Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Directions Hadoop is Moving In

Hadoop is a data system so big it is like a virtual jumbo where your PC is a flea. One of the developers named it after his kid?s toy elephant so there is no complicated acronym to stumble over. The system is actually conceptually simple. It has loads of storage capacity and an unusual way of processing data. It does not wait for big files to report in to its software. Instead, it takes the processing system to the data.

The next question is what to do with Hadoop. Perhaps the question would be better expressed as, what can we do with a wonderful opportunity that we could not do before. Certainly, Hadoop is not for storing videos when your laptop starts complaining. The interfaces are clumsy and Hadoop belongs in the realm of large organisations that have the money. Here are two examples to illustrate the point.

Hadoop in Healthcare

In the U.S., healthcare generates more than 150 gigabytes of data annually. Within this data there are important clues that online training provider DeZyre believes could lead to these solutions:

  • Personalised cancer treatments that relate to how individual genomes cause the disease to mutate uniquely
  • Intelligent online analysis of life signs (blood pressure, heart beat, breathing) in remote children?s hospitals treating multiple victims of catastrophes
  • Mining of patient information from health records, financial status and payroll data to understand how these variables impact on patient health
  • Understanding trends in healthcare claims to empower hospitals and health insurers to increase their competitive advantages.
  • New ways to prevent health insurance fraud by correlating it with claims histories, attorney costs and call centre notes.

Hadoop in Retail

The retail industry also generates a vast amount of data, due to consumer volumes and multiple touch points in the delivery funnel. Skillspeed business trainers report the following emerging trends:

  • Tracing individual consumers along the marketing trail to determine individual patterns for different demographics and understand consumers better.
  • Obtaining access to aggregated consumer feedback regarding advertising campaigns, product launches, competitor tactics and so on.
  • Staying with individual consumers as they move through retail outlets and personalising their experience by delivering contextual messages.
  • Understanding the routes that virtual shoppers follow, and adding handy popups with useful hints and tips to encourage them on.
  • Detecting trends in consumer preferences in order to forecast next season sales and stock up or down accordingly.

Where to From Here?

Big data mining is akin to deep space research in that we are exploring fresh frontiers and discovering new worlds of information. The future is as broad as our imagination.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
UK Government Updates ESOS Guidelines

Britain?s Environment Agency has produced an update to the ESOS guidelines previously published by the Department of Energy and Climate Change. Fortunately for businesses much of it has remained the same. Hence it is only necessary to highlight the changes here.

  1. Participants in joint ventures without a clear majority must assess themselves individually against criteria for participation, and run their own ESOS programs if they comply.
  2. If a party supplying energy to assets held in trust qualifies for ESOS then these assets must be included in its program.
  3. Total energy consumption applies only to assets held on both the 31 December 2014 and 5 December 2015 peg points. This is relevant to the construction industry where sites may exchange hands between the two dates. The definition of ?held? includes borrowed, leased, rented and used.
  4. Energy consumption while travelling by plane or ship is only relevant if either (or both) start and end-points are in the UK. Foreign travel may be voluntarily included at company discretion. The guidelines are silent regarding double counting when travelling to fellow EU states.
  5. The choice of sites to sample is at the discretion of the company and lead assessor. The findings of these audits must be applied across the board, and ?robust explanations? provided in the evidence pack for selection of specific sites. This is a departure from traditional emphasis on random.

The Environment Agency has provided the following checklist of what to keep in the evidence pack

  1. Contact details of participating and responsible undertakings
  2. Details of directors or equivalents who reviewed the assessment
  3. Written confirmation of this by these persons
  4. Contact details of lead assessor and the register they appear on
  5. Written confirmation by the assessor they signed the ESOS off
  6. Calculation of total energy consumption
  7. List of identified areas of significant consumption
  8. Details of audits and methodologies used
  9. Details of energy saving opportunities identified
  10. Details of methods used to address these opportunities / certificates
  11. Contracts covering aggregation or release of group members
  12. If less than twelve months of data used why this was so
  13. Justification for using this lesser time frame
  14. Reasons for including unverifiable data in assessments
  15. Methodology used for arriving at estimates applied
  16. If applicable, why the lead assessor overlooked a consumption profile

Check out: Ecovaro ? energy data analytics specialist 

Could Kanban Be?Best for Knowledge Workers?

Knowledge Workers include academics, accountants, architects, doctors, engineers, lawyers, software engineers, scientists and anybody else whose job it is to think for a living. They are usually independent-minded people who do not appreciate project managers dishing out detailed orders. Kanban project management resolves this by letting them choose the next task themselves.

The word ?Kanban? comes from a Japanese word meaning ?billboard? or ?signboard?. Before going into more detail how this works let’s first examine how Japanese beliefs of collaboration, communication, courage, focus on value, respect for people and a holistic approach to change fit into the picture.

The Four Spokes Leading to the Kanban Hub

  1. Visualise the Workflow ?You cannot improve what you cannot see. The first step involves team members reducing a project to individual stages and posting these on a noticeboard.
  2. Create Batches ? These stages are further reduced to individual tasks or batches that are achievable within a working day or shift. More is achievable when we do not have to pick up where we left off the previous day.
  3. Choose a Leader the Team Respects – Without leadership, a group of people produces chaotic results. To replace this with significant value they need a leader, and especially a leader they can willingly follow.
  4. Learn and Improve Constantly ? Kaizen or continuous improvement underpins the Japanese business model, and respects that achievement is a step along the road, and not fulfilment.

The Kanban Method in Practice

Every Kanban project begins with an existing process the participants accept will benefit from continuous change. These adjustments should be incremental, not radical step-changes to avoid disrupting the stakeholders and the process. The focus is on where the greatest benefits are possible.

Anybody in the team is free to pull any batch from the queue and work on it in the spirit of collaboration and cooperation. That they do so, should not make any waves in a culture of respect for people and a holistic approach to working together. All it needs is the courage to step out of line and dream what is possible.

The Kanban Project Method ? Conclusions and Thoughts

Every engine needs some sort of fuel to make it go. The Kanban project management method needs collaboration, communication, courage, focus on value, respect for people and a holistic approach to work. This runs counter to traditional western hierarchies and probably limits its usefulness in the West.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?