Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Benefits Realisation Frameworks – A Useful Handle

One of the greatest challenges of project management is maintaining top-down support in the face of fluctuating priorities. If you elect to take on the role yourself and are peppered by other priorities, it can be a challenge to exactly remember why you are changing things and what your goals are. Sometimes you may not even notice you have reached your goal.

The Benefits Realisation Chart-room

The Benefits Realisation Model is a framework on which to hang key elements of any project. These traditionally include the following, although yours may not necessarily be the same:

  • Definition of the project goal
  • Quantification of intended benefits
  • Project plan versus actual progress
  • How you know you reached your goal
  • Quantification of actual benefits

Another way of describing Benefits Realisation Frameworks is they answer four fundamental questions that every project manager should know by heart:

  • What am I going to do?
  • How am I going to do it?
  • When will I know it’s done?
  • What exactly did I achieve?

The Benefits Realisation Promise

An astounding number of projects fail to reach completion, or miss their targets. It’s not for nothing that the expression ?after the project failed the non-participants were awarded medals? is often used in project rooms. We’re not saying that it is a panacea for success. However it can alert you to warnings that your project is beginning to falter in terms of delivering the over-arching benefits that justify the effort.

When Projects Wander Off-Target

Pinning blame on participants is pointless when project goals are flawed. For example, the goals may be entirely savings-focused and not follow through on what to do with the windfall. At other times realisation targets may be in place, but nobody appointed to recycle the benefits back into the organisation. This is why a Benefits Realisation Framework needs to look beyond the project manager?s role.

Realisation Management in Practice

If the project framework does not look beyond the project manager?s role, then it is over when it reaches its own targets ? and can even run the risk of being an event that feeds entirely off itself. In order to avoid a project being a means to its own end, this first phase must culminate with handover to a benefits realisation custodian.

An example of this might be a project to centralise facilities that is justified in terms of labour savings. The project manager?s job is to build the structure. Someone else needs to rationalise the organisation.

In conclusion, the Benefits Realisation Framework is a useful way of ensuring a project does not only achieve its internal goals, but also remains a focus of management attention because of its extended, tangible benefits.

How Energy Conservation saved Fambeau River Paper

Rising energy costs caught this Wisconsin paper mill napping, and it soon shut down because it was unable to innovate. Someone else bought it and turned it around by measuring, modifying, monitoring and listening to people.

The Fambeau River Paper Mill in Prince County, Wisconsin USA employed 13% of the city?s residents until rising energy costs shut it down in 2006. Critics wrote it off as an energy dinosaur unable to adapt. But that was before another company bought it out and resuscitated it as a fleet-footed winner.

Its collapse was a long time coming and almost inevitable. Wisconsin electricity prices had grown a third since 1997, the machinery was antiquated and the dependence on fossil power absolute. So what did the new owners change, and is there anything we can learn from this?

The key to understanding what suddenly went right was the new owners? ability to listen. They requested a government Energy Assessment that suggested a number of small step changes that took them where they needed to go in terms of energy saving. These included enhancements in steam systems and fuel switch modifications. However they needed more than that.

The second game changer was tracking down key members of the old workforce and listening to them too. This combination enabled them to finally hire back 92% of the original labour force under the same terms and conditions – and still make a profit (the other 8% had moved on elsewhere or retired). The combined energy savings produced a payback plan of 5.25 years. Three years into the project their capital investment of $15 million had already clawed back the following electricity savings.

  • Evaporator Temperature Control $2,245,000
  • Hot Water Heat Recovery $2,105,000
  • Paper Machine Devronisers $1,400,000
  • Increased Boiler Output $1,134,000
  • Paper Machine Modifications; $761,000
  • Motive Air Dryer $610,000
  • Accumulator Savings $448,000
  • Densified Fuels Plant $356,000

In terms of carbon dioxide produced, the Fambeau River Paper Mill?s contribution dropped from 1 ton to 600 pounds.

How well do you know where your company?s energy spend is concentrated, and how this compares with your industry average; could you be doing better if you innovated, and by how much? Get these questions answered by asking ecoVaro how easy it could be to get on top of your carbon metrics. This could cost you a phone call and a payback on it so rapid it’s not worth stopping to calculate.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
9 Cloud Security Questions you need to ask Service Providers

Companies in Ireland and the UK who are considering cloud adoption might already have a general idea of the security risks inherent in cloud computing. However, since different providers may not offer the same levels of risk mitigation, it is important to know which providers can give sufficient assurance on cloud security.

Here are 10 cloud security questions to ask service providers vying for your attention.

1. Where will my data be located?

There are a variety of reasons why you will want to ask this question. One big reason is that there are certain countries that don’t have strict legislation (or any legislation at all) pertaining to cloud computing. In that case, the provider won’t be as motivated to apply high levels of risk mitigation.

So if your data is hosted off shore, then you might want to reconsider or at least conduct a deeper study regarding the security conditions there.

2. Do you have provisions for regulatory compliance?

Certain standards and regulations (e.g. PCI DSS and possibly the EU Data Protection Directive) have specific guidelines pertaining to data stored in the cloud. If your organisation is covered by any of these legislation, then you need to know whether your provider can help you meet requirements for compliance.

3. Who will have access to my data?

In a cloud environment, where your data is going to be managed by people who aren’t under your direct supervision, you’ll have to worry as much about internal threats as you would with external threats.

Therefore, you need to know how many individuals will have access to your data. You also need to know relevant information such as how admins and technicians with data access rights are screened prior to getting hired. You also need to determine what access controls are being implemented.

4. How is data segregated?

Since there will be other clients, you will want to know how your data is going to be segregated from theirs. Is there any possibility of an accidental or intentional data breach due to poor data segregation? Find out if your data is going to be encrypted and how strong the encryption algorithm is.

5. How will you support investigative activities?

Sometimes, even if strong cloud security measures are in place, a data breach can still happen. If it does happen, the provider should have ways to track each user/administrator’s activity that can sufficiently support a detailed data forensics investigation.

Find out whether logs are being kept and how detailed they are.

6. Are we protected by a Disaster Recovery/Business Continuity plan? How?

Don’t be fooled by sales talk of 100% up-time. Even the most robust cloud infrastructures can suffer outages too. But the important thing is that, when they do fail, they should be able to get up and running in the soonest time possible.

Don’t just ask about their guaranteed RPOs and RTOs. Find out whether your data and applications will be replicated across multiple sites. Unless the provider says they will be, you need to find a provider with a better infrastructure.

7. Can I get copies of my VMs?

In a cloud infrastructure, your servers are actually in the form of files known as virtual machines (VMs). Because VMs are just files, they should be easily copied. There may be issues though, like the VMs might be stored in a not-so-popular proprietary format. Another possible issue is that the provider may simply not allow copying.

Having copies of your VMs can be useful should you later on decide to transfer to another provider or even duplicate your cloud infrastructure on your own.

8. What will happen to my data when I scale down?

One outstanding benefit of cloud computing is that when your business demands drop, you can easily scale down computing resources and reduce your cloud spending. ?But what will happen to your data when you decommission virtual servers? Will they be discarded?

You might want your data to be retained up to a certain period. On the other hand, you might also want them to be deleted immediately. Ask about the provider’s data deletion/data retention policies and see if they are in line with yours.

9. What will happen to my data if I decide to close my account?

There might come a time when you’ll want to terminate your contract with your cloud provider. Just like in issue #8, you’ll want to find out more about data deletion/data retention policies.

Although some providers can give you detailed answers, many of these answers can include a lot of technical jargon that can leave you totally confused. If you want someone you can trust to:

  • simplify those answers;
  • help you pick the right cloud service provider, and
  • even make sure cloud security is really upheld once your cloud engagement is ?under way

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?