Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

A Small External Enterprise Development Team is Cheaper than Your Own

Time is money in the application development business. We have to get to market sooner so someone else does not gazump us, and pip us at the post. We increase the likelihood of this with every delay. Moreover, the longer your in-house team takes to get you through the swamp, the higher the project cost to you.

Of course, in theory this should not be the case. Why bring in a team from outside, and pay more to support their corporate structure? Even going for a contract micro team ought not to make financial sense, because we have to fund their mark-up and their profit taking. Our common sense tells us that this is crazy. But, hold that thought for a minute. What would you say if a small external enterprise development team was actually cheaper? To achieve that, they would have to work faster too.

The costs of an Enterprise Internal Development Team

Even if you were able to keep your own team fully occupied ? which is unlikely in the long term ? having your own digital talent pool works out expensive when you factor in the total cost. Your difficulties begin with the hiring process, especially if you do not fully understand the project topic, and have to subcontract the hiring task.

If you decide to attempt this yourself, your learning curve could push out the project completion date. Whichever way you decide to go, you are up for paying advertising, orientation training, technical upskilling, travel expenses, and salaries all of which are going to rob your time. Moreover, a wrong recruitment decision would cost three times the new employee?s annual salary, and there is no sign of that changing.

But that is not all, not all by far. If want your in-house team to keep their work files in the office, then you are going to have to buy them laptops, plus extra screens so they can keep track of what they are doing. Those laptops are going to need desks, and those employees, chairs to sit in. Plus, you are going to need expensive workspace with good security for your team?s base.

If we really wanted to lay it on, we would add software / cloud costs, telephony, internet access, and ongoing technical training to the growing pile. We did a quick scan on PayScale. The median salary of a computer programmer in Ireland is ?38,000 per year and that is just the beginning. If you need a program manager for your computer software, their salary will be almost double that at ?65,000 annually.

Advantages of R&D outsourcing

The case for a small externally sourced enterprise development team revolves around the opportunity cost ? or loss to put in bluntly ? of hiring your own specialist staff for projects. If you own a smaller business with up to 100 people, you are going to have to find work for idle digital fingers, after you roll out your in-house enterprise project. If you do not, you head down the road towards owning a dysfunctional team lacking a core, shared objective to drive them forward.

Compared to this potential extravagance, hiring a small external enterprise development team on an as-needed basis makes far more sense. Using a good service provider as a ?convenience store? drives enterprise development costs down through the floor, relative to having your own permanent team. Moreover, the major savings that arise are in your hands and free to deploy as opportunities arise. A successful business is quick and nimble, with cash flow on tap for R & D.

How Armstrong World Industries is going Cradle-to-Cradle

The Cradle-to-Cradle concept holds that human effort must be biometric, in other words enrich the environment within which it functions as opposed to breaking it down. This means manufacturing must be holistic in the sense that everything is reusable and nothing is destroyed. Armstrong World Industries was the first global mineral ceiling tile manufacturer to achieve Cradle-to-Cradle certification. We decided to take a closer look at how they achieved this.

Armstrong Worldwide Industries has five plants in the UK alone. These produce an annual turnover of ?2.7 billion. They have been making ceilings for more than 150 years. Fifteen years ago and way ahead of the curve it started recycling, and has maintained a policy of not charging contractors for waste ever since. Along the way, it developed a product that can be re-used indefinitely.

The Challenge

Going green must also be commercially sustainable. In Armstrong?s case, it faced a rise in landfill tax from ?8 per tonne per year to ?80 per tonne per year. This turned the financial cost of waste from a nuisance to a threat. It calculated that recycling one tonne of ceiling materials would:

  • Eliminate 456kg of CO2 equivalents by saving 1,390 kWh of electricity
  • Preserve 11 tons of virgin material and save 1,892 gallons of potable water

They hoped to extend their own recycling project by asking demolition and strip-out contractors to join it, so they could reprocess their scrap as new batches of tiles too.

The Achievement

As things stand today, an Armstrong ceiling tile now contains an average of 82% recycled content. Indeed, if they could find more ceilings to recycle this could reach 100%. In the past two years alone, Armstrong Worldwide Industries UK has saved 130,399m? of greenfield from landfill, being the equivalent of 520 skips that would otherwise have cost contractors over ?88,000 to dispose of.

The Broader Context

Armstrong Worldwide Industries is a global leader in water management, and is bent on minimising its reliance on fossil for energy. It has implemented online measurement systems that feed data to its corporate environmental, health and safety system. This empowers it to produce reports, track corrective actions and measure progress towards its overall goal of being carbon neutral.

Next time you sit beneath an Armstrong Worldwide Industries panelled ceiling, spare a thought for how much ecoVaro consumption analytics could contribute to your bottom line (and how it would feel to be lighter on carbon too).

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Disadvantages of Spreadsheets – Obstacles to Compliance in the Healthcare Industry

Most of the regulatory compliance issues we talked about concerning spreadsheets have been related to financial data. But there are other kinds of data that are stored in spreadsheets which may also cause regulatory problems in the future.

In the US, a legislation known as HIPAA or Health Insurance Portability and Accountability Act is changing the way health care establishments and practitioners handle patient records. The HIPAA Privacy Rule is aimed at protecting the privacy of individually identifiable health information a.k.a. protected health information (PHI).

Examples of PHI include common identifiers like a patient’s name, address, Social Security Number, and so on, which can be used to identify the patient. HIPAA covers a wide range of health care organisations and service providers, including: health plan payers, health care clearing houses, hospitals, doctors, dentists, etc.

To protect the confidentiality, integrity, and availability of PHI, covered entities are required to implement technical policies such as access controls, authentication, and audit controls. These can easily be implemented on server-based systems.

Sad to say, many health care organisations who have started storing data electronically still rely on spreadsheet-based systems. Those policies are hard to implement in spreadsheet-based systems, where files are handled by end-users who are overloaded with their main line of work (i.e. health care) and have very little concern for data security.

In some of these systems, spreadsheet files containing PHI may have multiple versions in different workstations. Chances are, none of these files have any access control or user authentication mechanism whatsoever. Thus, changes can easily be made without proper documentation as to who carried out the changes.

And because the files are normally easily accessible, unauthorised disclosures – whether done intentionally or accidentally – will always be a lingering threat. Remember that HIPAA covered entities who are caught disclosing PHI can be fined from $50,000 up to $500,000 plus jail time.

But that’s not all. Through the HITECH Act of 2009, business associates of covered entities will now have to comply with HIPAA standards as well. Business associates are those companies who are performing functions and services for covered entities.

Examples of business associates are accounting firms, law firms, consultants, and so on. They automatically need to comply with the standards the moment they too deal with PHI.

 

More Spreadsheet Blogs

 

Spreadsheet Risks in Banks

 

Top 10 Disadvantages of Spreadsheets

 

Disadvantages of Spreadsheets – obstacles to compliance in the Healthcare Industry

 

How Internal Auditors can win the War against Spreadsheet Fraud

 

Spreadsheet Reporting – No Room in your company in an age of Business Intelligence

 

Still looking for a Way to Consolidate Excel Spreadsheets?

 

Disadvantages of Spreadsheets

 

Spreadsheet woes – ill equipped for an Agile Business Environment

 

Spreadsheet Fraud

 

Spreadsheet Woes – Limited features for easy adoption of a control framework

 

Spreadsheet woes – Burden in SOX Compliance and other Regulations

 

Spreadsheet Risk Issues

 

Server Application Solutions – Don’t let Spreadsheets hold your Business back

 

Why Spreadsheets can send the pillars of Solvency II crashing down

?

Advert-Book-UK

amazon.co.uk

?

Advert-Book-USA

amazon.com

 

Ready to work with Denizon?