Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

How Westin Melbourne Hotel Trimmed its Footprint

Becoming sustainable is a three-pronged process. You must save money and push the buttons the government is pressing you to. But there?s a deeper, more urgent issue. If your customers mark you down for not being green enough you are heading for trouble. Let’s see how well this hotel is doing.

The Melbourne flagship of the Westin hotel chain boasts 262 spacious rooms with views of Melbourne Square and surrounding theatres, designer boutiques, galleries and national landmarks. The architects included conference facilities, a wellness centre and sundry bars and restaurants. After climate change arrived to stay, hotel management discovered they had inherited a water and energy-greedy monster. Their solution was to measure what was going through their systems, and then progressively cap the building?s greedy appetite.

The Melbourne Westin Hotel could not have achieved results without these metrics. They began by determining key indicators and measuring them. This provided them with criteria to set achievable, cost effective targets in the following key areas of their business:

  1. Water Management ? Demand-based linen and towel recycling, installation of back-washable water filters, water-saving shower heads, dual-flush toilets.
  2. Waste Management ? Conversion to green products, recycling kitchen oil, moving towards a paperless office, recycling everything possible.
  3. Energy Management ? Energy-efficient light bulbs, standby settings for lights, computers, televisions and air conditioners
  4. Stakeholder Communication ? Staff green-team training, guest education, ongoing employee briefings
  5. Strategic Positioning ? Visible, top-down commitment, optimised carbon offsets from clean, renewable energy sources, clearly stated position in the market

Westin?s Melbourne landmark has made good progress towards becoming the green hotel for others to follow. It has adjusted its environmental policies, increased water and energy awareness and implemented tight waste management.

Consumers are already shopping to make their carbon footsteps lighter. Food stores are on the bandwagon although apparel is lagging. Perhaps it’s time you found out just how your company is shaping up. It’s no longer a matter of ?if carbon taxes?. It’s a matter of ?when it does?.

ecoVaro is a software system-in-the-cloud that lets you enter your water and energy consumption and process it online so you can monitor and manage your usage. In no time at all you could be saving money like Westin Melbourne did. Does that sound like something worth investigating?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
A Definitive List of the Business Benefits of Cloud Computing ? Part 3

Strengthens business continuity/disaster recovery capabilities

Today’s business landscape calls for companies to have reliable business continuity and disaster recovery capabilities. After all, when the system goes down, customers and even employees would rarely ask ‘why‘ or ‘what happened‘ but instead go directly to the ‘how soon can we get back up‘ part.

So unless they’ve been struck by the same unforeseen disaster your business is also experiencing, a couple of hours downtime is plenty enough for most of these people. What’s worse is when they simply don’t wait until they get access again and just go to other providers that can offer the same services. In short, your inability to provide continuous IT and business services could translate to lost opportunities which your competition would only be too willing to gain. And that’s not even counting the possibility of losing essential data and other potential negative impact that critical IT failure can bring about.

The answer to avoiding such a scenario is of course, having a sound business continuity and disaster recovery plan in place. But this is actually easier said than done.

Traditionally, setting up a business continuity plan entailed some tedious procedures in addition to very costly infrastructure. We’re talking here about acquiring and maintaining practically a replication of the hardware infrastructure and environments currently existing for business-critical systems and data. Note that these mirror systems should be set-up, housed, and maintained in a remote facility or location.

Making the deployment even more complex is the constant need to update the data in storage as well as keep software applications in sync between the system in use and the one on standby mode. This process would involve the physical transfer of data and syncing of applications, which is cumbersome and again, expensive.

While large enterprises would not even think twice about having to spend so much to ensure that operations would never come to a grinding halt, most small and mid-sized organisations would not have the required financial means for them to even start considering this option. Often, the bulk of their disaster recovery plan would simply consist of some tape backups, and a lot of hoping that they would never have to suffer from any outage or IT failure.

But all that can be changed with the arrival of cloud computing.

A cloud strategy offers an affordable solution for business continuity and disaster recovery for SMBs with limited resources and even big companies trying to minimise expenses by looking for alternative options.

A reliable service provider would already have the required infrastructure and software vital to a viable BC/DR plan and complete with the appropriate security measures. Organisations need not spend upfront for these facilities, but get to benefit from having updated data backup and a virtualised mirror system that would allow them to quickly get back up in the event of an outage or catastrophic disaster.

When looking to the cloud for a cost-effective BC/DR plan however, it’s worth keeping in mind that not all cloud providers are created equal. That’s why businesses also have many important factors to take into account before signing cloud contracts.

Yes, provision for continuity and and taking necessary precautions against outages are inherent in the cloud service itself, but you’d be surprised how many of these providers don’t actually take responsibility for service interruption. To give organisations some assurance of the cloud company’s capacity for continued service, contracts should stipulate availability guarantees and liability for downtime that the provider is willing to answer for.

Once these relevant issues are ironed out however, it’s easy for business to see how cloud-based data storage and computing can significantly lower the costs involved for SMB BC/DR while greatly improving efficiency, mobility, and collaboration capabilities.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
IT Systems Implementation

Are you ready to find out how your newly accepted IT system fares in the real world? Although a rigorous Acceptance testing process can spot a wide spectrum of flaws in a newly constructed IT system, there is no way it can identify all possible defects. The moment the IT system is delivered into the hands of actual end users and other stakeholders, it is effectively stepping out of a controlled and secure environment.

Thus, it is during this phase wherein issues having direct impact on the business can arise.

It is our duty to ensure that the Systems Implementation phase is carried out as thoroughly, professionally, and efficiently as possible.

Thoroughly, because we need to include all relevant data and other deliverables, eliminate hard-to-detect miscalculated results, and substantially reduce the probability of business and mission critical issues popping up in the future;

Professionally, because it is the best way to address the sensitive process of turning over a new system to users who have gotten used to the old one;

And efficiently, because we want to minimise the duration over which all stakeholders have to adapt to the new system and allow them to move on to the process of growing the business.

Preparation

Louis Pasteur once said, “Luck favours the mind that is prepared.”

While we certainly won’t leave anything to chance, we do put substantial weight on the Preparation stage of Systems Implementation. We’re so confident with the strategies we employ in Preparation, that we can assure you of an utterly seamless Deployment and Transition phase.

By this we mean that issues that may arise during Deployment and Transition will be handled smoothly and efficiently because your people will know exactly what to do.

Here’s how we will prepare your organisation for Deployment:

  • Identify all key players for the Systems Implementation phase and orient them on their specific roles. We’ll make sure they know what possible hitches may come their way and how to deal with them.
  • Identify all end users and their corresponding functions, then assign appropriate access rights.
  • Draw multi-layered contingency plans to capture and address each possible concern that may crop up during Deployment.
  • Prepare a systematic step-by-step procedure and checklist for the entire Deployment stage. Both of them should have been copied from a similar procedure and checklist used in the Acceptance testing phase.
  • Make all stakeholders understand the conditions required before Deployment can commence.
  • Set the appropriate environment so that all stakeholders know what to expect and when to expect them the moment Deployment commences.
  • Prepare Technical Services and Technical Support personnel for the gruelling mission ahead.
  • Make sure all communication processes are well coordinated so that everyone affected will know who to contact and how to get in touch with them when a problem arises.
  • Plan and schedule training sessions so that they can be conducted “just in time”. Training sessions conducted way ahead of Deployment are often useless because the trainees tend to forget about what they learned when the time comes to apply them. Similarly, training sessions conducted way after Deployment also become useless because trainees are seldom able to internalise instructions delivered during crash courses.

Deployment

There are two sets of issues to keep an eye on during Deployment:

  1. Issues directly related to the technology itself, e.g. application functionality and data integrity, and
  2. Issues emanating from the end users, i.e., their unwillingness to use the new system. One reason may be because they find the interface and procedures too confusing. Another would be due to other inconveniences that come with adapting to a new set of procedures.

Despite all the meticulous scrutiny employed during Acceptance testing, there are just some problems that are made obvious only during Deployment. Issues belonging to the first set are dealt with easily because of the plans and procedures we put in place during the Preparation stage. As an added measure, our team will be on hand to make sure contingency plans are executed accordingly.

While the second set of issues is often neglected by many IT consultancy companies, we choose to meet it head on.

We fully understand that end users are most sensitive to the major changes that accompany a new system. It is precisely for this reason why our training activities during Deployment are designed not only to educate them but also to make them fully appreciate the necessity of both the new system and the familiarisation phase they will need to go through.

The faster we can bring your end users to accept the new system, the faster they can refocus on your company’s business objectives.

Here’s what we’ll do to guarantee the smoothest Deployment process you’ve ever experienced.

  • Employ the procedure and checklist formulated during the Preparation stage.
  • Ensure all end users are well acquainted with any additional tasks they would need to perform (e.g. filling up manual logs).
  • Assess which legacy systems can still be used alongside the new technology and which ones have to be retired.
  • Supervise the installation and optimal configuration of all supporting hardware and software to make sure the likelihood of errors originating from them are brought to near-zero levels.
  • Supervise the installation and optimal configuration of the products themselves.
  • Carry out data migration tasks if necessary.
  • Organise and oversee parallel runs to check for data and report inconsistencies.
  • Conduct training sessions in a professional and well-timed manner to eliminate end-users’ feelings of agitation and to take advantage of memory absorption and retention duration as with regards to their assigned duties and responsibilities.

Transition

Do you often feel uneasy whenever the reins to a newly purchased IT system are handed over to you? Perhaps there are some issues that you feel haven’t been fully settled but, at the same time, find it too late to back out, having already invested so much time and resources.

Alright, so maybe the thought of “backing up” never crossed your mind. However, the concern of being “not yet ready” is raised by many organisations towards the tail end of most Deployment stages. This usually drags the Deployment stage into a never-ending process.

Our team of highly experienced specialists will make sure you reach this point with utmost confidence to proceed on your own.

To wrap up our comprehensive IT Systems Implementation offering, we’ll take charge of the following:

  • Verify that all deliverables, including training materials and other technical documentation, are accomplished and expected outcomes are realised.
  • Make sure all technical documentation are placed in a secure and accessible location.
  • Institute best practices to ensure the IT system becomes fully utilised and to reduce its exposure to avoidable risks.
  • Establish open communication lines with the Technical Support team to enable quick resolution of issues.
  • Ensure complete knowledge transfer has been fully achieved so that your people will spend less time calling Technical Support and more on operations contributory to business growth.

Ready to work with Denizon?