Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

How To Get Started with your IT Compliance Efforts for SOX

There’s no question about it. For many of you top executives in the corporate world, all roads leading to a brighter future have to go through SOX compliance. And because the business processes that contribute to financial reporting (the crux of the Sarbanes-Oxley Act) are now highly reliant on IT systems, it is important to focus a good part of your attention there.

It is a long and arduous path to IT compliance, so if you don’t want your company to fall by the wayside due to inefficient utilisation of resources, it is important to set out with a plan on hand. What we have here are some vital information that will guide you in putting together a sound plan for SOX compliance of your company?s IT systems.

Why focus on IT systems for SOX compliance?

We’ll get to that. But first, let’s take up the specific portions of the Sarbanes-Oxley Act that affect information technology. These portions can be found in Section 302 and Section 404 of the act.

In simplified form, Section 302 grants the SEC (Securities and Exchange Commission) authority to come up with rules requiring you, CEOs and CFOs, to certify in each annual or quarterly financial report the following:

  • that you have reviewed the report;
  • that based on your knowledge, the report does not contain anything or leave out anything that would render it misleading;
  • that based on your knowledge, all financial information in the report fairly represent the financial conditions of the company;
  • that you are responsible for establishing internal controls over financial reporting; and
  • that you have assessed the effectiveness of the internal controls.

Similarly, Section 404, stated in simplified form, allows the SEC to come up with rules requiring you, CEOs and CFOs, to add an internal control report to each annual financial report stating that you are responsible for establishing internal controls over financial reporting.

You are also required to assess the effectiveness of those controls and to have a public accounting firm to attest to your assessment based upon standards adopted by the Public Company Accounting Oversight Board (PCAOB).

While there is no mention of IT systems, IT systems now play a significant role in financial reporting. Practically all of the data you need for your financial reports are stored, retrieved and processed on IT systems, so you really have to include them in your SOX compliance initiatives and establish controls on them.

Now that that’s settled, your next question could very well be: How do you know what controls to install and whether those controls are already sufficient to achieve compliance?

Finding a suitable guide for IT compliance

The two bodies responsible for setting rules and standards dealing with SOX, SEC and PCAOB, point to a well-established control framework for guidance – COSO. This framework was drafted by the Committee of Sponsoring Organisations of the Treadway Commission (COSO) and is the most widely accepted control framework in the business world.

However, while COSO is a tested and proven framework, it is more suitable for general controls. What we recommend is a widely-used control framework that aligns well with COSO but also caters to the more technical features and issues that come with IT systems.

Taking into consideration those qualifiers, we recommend COBIT. COBIT features a well thought out collection of IT-related control objectives grouped into four domains: Plan and Organise (PO), Acquire and Implement (AI), Deliver and Support (DS), and Monitor and Evaluate (ME). The document also includes maturity models, performance goals and metrics, and activity goals.

A few examples of COBIt’s detailed control objectives are:

DS4.2 – IT Continuity Plans
DS4.9 – Offsite Backup Storage
DS5.4 – User Account Management
DS5.8 – Cryptographic Key Management
DS5.10 – Network Security
DS5.11 – Exchange of Sensitive Data

By those titles alone, you can see that the framework is specifically designed for IT. But the document is quite extensive and, chances are, you won’t need all of the items detailed there. Furthermore, don’t expect COBIT to specify a control solution controls for every control objective. For example, throughout the control objective DS4 (Ensure Continuous Service), you won’t find any mention of virtualisation, which is common in any modern business continuity solution.

Basically, COBIT will tell you what you need to attain in order to achieve effective governance, management and control, but you’ll have to pick the solution best suited to reach that level of attainment.

Articles highly relevant to the one you just read:

Month End Accounting The Way It Should Be Today
Spreadsheet Woes ? Burden in SOX Compliance and Other Regulations
Spreadsheet Woes ? Limited Features For Easy Adoption of a Control Framework
How Internal Auditors Can Win The War Against Spreadsheet Fraud

Job & Staff Scheduling with FieldElite Mobile Service Management Software

Field Service Management (FSM) software systems are designed to enable you to manage your mobile workforce from a central point- and do away with the paperwork involved with the process. They connect your technicians on the ground (via app on their phones), to the staff at the head office- who have an interactive dashboard accessed through their browsers. The office team will have access to all the jobs that are to be handled by the company, simplifying the management process and taking away the risks that come with manual data entry. Here, we will walk you through a quick process of scheduling a job for your personnel with FieldElite.

Say you are a HVAC contractor, licensed, bonded and insured. You’ve made quite a name for yourself in the industry, and have a wide range of clients- in both residential and commercial establishments. Consequently, you also have a large workforce to attend to the different situations- from installing to repair and maintenance. One of your clients- let’s call them ABC Computer Supplies, has an issue with their HVAC unit- perhaps a pipe is leaking. It needs to be fixed, and ABC have booked an appointment.? Your goal here is to get one of your personnel to handle the task as soon as possible, and this field service scheduling software comes in handy.

There are two approaches that you can take:

1. Job Scheduling

From your Dashboard, on the left-hand side you will see the menu option. Clicking on Jobs, will take you to all jobs carried out by your company.

FieldElite

The filters will allow you to view different categories of jobs:

  • Complaint– This means that there was an issue with on ground during the task delivery, and the client lodged a complaint.
  • On hold– Here, different aspects can cause a job to be paused- like when spare parts or equipment required for repair jobs have been ordered, and one needs to wait for them to be shipped in from a different location.
  • Pending– This is basically your in-tray, a list of jobs that are to be carried out.
  • In Progress– The technicians are on the ground, attending to the client’s needs, and you’re getting routine updates from them.
  • Incomplete– Though the job had been assigned to the required technician, it was not completed in the set amount of time, thus requiring an additional visit to the site. Given that the FSM solution increases the first-time fix rate, cases of ?incomplete tasks? are reduced.
  • Complete– The task is successfully done and the customer has appended their e-signature, and now it can be invoiced.
  • Cancelled Invoice– The head office determines that a particular invoice shouldn’t be paid, and thus cancels it.

Our focus here is the pending tasks, so use this filter. ABC’s HVAC job will be among these. Clicking on its Job ID will open up the details of the task, with such an Update Job window:

FieldElite Job

This section contains all the information of the job- both past and present, which you can update in real-time. Any changes will be recorded by the system and can be viewed on the “Audit” tab.

As you can see here, the HVAC repair job is both “pending” and “urgent”. No one really likes sitting in an office that feels like an oven. Being the headquarters, it’s likely handles lots of foot traffic, and the damaged HVAC unit will make the working conditions really difficult. It’s best not to keep the client waiting, right?

So, head on over to the Supervisor and Workers section (on the same “Details” tab), and select the personnel suited for the task.

FieldElite Job Details

Set the time that the task will take for your technician, and once satisfied with the details of the job, click on Update. Voila! You’re done.

FieldElite Job Update

Immediately this happens, the worker received a notification on their app, telling them that they have been assigned the job.

From the app, the technician will be able to view the specifics of the HVAC job, including notes and attachments that you can add directly from your own dashboard, such as schematics of the building and reports from other technicians who installed the air conditioning system for the facility. You also get to add products that will be required for the task- like the pipe and panel mounted socket shown here. As the system also includes an inventory of the products used, their quantity and costs, you will be able to keep an accurate record of the supplies as they as are used.

As such, the field workers will not have to keep coming back to the central office to get documents and reports of new tasks, or walk around with bulky files. When they are carrying out the job, they will also be able to keep the staff at the office updated about its progress, through the chat feature on the mobile app, taking photos and adding notes as required.

2. Staff Scheduling

With this approach, the perspective is basically: ?So I have a couple of jobs- which of my employees has time to handle them?? The FSM allows you to optimise your productivity- by ensuring that you get the most out of the staff work hours, and avoid cases of jobs going into overtime.

Follow these steps:

  1. Select ?Scheduler? from the left-hand side of the window. You will have a view of the workers of your company and how their day is planned out, and a summary of the unassigned jobs.

Here, you can tell whose busy, and who can have a new task assigned to them at the click of a button- which is far more effective than keeping on jotting down points in your diary or going through files of documents.

If the job has yet to be added to the system- like for the cases of new clients, simply click on the ?Add Job? button and key in its details.

2. Scroll down, you will see a list of unassigned jobs.

unassigned jobs

3. Next, click on the edit button under ?Actions?. This will take you to the same ?Update Job? window described in the first approach, in order to assign the preferred worker to the role.

This real-time dispatching avoids cases of your desk getting cluttered with paper sheets, and prevents duplicate entries as each job has its own ID and task details- from the scheduling to the invoicing. In this case, your HVAC technician will have access to the information needed right at the palm of their hand, to ensure that the task at ABC?s head office goes seamlessly. The optimised schedule will enable the task to be carried out faster- restoring normalcy to your client’s facility.? In case the client’s location is on the route that one of your technicians takes while heading home, you can take advantage of this by giving them the task towards the end of their working day- thus clearing more of your backlog, sorting out your client, and easing your technician?s worries about getting home late.

As you can see, the field service scheduling software enables you to easily and efficiently handle your workflow, avoid the mess that is associated with manual documentation and cases of your employees getting conflicting schedules and overlaps- which would strain them and dampen their morale. Streamlining your workflow and standardising operations ultimately results in increased customer satisfaction.

Saving Energy Step 3 ? Towards a Variable Energy Bill

Do you remember the days when energy was so cheap we paid the bill almost without thinking about it? Things have changed and we have the additional duty of reducing consumption to help save the planet. This is the third article in our mini-series on saving energy. It follows on from the first that explored implementing a management system, and the second listing practical things to implement on the shop floor. These open up the possibility of the variable energy bill we expand on as follows.

If ?variable energy bill? sounds strange to you, I used the unusual turn of phrase to encourage you to view things in a different light. We need to move on from the ?pie chart? mentality where we focus on the biggest numbers like materials, facilities and labour, and zoom in on energy where we can achieve similar gains faster with less pain. But first, we need to see beyond the jargon that governments and consultants love, and get to grips with the reality that we can vary our energy bill and bring cost down.

As executives we recognise this, although other pressures distract us from accepting it as a personal goal. And so we delegate it down the organisation to a level where it becomes ?another crazy management idea? we have to follow to stay out of trouble. I read somewhere that half the world?s organisations do not have energy as a defined objective to monitor in the C Suite. No wonder commerce is only pecking away at energy wastage at a rate of 1% per year.

Find out where you are ?spending energy? and relate this to your core business. If there are places where you are unable to make a connection, challenge the activity?s right to exist. Following the energy trail produces unexpected benefits because it permeates everything we do.

  • Improved product design reducing time spent in factory
  • Streamlined production schedules reducing machine run times
  • Less wear on equipment reducing costly maintenance
  • A more motivated workforce that is prouder of ?what we do?

As you achieve energy savings you can pass these on in terms of lower prices and greater market share. All this and more is possible when you focus on the variables behind your energy bill. Run the numbers. It deserves more attention than it often gets.

Ready to work with Denizon?