Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Data Replication

Medical Data Form

These days, not many companies can continue to operate once their entire computer system goes down. All the information needed in daily operations are stored in databases while the interfaces that make use of them all come in the form of software applications.

Software applications can be rapidly reinstalled and configured for as long as the necessary programs are available. Data, however, cannot be reconstructed as quickly even with hard copies available. It is therefore necessary to store your data in a replicated setup so that when one section goes down, operations can proceed without interruption.

For instance, if a category 5 hurricane renders your main office useless, you can simply rent workstations elsewhere, connect to the Internet and continue with your usual transactions for as long as data is readily accessible.

So how do we ensure the accessibility and reliability of your data? Here’s what we’ll do:

  • Activate data replication on your database management system. If your DBMS does not support replication, we’ll migrate all your data to one that does.
  • If absolutely necessary, we can allow modernised systems to run parallel to your legacy systems and prepare both for full modernisation when you’re ready.
  • Implement fail-over technologies where applicable to provide for automatic switching to a backup data server or network from one that has just failed.

We can also assist you with the following:

What Sub-Metering did for Nissan in Tennessee

When Nissan built its motor manufacturing plant in Smyrna 30 years ago, the 5.9 million square-foot factory employing over 8,000 people was state of art. After the 2005 hurricane season sky-rocketed energy prices, the energy team looked beyond efficient lighting at the more important aspect of utility usage in the plant itself. Let’s examine how they went about sub-metering and what it gained for them.

The Nissan energy team faced three challenges as they began their study. They had a rudimentary high-level data collection system (NEMAC) that was so primitive they had to transfer the data to spread-sheets to analyse it. To compound this, the engineering staff were focused on the priority of getting cars faster through the line. Finally, they faced the daunting task of making modifications to reticulation systems without affecting manufacturing throughput. But where to start?

The energy team chose the route of collaboration with assembly and maintenance people as they began the initial phase of tracking down existing meters and detecting gaps. They installed most additional equipment during normal service outages. Exceptions were treated as minor jobs to be done when convenient. Their next step was to connect the additional meters to their ageing NEMAC, and learn how to use it properly for the first time.

Although this was a cranky solution, it had the advantage of not calling for additional funding which would have caused delays. However operations personnel were concerned that energy-saving shutdowns between shifts and over weekends could cause false starts. ?We’ve already squeezed the lemon dry,? they seemed to say. ?What makes you think there?s more to come??

The energy team had a lucky break when they stumbled into an opportunity to prove their point early into implementation. They spotted a four-hourly power consumption spike they knew was worth examining. They traced this to an air dryer that was set to cyclical operation because it lacked a dew-point sensor. The company recovered the $1,500 this cost to fix, in an amazing 6 weeks.

Suitably encouraged and now supported by the operating and maintenance departments, the Smyrna energy team expanded their project to empower operating staff to adjust production schedules to optimise energy use, and maintenance staff to detect machines that were running without output value. The ongoing savings are significant and levels of shop floor staff motivation are higher.

Let’s leave the final word to the energy team facilitator who says, ?The only disadvantage of sub-metering is that now we can’t imagine doing without it.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
SEO (Search Engine Optimization)

About a quarter of the world’s population use the Internet. That’s approximately 1.7 billion people. How many will come to your site the moment it launches? Zero.

It will take some time before the search engines are able to index your site and allow the possibility of driving some visitor traffic there. But even when your site does get indexed, that’s no assurance people will even have the chance of finding it.

So unless you apply SEO, your chances of improving those traffic numbers from zilch would nearly be zilch too. Traffic is a fundamental prerequisite in eCommerce. Before any store, virtual or otherwise, can ever hope to make a sale, the first step is to get noticed by the potential customer.

Our SEO specialists can drive your pages to the top of search results so that potential customers can see results leading to your site first.

Depending on the product or service you’re offering, getting to be ranked high on the search engines can be extremely labour-intensive. Basically, it’s the kind of job you’d rather not keep in-house but its the kind of job our team would be happy to take charge on.

Different products and services have different SEO requirements. We won’t recommend an SEO package if we think it will only translate to unnecessary spending.

These are the essentials of our SEO packages:

  • Targeted keywords and keyphrases. We’ll conduct extensive research on your product line and your product competitors to get hold of the best targeted keywords and keyphrases. If your competitors missed any important keyphrases, we’ll find those as well.
  • Strategically planted backlinks. We’ll concentrate our backlinking efforts on relevant backlinks to achieve top search engine rankings. As an added bonus, relevant backlinks drive in traffic that really matter as this is made up of visitors with the highest potential of turning into buyers.
  • On-site SEO. Certain issues arising from the mere makeup of most eCommerce websites are making on-site SEO tweaking more challenging. In fact, not all SEO consultants cater to these specific problems. Our specialists, on the other hand, pay special attention to issues regarding pagination resulting in keyword cannibalisation, product pages, landing page optimisation and the like.
  • Selection of SEO packages. While you’re still starting out, you may want to try our basic packages first. Then once you see traffic pouring in and revenues begin to build up, you can up the ante by upgrading to our premium packages.

Other services you might be interested in:

Ready to work with Denizon?