Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

How Volvo Dublin achieved Zero Landfill Status

The sprawling New River Valley Volvo plant in Dublin, Virginia slashed its electricity bill by 25% in a single year when it set its mind to this in 2009. It went on to become the first carbon-neutral factory in 2012 after replacing fossil energy with renewable power. Further efforts rewarded it with zero-landfill status in 2013. ecoVaro decided to investigate how it achieved this latest success.

Volvo Dublin?s anti-landfill project began when it identified, measured and evaluated all liquid and solid waste sources within the plant (i.e. before these left the works). This quantified data provided its environmental project team with a base from which to explore options for reusing, recycling and composting the discards.

Several decisions followed immediately. Volvo instructed its component suppliers to stop using cardboard boxes and foam rubber / Styrofoam as packaging, in favour of reusable shipping containers. This represented a collaborative saving that benefited both parties although this was just a forerunner of what followed.

Next, Volvo?s New River Valley truck assembly plant turned its attention to the paint shop. It developed methods to trap, reconstitute and reuse solvents that flushed paint lines, and recycle paint sludge to fire a cement kiln. The plant cafeteria did not escape attention either. The environment team made sure that all utensils, cups, containers and food waste generated were compostable at a facility on site.

The results of these simple, and in hindsight obvious decisions were remarkable. Every year since then Volvo has generated energy savings equivalent to 9,348 oil barrels or if you prefer 14,509 megawatts of electricity. Just imagine the benefits if every manufacturing facility did something similar everywhere around the world.

By 2012, the New River Valley Volvo Plant became the first U.S. facility to receive ISO 50001 energy-management status under a government-administered process. Further technology enhancements followed. These included solar hot water boilers and infrared heating throughout the 1.6 million square foot (148,644 square meter) plant, building automation systems that kept energy costs down, and listening to employees who were brim-full with good ideas.

The Volvo experience is by no means unique although it may have been ahead of the curve. General Motors has more than 106 landfill-free installations and Ford plans to reduce waste per vehicle by 40% between 2010 and 2016. These projects all began by measuring energy footprints throughout the process. ecoVaro provides a facility for you to do this too.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Mobile Security

Today’s advanced enterprises make extensive use of mobile devices in order for team members to exchange information, collaborate, and carry out business whenever and wherever they need to. BlackBerries, iPhones, Google Phones, and other smartphones as well as PocketPCs and PDAs are now allowed wireless remote access to the enterprise network.

As a result, they introduce additional vulnerabilities into the system.

  • Bluetooth exploits and unencrypted passwords can allow malicious individuals to gain access to private information.
  • Various wireless technologies that have substantially simplified the task of transferring data have provided openings for malicious code. In addition, the diversity of these wireless technologies combined with the constrained environments of these devices have made it difficult to come up with an all-in-one solution.
  • All PocketPCs, PDAs and smartphones can be synchronised with PCs and laptops, giving malware an entry point into computers and networks. Memory cards are guilty of this too.
  • VoIP, which are usually unencrypted, allow other people to perform unauthorised capture and recording of private conversations.

Mobile security is still an emerging discipline. Because of this, many organisations that allow members’ mobile phone access into the network don’t actually have a specific security policy for such devices.

That’s why we’re here to help. We’ll conduct a thorough evaluation of your security policies and systems in relation to mobile devices and seal gaps we spot along the way. If you don’t have the needed policies or if what you have needs an overhaul, we’ll set everything up (including the needed applications and infrastructure) for you.

Once we’ve got everything in place, you won’t have to worry about the vulnerabilities mentioned earlier. In addition to that, your organisation will already be capable of preventing the following:

  • Access to company information when the phone ends up in the hands of anyone other than the authorised user.
  • Being billed for phone usage due to virus activity
  • Unauthorised phone activity monitoring through spyware
  • Other disruptions caused by mobile-based malware

Other defences we’re capable of putting up include:

Which KPI?s to Use in CRM

Customer relationship management emerged in the 1980?s in the form of database marketing. In those tranquil pre-social media days, the possibility of ?managing? clients may have been a possibility although Twitter and Facebook took care of that. Modern managers face a more dynamic environment. If you are one, then what are the trends you should be monitoring yourself (as opposed to leaving it to others).

If you want to drip feed plants, you have to keep the flow of liquid regular. The same applies to drip-feed marketing. Customers are fickle dare we say forgetful. Denizon recommends you monitor each department in terms of Relationship Freshness. When were the people on your list last contacted, and what ensued from this?

Next up comes the Quality of Engagements that follow from these efforts. How often do your leads respond at all, and how many interfaces does it take to coax them into a decision? You need to relate this to response blocks and unsubscribes. After a while you will recognise the tipping point where it is pointless to continue.

Response Times relate closely to this. If your marketing people are hot then they should get a fast response to sales calls, email shots and live chats. It is essential to get back to the lead again as soon as possible. You are not the only company your customers are speaking too. Fortune belongs to the fast and fearless.

The purpose of marketing is to achieve Conversions, not generate data for the sake of it. You are paying for these interactions and should be getting more than page views. You need to drill down by department on this one too. If one team is outperforming another consider investing in interactive training.

Finally Funnel Drop-Off Rate. Funnel analysis identifies the points at which fish fall off the hook and seeks to understand why this is happening. If people click your links, make enquiries and then drift away, you have a different set of issues as opposed to if they do not respond at all.

You should be able to pull most of this information off your CRM system if it is half-decent, although you may need to trigger a few options and re orientate reporting by your people in the field. When you have your big data lined up speak to us. We have a range of data analysts brimming over with fresh ideas.

Ready to work with Denizon?