Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Are Master Data Management and Hadoop a Good Match?

Master Data is the critical electronic information about the company we cannot afford to lose. Accordingly, we should sanitise it, look after it, and store it safely in several separate places that are independent of each other. The advent of Big Data introduced the current era of huge repositories ?in the clouds?. They are not, of course but at least they are remote. This short article includes a discussion about Hadoop, and whether this is a good platform to back up your Master Data.

About Hadoop

Hadoop is an open-source Apache software framework built on the assumption that hardware failure is so common that backups are unavoidable. It comprises a storage area and a management part that distributes the data to smaller nodes where it processes faster and more efficiently. Prominent users include Yahoo! and Facebook. In fact more than half Fortune 50 companies were using Hadoop in 2013.

Hadoop – initially launched in December 2011 ? has survived its baptism of fire and became a respected, reliable option. But is this something the average business owner can tackle on their own? Bear in mind that open source software generally comes with little implementation support from the vendor.

The Hadoop Strong Suite

  • Free to download, use and contribute to
  • Everything you need ?in the box? to get started
  • Distributed across multiple fire-walled computers
  • Fast processing of data held in efficient cluster nodes
  • Massive scaleable storage you are unlikely to run out of

Practical Constraints

There is more to Hadoop than writing to WordPress. The most straightforward solutions are uploading using Java commands, obtaining an interface mechanism, or using third party vendor connectors such as ACCESS or SAS. The system does not replace the need for IT support, although it is cheap and exceptionally powerful.

The Not-Free Safer Option

Smaller companies without in-depth in-house support are wise to engage with a technical intermediary. There are companies providing commercial implementations followed by support. Microsoft, Amazon and Google among others all have commercial versions in their catalogues, and support teams at the end of the line.

Denizon’s Business Continuity Services

Disruptions to business operations can be as catastrophic as a Hurricane Katrina or a 9/11 or as relatively trivial as a minor power outage or a planned shutdown. What ever the gravity, scope and duration the disruption has, your company should be able to handle each situation so that you can declare “business as usual” and really mean it. (more…)

Benefits Realisation Frameworks – A Useful Handle

One of the greatest challenges of project management is maintaining top-down support in the face of fluctuating priorities. If you elect to take on the role yourself and are peppered by other priorities, it can be a challenge to exactly remember why you are changing things and what your goals are. Sometimes you may not even notice you have reached your goal.

The Benefits Realisation Chart-room

The Benefits Realisation Model is a framework on which to hang key elements of any project. These traditionally include the following, although yours may not necessarily be the same:

  • Definition of the project goal
  • Quantification of intended benefits
  • Project plan versus actual progress
  • How you know you reached your goal
  • Quantification of actual benefits

Another way of describing Benefits Realisation Frameworks is they answer four fundamental questions that every project manager should know by heart:

  • What am I going to do?
  • How am I going to do it?
  • When will I know it’s done?
  • What exactly did I achieve?

The Benefits Realisation Promise

An astounding number of projects fail to reach completion, or miss their targets. It’s not for nothing that the expression ?after the project failed the non-participants were awarded medals? is often used in project rooms. We’re not saying that it is a panacea for success. However it can alert you to warnings that your project is beginning to falter in terms of delivering the over-arching benefits that justify the effort.

When Projects Wander Off-Target

Pinning blame on participants is pointless when project goals are flawed. For example, the goals may be entirely savings-focused and not follow through on what to do with the windfall. At other times realisation targets may be in place, but nobody appointed to recycle the benefits back into the organisation. This is why a Benefits Realisation Framework needs to look beyond the project manager?s role.

Realisation Management in Practice

If the project framework does not look beyond the project manager?s role, then it is over when it reaches its own targets ? and can even run the risk of being an event that feeds entirely off itself. In order to avoid a project being a means to its own end, this first phase must culminate with handover to a benefits realisation custodian.

An example of this might be a project to centralise facilities that is justified in terms of labour savings. The project manager?s job is to build the structure. Someone else needs to rationalise the organisation.

In conclusion, the Benefits Realisation Framework is a useful way of ensuring a project does not only achieve its internal goals, but also remains a focus of management attention because of its extended, tangible benefits.

Ready to work with Denizon?