Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Month End Accounting the way it should Be Today

Month end accounting has always been a business critical exercise. Without the balance sheet, income statement, and other financial reports this exercise ultimately produces, management could not make informed decisions to keep the company in the right direction and at the ideal operational speed.

Now, in order to maintain optimal business velocity, month end activities have to be carried out as swiftly and as accurately as possible. Delays will only inhibit managers from reacting and effecting necessary adjustments in time. Inaccurate information, on the other hand, obviously lead to bad decisions.

But that’s not all. Never has the month end close been as demanding as it is today. Regulations like the Sarbanes-Oxley Act, Solvency II, Dodd-Frank Act, and others, which call for more stringent controls and more robust risk management practices, are now forcing companies to find better ways to face the end of the month.

Sticking to old month-end practices while striving to achieve regulation compliance can either cost a company more (if they add manpower) or simply bog it down (if they don’t). Among the worst of these practices is the use of spreadsheets.

These User Developed Applications (UDAs) are very susceptible to errors. (See spreadsheet risks)

What’s more, consolidating data from spreadsheets as well as carrying out reconciliations on them is very time consuming. These activities usually require data from outside sources – i.e. a workstation in a different department, building, or (in the case of really large corporations) geographical locations.

Furthermore, if one of these sources fail, the financial reports won’t be complete. This is not a far-fetched scenario, considering that spreadsheet storage and backup is typically carried out by the average end user. This leaves the spreadsheet data vulnerable to hard disk crashes, virus attacks, and unexpected disasters.

Thus, in order to produce accurate financial reports on time all the time, you need a financial/IT solution that offers optimal provisions for risk management, collaboration, backup, and business continuity. Learn about server-based solutions and discover a better way to carry out month end accounting.

Spreadsheet Risk Issues

It is interesting to note that the riskiness of operational spreadsheets are overlooked even by companies with high standards of risk management. Only when errors amount to actual losses do they realize that these risks have been staring them in the face all along.

Common spreadsheet risk issues

Susceptibility to trivial manual errors

Due to the fundamental structure of spreadsheets, a slight change in the formula or value in any of their inhabited cells may already affect their overall output. An

  • accidental copy-paste,
  • omission of a negative sign,
  • erroneous range selection,
  • incorrect data input or
  • unintentional deletion of a character,cell, range, column, or row

are just some of the simple errors spreadsheet users frequently encounter. Rarely are there any counter-checking controls in place in a spreadsheet-based activity and manual errors therefore easily go undetected.

Possibility of the user working on the wrong version

How do you store spreadsheet files?

Since the most common reports are usually generated on a monthly basis, users tend to store them using variations of these two configurations:

spreadsheet storage

If you notice, a user can accidentally work on the wrong version with any of these structures.

Prone to inconsistent company-wide reporting

This happens when a summary or ?final? spreadsheet is fed information by different departments coming from their own spreadsheets. Even if most of the data in their spreadsheets come from one source (the company-wide database), erroneous copy-pasting and linking, or even different interpretations of the same data can result to contradicting information in the end.

Often defenceless against unauthorised access

Some spreadsheets contain information needed by various individuals or department units in an organisation. Hence, they are often shared via email or through shared folders in a network. Now, because spreadsheets don’t normally use any access control, any user can easily open a spreadsheet file and view or modify the contents as he wishes.

Highly vulnerable to fraud

A complex spreadsheet system with zero or very minimal controls provides the perfect setting for would-be fraudsters. Hidden cells with malicious formulas and links to bogus information can go unnoticed for a long time especially if the final figures don’t deviate much from expected values.

Spreadsheet risk mitigation solutions may not suffice

Inherent complexity makes testing and logic inspection very time consuming

Deep testing can uncover possible errors hidden in spreadsheet cells and consequently mitigate risks. But spreadsheets used to support financial reporting are normally large, complex, highly-personalised and, without ample supporting documentation, understandably hard to follow.

No clear ownership of risk management responsibilities

There?s always a dilemma when an organisation starts assigning risk management responsibilities for spreadsheets. IT personnel believe users in the business side of the organisation should be responsible since they are the ones who create, edit, store, duplicate, and share the spreadsheet files. On the other hand, users believe IT should be responsible since they have always been in-charge of managing IT infrastructure, applications, and files.

To get rid of spreadsheet risks, you’ll have to get rid of spreadsheets altogether

One remedy is to have a risk management activity that involves both IT personnel and spreadsheet users. But wouldn’t you want to get rid of the complexity of having to distribute the responsibilities between the two parties instead of just one?

Learn more about Denizon’s server application solutions and how you can get rid of spreadsheet risk issues.

More Spreadsheet Blogs


Spreadsheet Risks in Banks


Top 10 Disadvantages of Spreadsheets


Disadvantages of Spreadsheets – obstacles to compliance in the Healthcare Industry


How Internal Auditors can win the War against Spreadsheet Fraud


Spreadsheet Reporting – No Room in your company in an age of Business Intelligence


Still looking for a Way to Consolidate Excel Spreadsheets?


Disadvantages of Spreadsheets


Spreadsheet woes – ill equipped for an Agile Business Environment


Spreadsheet Fraud


Spreadsheet Woes – Limited features for easy adoption of a control framework


Spreadsheet woes – Burden in SOX Compliance and other Regulations


Spreadsheet Risk Issues


Server Application Solutions – Don’t let Spreadsheets hold your Business back


Why Spreadsheets can send the pillars of Solvency II crashing down

?

Advert-Book-UK

amazon.co.uk

?

Advert-Book-USA

amazon.com

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Total Quality Management

Total Quality Management (TQM) is another business management approach that focuses on the involvement of all members of the organisation to participate in improving processes, products, services, and the culture in which they work in. It is important that every team member realises how each individual and each activity affects, and in turn is affected by, others.

With the use of combined quality and management tools, TQM also aims to reduce losses brought about by wasteful practices, a common concern in most companies. Using the TQM strategy, business would also be able to identify the cause of a defect, thereby preventing it from entering the final product.

Deming’s 14 Points

At the core of the Total Quality Management concept and implementation is Deming’s 14 points, a set of guidelines on quality as conceptualised by W Edwards Deming, one of the pioneers of quality. Deming’s 14 points are as follows:

  1. Create constancy of purpose for improving products and services.
  2. Adopt the new philosophy.
  3. Cease dependence on inspection to achieve quality.
  4. End the practice of awarding business on price alone; instead, minimise total cost by working with a single supplier.
  5. Improve constantly and forever every process for planning, production and service.
  6. Institute training on the job.
  7. Adopt and institute leadership.
  8. Drive out fear.
  9. Break down barriers between staff areas.
  10. Eliminate slogans, exhortations and targets for the workforce.
  11. Eliminate numerical quotas for the workforce and numerical goals for management.
  12. Remove barriers that rob people of pride of workmanship, and eliminate the annual rating or merit system.
  13. Institute a vigorous program of education and self-improvement for everyone.
  14. Put everybody in the company to work accomplishing the transformation.

But if you were to reduce to bare bones the TQM philosophy from Deming’s 14 points, it would all come down to two simple goals:

  1. To make things right the first time; and
  2. To work for continuous improvement.

As with all other quality management process, the end goal is to be able to offer products and services that meet and even exceed customer’s expectations.

Find out more about our Quality Assurance services in the following pages:

Ready to work with Denizon?