Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Telemetry and the Survival of the Human Species

Without moisture, plants die. Without fodder, the animal food chain collapses. This is why climate change is the greatest threat humankind faces. Crop management needs timely information regarding ambient conditions, and also in the soil itself. In dry areas, online knowledge of trends in rainfall, sunlight, wind speed, leaf moisture, air temperature, relative humidity and solar radiation are indicators of soil stress that can be deadly for plants, and everything that relies on them.

As climate change bites, the need to find solutions accelerates. Drones swoop across to monitor ambient conditions, while probes sunk into plants and the earth in which they grow transmit information to big data repositories for feedback to administrators. In Australia, a remarkable cattle farmer is applying the same approach to his herds.

Nuffield scholar Rob Cook has always been on the edgy side of things. He lost his mobility in a helicopter crash in 2008 patrolling farmland but that has not deterred him. If anything, it has freed his mind to explore the potential that telemetry offers farmers in Australia. He shared this potential with the young beef producers in Roma Australia recently, and here is a summary what he said.

Being wheelchair bound he had to shift from herding with cattle dogs to a more scientific approach. He bought a farm 230 miles / 370 kilometres inland from Brisbane in a warm, temperate climate with significant rainfall even in the driest months. He uses observant software that reports on critical issues like water levels indicating animal consumption, and supplementary water flows from a central irrigation channel.

He also monitors fodder sources for dryer months, and moisture levels in food stocks. Rob is committed to making every blade of grass count. ?We even have the ability to take a photo of the cattle when they are taking a drink of water,? he explains, and that provides valuable information regarding tick and fly infestation and overall condition.

None of this would be possible for Rob Cook without telemetry, which is the process of collecting data at remote points and transmitting it to receiving equipment for analysis. Independent farmers do not have equipment to fund these analytic resources on their own, and use big data resources in a cloud to obtain reports. ecoVaro is on top of current trends. Please speak to us when you need independent advice.

?

The Matrix Management Structure

Organizations exploit matrix management in various ways. A company, for instance, that operates globally uses it at larger scale by giving consistent products to various countries internationally. A business entity, having many products, does not assign its people to each product full-time but assign those to different ones on a part time basis, instead. And when it comes to delivering high quality and low cost products, companies overcome industry pressures with the help of many overseeing managers. In a rapidly changing environment, organizations respond quickly by sharing information through a matrix model.

Understanding the Matrix Management Structure

A basic understanding of matrix management starts with the three key roles and responsibilities that applies in the structure.

  • Matrix Leader ? The common person above all the matrix bosses is the matrix leader. He ensures that the balance of power is maintained in the entire organization by delegating decisions and promoting collaboration among the people.
  • Matrix Managers ? The managers cooperate with each other by defining the respective activities that they are responsible for.
  • Matrix Employees – The employees have lesser direct authority but has more responsibilities. They resolve differing demands from more than one matrix managers while they work things out upwards. Their loyalty must be dual and their relationships with managers must be maintained.

Characteristics of a Matrix Structure

Here are some features that define the matrix management structure:

  • Hybrid Structure ?The matrix structure is a mix of functional and project organization. Since it is a combination of these two, matrix management is hybrid in nature.
  • Functional Manager ? When it comes to the technical phases of the project, the functional manager assumes responsibility. The manager decides on how to get the project done, delegates the tasks to the subordinates and oversees the operational parts of the organization.
  • Project Manager ? The project manager has full authority in the administrative phases, including the physical and financial resources needed to complete the project. The responsibilities of a project manager comprise deciding on what to do, scheduling the work, coordinating the activities to diverse functions and evaluating over-all project performance.
  • Specialization ?As the functional managers concentrate on the technical factors, the project managers focus on administrative ones. Thus, in matrix management, there is specialization.
  • Challenge in Unity of Command ? Companies that employs matrix management usually experience a problem when it comes to the unity of command. This is largely due to the conflicting orders from the functional and project managers.

Types of Matrix Structure

The matrix management structure can be classified according to the level of power of the project manager. Here are three distinct types of matrix structures that are widely used by organizations.

  • Weak Matrix ? The project manager has limited authority and power as the functional manager controls the budget of the project. His role is only part-time and more like a coordinator.
  • Strong Matrix ? Here, the project manager has almost all the authority and power. He controls the budget, holds the full time administrative project management and has a full time role.
  • Balanced Matrix ? In this structure type, both the project and functional managers control the budget of the project. The authority and power is shared by the two as well. Although the project manager has a full time role, he only has a part time authority for the administrative staff to report under his leadership.

Successful companies of today venture more on enhancing the abilities, skills, behavior and performances of their managers than the pursuit of finding the best physical structure. Indeed, learning the fundamentals of the matrix structure is essential to maximize its efficiency. A senior executive pointed out that one of the challenges in matrix management is not more of building a structure but in creating the matrix to the mind of the managers. This comes to say that matrix management is not just about the structure, it is a frame in the mind.

2015 ESOS Guidelines Chapter 2 – Deadlines and Status Changes

The ESOS process is deadline driven and meeting key dates is a non-negotiable. The penalties for not complying / providing false or misleading information are ?50,000 each. Simply not maintaining adequate records could cost you ?5,000. The carrot on the end of the stick is the financial benefits you stand to gain.

Qualifying for inclusion under the ESOS umbrella depends on the status of your company in terms of employee numbers, turnover and balance sheet on 31 December 2014. Regardless of whether you meet the 2014 threshold or not, you must reconsider your situation on 31 December 2018, 2022 and 2026.

Compliance Period Qualification Date Compliance Period Compliance Date
1 31 December 2014 From 17 July 2014* to 5 December 2015 5 December 2015
2 31 December 2018 From 6 December 2015 to 5 December 2019 5 December 2019
3 31 December 2022 From 6 December 2019 to 5 December 2023 5 December 2023
4 31 December 2026 From 6 December 2023 to 5 December 2027 5 December 2027

Notes:

1. The first compliance period begins on the date the regulations became effective

2. Energy audits from 6 December 2011 onward may go towards the first compliance report

Changes in Organisation Status

If your organisation status changes after a qualification date when you met compliance thresholds, you are still bound to complete your ESOS assessment for that compliance period. This is regardless of any change in size or structure. Your qualification status then remains in force until the next qualification date when you must reconsider it.

Ready to work with Denizon?