFILM Cracks the Energy Code

FUJIFILM was in trouble at its Dayton, Tennessee plant in 2008 where it produced a variety of speciality chemicals for industrial use. Compressed-air breakdowns were having knock-on effects. The company decided it was time to measure what was happening and solve the problem. It hoped to improve reliability, cut down maintenance, and eliminate relying on nitrogen for back-up (unless the materials were flammable).

The company tentatively identified three root causes. These were (a) insufficient system knowledge within maintenance, (b) weak spare part supply chain, and (c) generic imbalances including overstated demand and underutilised supply. The maintenance manager asked the U.S. Department of Energy to assist with a comprehensive audit of the compressed air system.

The team began on the demand side by attaching flow meters to each of several compressors for five days. They noticed that – while the equipment was set to deliver 120 psi actual delivery was 75% of this or less. They found that demand was cyclical depending on the production phase. Most importantly, they determined that only one compressor would be necessary once they eliminated the leaks in the system and upgraded short-term storage capacity.

The project team formulated a three-stage plan. Their first step would be to increase storage capacity to accommodate peak demand; the second would be to fix the leaks, and the third to source a larger compressor and associated gear from a sister plant the parent company was phasing out. Viewed overall, this provided four specific goals.

  • Improve reliability with greater redundancy
  • Bring down system maintenance costs
  • Cut down plant energy consumption
  • Eliminate nitrogen as a fall-back resource

They reconfigured the equipment in terms of lowest practical maintenance cost, and moved the redundant compressors to stations where they could easily couple as back-ups. Then they implemented an online leak detection and repair program. Finally, they set the replacement compressor to 98 psi, after they determined this delivered the optimum balance between productivity and operating cost.

Since 2008, FUJIFILM has saved 1.2 million kilowatt hours of energy while virtually eliminating compressor system breakdowns. The single compressor is operating at relatively low pressure with attendant benefits to other equipment. It is worth noting that the key to the door was measuring compressed air flow at various points in the system.

ecoVaro specialises in analysing data like this on any energy type.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
How to create a custom form with Field Elite

A common requirement for most Field Service Workers is to complete various forms and paper based inspection checklists when visiting customer sites and remote area locations.  Often the data collected is often used in collaboration efforts across multiple teams and organisations. 

Using paper forms, binders, cameras, and filing cabinets can make this process complicated, frustrating, and often, near impossible.

If you consider that, even though we are entering the third decade of the new millennium and despite the proliferation of Smart Phones and Tablet computing an incredibly large percentage of field service teams are still making use of paper based systems!

Read more about the benefits of digital forms data collection

Field Elite Customised forms

Field Elite enables Field Service organisations to easily create their own customised forms which can be attached jobs. 

The creation of forms can be done using the Web Based Administration Portal which is provided as standard to all customers when signing up for an account.

To access the form builder from Side Navigation navigate Settings –> Form Templates –> Create Form


You will then be presented with Form Builder utility which will contain an Empty Default Form and a list of fields types you are able to insert.

There are a variety of fields you can use to create all manner of forms. There is no restriction on the number of fields or field types you can choose to create forms suitable for your purpose.

If you can think it you can create it

In the example, we’ll work through, we are going to create a Simple Conference Room Inspection  Report, to be used by Facility Managers to assist in carrying room inspection reports for conference centres.

To add fields to your form simply Drag and Drop the fields onto the form.

Once you have completed adding which fields you require to your form and you are satisfied with the layout.

Select Settings tab to provide a meaningful name for your form.

You can also select a Form Layout you wish for your form.  For the purpose of this post we are going to leave it as Vertical.

Once you are satisfied with your form you can select Save Form 


Once your form has been saved it will be available for selection when defining jobs in the system.

Summary

It is really easy to define custom forms using the Field Elite from templates module.  The Form Template module enables you to create any manner of forms your organisation may require.

Ready to work with Denizon?