Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Are Target Operating Models strategic compasses?

The short answer is they usually are, because every organisation needs a road-map of where they are going. Target operating models can be complex documents with illustrative details including project management structures, special tools, implementation procedures and management metrics. They can also be simple statements, as for example Winston Churchill?s promise that ?we shall fight them on the beaches, on the landing grounds and in the fields? which gave Britain the strategic direction it needed.

Many initiatives unfortunately fail because managers are ?too busy? to bottom on what their target operating model should say, or simply don’t believe in paperwork. As a result, promising initiatives may blunder off course or die a slow death without them really noticing. We cannot manage what we cannot measure, which is where the management metrics fit in. One of my favourite quotes is ?if you don’t know where you are going any road will get you there? which is what the Cheshire Cat said to Alice in Wonderland when she got lost.

The author blundered through life without a plan because there was no one else with his particular brand of imagination. The current business climate is different because everybody is trying to ramp up, and investors want to know exactly what is going to happen to their money and by when. Hence a target operating model can be indispensable throughout a change or product cycle.

The benefits of having a measurable operations / technology plan can produce powerfully tangible results if the organisation follows through on it. Built-in metrics with milestones are powerful tool for management, and, when they map through to the company financial plan almost irreplaceable as cash-flow forecasters.

Other benefits may include:

  • Shorter times to market and greater agility when launching new ideas
  • Reduced investor risk through a predictable process that’s readily monitored
  • A stable operating environment where there is consensus on direction
  • Greater likelihood of delivering on time and leading to repeat orders
  • A more cost-effective process, with less risk of loss of quality and money

Although it dates back a few years the Wills UK and Ireland Retail model still provides an excellent benchmark of a target operating plan that worked. The strategic goals were exceptionally clear, and they brought in a proven project manager to help them drive the program forward.

We have delivered advanced business management services to many of our clients, and believe you will find our personalised approach time-efficient and effective too.

2015 ESOS Guidelines Chapter 1 ? Who Qualifies

The base criteria are any UK undertaking that employs more than 250 people and/or has a turnover in excess of ?50 million and/or has a balance sheet total greater than ?43 million. There is little point in attempting to separate off high polluting areas. If one corporate group qualifies for ESOS, then all the others are obligated to take part too. The sterling equivalents of ?38,937,777 and ?33,486,489 were set on 31 December 2014 and apply to the first compliance period.

Representatives of Overseas Entities

UK registered branches of foreign entities are treated as if fully UK owned. They also have to sign up if any overseas corporate element meets the threshold no matter where in the world. The deciding factor is common ownership throughout the ESOS system. ecoVaro appreciates this. We have seen European companies dumping pollution in under-regulated countries for far too long.

Generic Undertakings that Could Comply

The common factor is energy consumption and the organisation’s type of work is irrelevant. The Environmental Agency has provided the following generic checklist of undertakings that could qualify:

Limited Companies Public Companies Trusts
Partnerships Private Equity Companies Limited Liability Partnerships
Unincorporated Associations Not-for-Profit Bodies Universities (Per Funding)

Organisations Close to Thresholds

Organisations that come close to, but do not quite meet the qualification threshold should cast their minds back to previous accounting periods, because ESOS considers current and previous years. The exact wording in the regulations states:

?Where, in any accounting period, an undertaking is a large undertaking (or a small or medium undertaking, as the case may be), it retains that status until it falls within the definition of a small or medium undertaking (or a large undertaking, as the case may be) for two consecutive accounting periods.?

Considering the ?50,000 penalty for not completing an assessment or making a false or misleading statement, it makes good sense for close misses to comply.

Joint Ventures and Participative Undertakings

If one element of a UK group qualifies for ESOS, then the others must follow suit with the highest one carrying responsibility. Franchisees are independent undertakings although they may collectively agree to participate. If trusts receive energy from a third party that must do an ESOS, then so must they. Private equity firms and private finance initiatives receive the same treatment as other enterprises. De-aggregations must be in writing following which separated ESOS accountability applies.

How Westin Melbourne Hotel Trimmed its Footprint

Becoming sustainable is a three-pronged process. You must save money and push the buttons the government is pressing you to. But there?s a deeper, more urgent issue. If your customers mark you down for not being green enough you are heading for trouble. Let’s see how well this hotel is doing.

The Melbourne flagship of the Westin hotel chain boasts 262 spacious rooms with views of Melbourne Square and surrounding theatres, designer boutiques, galleries and national landmarks. The architects included conference facilities, a wellness centre and sundry bars and restaurants. After climate change arrived to stay, hotel management discovered they had inherited a water and energy-greedy monster. Their solution was to measure what was going through their systems, and then progressively cap the building?s greedy appetite.

The Melbourne Westin Hotel could not have achieved results without these metrics. They began by determining key indicators and measuring them. This provided them with criteria to set achievable, cost effective targets in the following key areas of their business:

  1. Water Management ? Demand-based linen and towel recycling, installation of back-washable water filters, water-saving shower heads, dual-flush toilets.
  2. Waste Management ? Conversion to green products, recycling kitchen oil, moving towards a paperless office, recycling everything possible.
  3. Energy Management ? Energy-efficient light bulbs, standby settings for lights, computers, televisions and air conditioners
  4. Stakeholder Communication ? Staff green-team training, guest education, ongoing employee briefings
  5. Strategic Positioning ? Visible, top-down commitment, optimised carbon offsets from clean, renewable energy sources, clearly stated position in the market

Westin?s Melbourne landmark has made good progress towards becoming the green hotel for others to follow. It has adjusted its environmental policies, increased water and energy awareness and implemented tight waste management.

Consumers are already shopping to make their carbon footsteps lighter. Food stores are on the bandwagon although apparel is lagging. Perhaps it’s time you found out just how your company is shaping up. It’s no longer a matter of ?if carbon taxes?. It’s a matter of ?when it does?.

ecoVaro is a software system-in-the-cloud that lets you enter your water and energy consumption and process it online so you can monitor and manage your usage. In no time at all you could be saving money like Westin Melbourne did. Does that sound like something worth investigating?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?