Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

2015 ESOS Guidelines Chapter 1 ? Who Qualifies

The base criteria are any UK undertaking that employs more than 250 people and/or has a turnover in excess of ?50 million and/or has a balance sheet total greater than ?43 million. There is little point in attempting to separate off high polluting areas. If one corporate group qualifies for ESOS, then all the others are obligated to take part too. The sterling equivalents of ?38,937,777 and ?33,486,489 were set on 31 December 2014 and apply to the first compliance period.

Representatives of Overseas Entities

UK registered branches of foreign entities are treated as if fully UK owned. They also have to sign up if any overseas corporate element meets the threshold no matter where in the world. The deciding factor is common ownership throughout the ESOS system. ecoVaro appreciates this. We have seen European companies dumping pollution in under-regulated countries for far too long.

Generic Undertakings that Could Comply

The common factor is energy consumption and the organisation’s type of work is irrelevant. The Environmental Agency has provided the following generic checklist of undertakings that could qualify:

Limited Companies Public Companies Trusts
Partnerships Private Equity Companies Limited Liability Partnerships
Unincorporated Associations Not-for-Profit Bodies Universities (Per Funding)

Organisations Close to Thresholds

Organisations that come close to, but do not quite meet the qualification threshold should cast their minds back to previous accounting periods, because ESOS considers current and previous years. The exact wording in the regulations states:

?Where, in any accounting period, an undertaking is a large undertaking (or a small or medium undertaking, as the case may be), it retains that status until it falls within the definition of a small or medium undertaking (or a large undertaking, as the case may be) for two consecutive accounting periods.?

Considering the ?50,000 penalty for not completing an assessment or making a false or misleading statement, it makes good sense for close misses to comply.

Joint Ventures and Participative Undertakings

If one element of a UK group qualifies for ESOS, then the others must follow suit with the highest one carrying responsibility. Franchisees are independent undertakings although they may collectively agree to participate. If trusts receive energy from a third party that must do an ESOS, then so must they. Private equity firms and private finance initiatives receive the same treatment as other enterprises. De-aggregations must be in writing following which separated ESOS accountability applies.

Migrating from CRM to Big Data

Big data moved to centre stage from being just another fad, and is being punted as the latest cure-all for information woes. It may well be, although like all transitions there are pitfalls. Denizon decided to highlight the major ones in the hope of fostering better understanding of what is involved.

Accurate data and interpretation of it have become increasingly critical. Ideas Laboratory reports that 84% of managers regard understanding their clients and predicting market trends essential, with accelerating demand for data savvy people the inevitable result. However Inc 5000 thinks many of them may have little idea of where to start. We should apply the lessons learned from when we implemented CRM because the dynamics are similar.

Be More Results Oriented

Denizon believes the key is focusing on the results we expect from Big Data first. Only then is it appropriate to apply our minds to the technology. By working the other way round we may end up with less than optimum solutions. We should understand the differences between options before committing to a choice, because it is expensive to switch software platforms in midstream. data lakes, hadoop, nosql, and graph databases all have their places, provided the solution you buy is scalable.

Clean Up Data First

The golden rule is not to automate anything before you understand it. Know the origin of your data, and if this is not reliable clean it up before you automate it. Big Data projects fail when executives become so enthused by results that they forget to ask themselves, ?Does this make sense in terms of what I expected??

Beware First Impressions

Big Data is just that. Many bits of information aggregated into averages and summaries. It does not make recommendations. It only prompts questions and what-if?s. Overlooking the need for the analytics that must follow can have you blindly relying on algorithms while setting your business sense aside.

Hire the Best Brains

Big Data?s competitive advantage depends on what human minds make with the processed information it spits out. This means tracing and affording creative talent able to make the shift from reactive analytics to proactive interaction with the data, and the customer decisions behind it.

If this provides a d?j? vu moment then you are not alone. Every iteration of the software revolution has seen vendors selling while the fish were running, and buyers clamouring for the opportunity. Decide what you want out first, use clean data, beware first impressions and get your analytics right. Then you are on the way to migrating successfully from CRM to Big Data.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
The Matrix Management Structure

Organizations exploit matrix management in various ways. A company, for instance, that operates globally uses it at larger scale by giving consistent products to various countries internationally. A business entity, having many products, does not assign its people to each product full-time but assign those to different ones on a part time basis, instead. And when it comes to delivering high quality and low cost products, companies overcome industry pressures with the help of many overseeing managers. In a rapidly changing environment, organizations respond quickly by sharing information through a matrix model.

Understanding the Matrix Management Structure

A basic understanding of matrix management starts with the three key roles and responsibilities that applies in the structure.

  • Matrix Leader ? The common person above all the matrix bosses is the matrix leader. He ensures that the balance of power is maintained in the entire organization by delegating decisions and promoting collaboration among the people.
  • Matrix Managers ? The managers cooperate with each other by defining the respective activities that they are responsible for.
  • Matrix Employees – The employees have lesser direct authority but has more responsibilities. They resolve differing demands from more than one matrix managers while they work things out upwards. Their loyalty must be dual and their relationships with managers must be maintained.

Characteristics of a Matrix Structure

Here are some features that define the matrix management structure:

  • Hybrid Structure ?The matrix structure is a mix of functional and project organization. Since it is a combination of these two, matrix management is hybrid in nature.
  • Functional Manager ? When it comes to the technical phases of the project, the functional manager assumes responsibility. The manager decides on how to get the project done, delegates the tasks to the subordinates and oversees the operational parts of the organization.
  • Project Manager ? The project manager has full authority in the administrative phases, including the physical and financial resources needed to complete the project. The responsibilities of a project manager comprise deciding on what to do, scheduling the work, coordinating the activities to diverse functions and evaluating over-all project performance.
  • Specialization ?As the functional managers concentrate on the technical factors, the project managers focus on administrative ones. Thus, in matrix management, there is specialization.
  • Challenge in Unity of Command ? Companies that employs matrix management usually experience a problem when it comes to the unity of command. This is largely due to the conflicting orders from the functional and project managers.

Types of Matrix Structure

The matrix management structure can be classified according to the level of power of the project manager. Here are three distinct types of matrix structures that are widely used by organizations.

  • Weak Matrix ? The project manager has limited authority and power as the functional manager controls the budget of the project. His role is only part-time and more like a coordinator.
  • Strong Matrix ? Here, the project manager has almost all the authority and power. He controls the budget, holds the full time administrative project management and has a full time role.
  • Balanced Matrix ? In this structure type, both the project and functional managers control the budget of the project. The authority and power is shared by the two as well. Although the project manager has a full time role, he only has a part time authority for the administrative staff to report under his leadership.

Successful companies of today venture more on enhancing the abilities, skills, behavior and performances of their managers than the pursuit of finding the best physical structure. Indeed, learning the fundamentals of the matrix structure is essential to maximize its efficiency. A senior executive pointed out that one of the challenges in matrix management is not more of building a structure but in creating the matrix to the mind of the managers. This comes to say that matrix management is not just about the structure, it is a frame in the mind.

Ready to work with Denizon?