Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

How Volvo Dublin achieved Zero Landfill Status

The sprawling New River Valley Volvo plant in Dublin, Virginia slashed its electricity bill by 25% in a single year when it set its mind to this in 2009. It went on to become the first carbon-neutral factory in 2012 after replacing fossil energy with renewable power. Further efforts rewarded it with zero-landfill status in 2013. ecoVaro decided to investigate how it achieved this latest success.

Volvo Dublin?s anti-landfill project began when it identified, measured and evaluated all liquid and solid waste sources within the plant (i.e. before these left the works). This quantified data provided its environmental project team with a base from which to explore options for reusing, recycling and composting the discards.

Several decisions followed immediately. Volvo instructed its component suppliers to stop using cardboard boxes and foam rubber / Styrofoam as packaging, in favour of reusable shipping containers. This represented a collaborative saving that benefited both parties although this was just a forerunner of what followed.

Next, Volvo?s New River Valley truck assembly plant turned its attention to the paint shop. It developed methods to trap, reconstitute and reuse solvents that flushed paint lines, and recycle paint sludge to fire a cement kiln. The plant cafeteria did not escape attention either. The environment team made sure that all utensils, cups, containers and food waste generated were compostable at a facility on site.

The results of these simple, and in hindsight obvious decisions were remarkable. Every year since then Volvo has generated energy savings equivalent to 9,348 oil barrels or if you prefer 14,509 megawatts of electricity. Just imagine the benefits if every manufacturing facility did something similar everywhere around the world.

By 2012, the New River Valley Volvo Plant became the first U.S. facility to receive ISO 50001 energy-management status under a government-administered process. Further technology enhancements followed. These included solar hot water boilers and infrared heating throughout the 1.6 million square foot (148,644 square meter) plant, building automation systems that kept energy costs down, and listening to employees who were brim-full with good ideas.

The Volvo experience is by no means unique although it may have been ahead of the curve. General Motors has more than 106 landfill-free installations and Ford plans to reduce waste per vehicle by 40% between 2010 and 2016. These projects all began by measuring energy footprints throughout the process. ecoVaro provides a facility for you to do this too.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
2015 ESOS Guidelines Chapter 1 ? Who Qualifies

The base criteria are any UK undertaking that employs more than 250 people and/or has a turnover in excess of ?50 million and/or has a balance sheet total greater than ?43 million. There is little point in attempting to separate off high polluting areas. If one corporate group qualifies for ESOS, then all the others are obligated to take part too. The sterling equivalents of ?38,937,777 and ?33,486,489 were set on 31 December 2014 and apply to the first compliance period.

Representatives of Overseas Entities

UK registered branches of foreign entities are treated as if fully UK owned. They also have to sign up if any overseas corporate element meets the threshold no matter where in the world. The deciding factor is common ownership throughout the ESOS system. ecoVaro appreciates this. We have seen European companies dumping pollution in under-regulated countries for far too long.

Generic Undertakings that Could Comply

The common factor is energy consumption and the organisation’s type of work is irrelevant. The Environmental Agency has provided the following generic checklist of undertakings that could qualify:

Limited Companies Public Companies Trusts
Partnerships Private Equity Companies Limited Liability Partnerships
Unincorporated Associations Not-for-Profit Bodies Universities (Per Funding)

Organisations Close to Thresholds

Organisations that come close to, but do not quite meet the qualification threshold should cast their minds back to previous accounting periods, because ESOS considers current and previous years. The exact wording in the regulations states:

?Where, in any accounting period, an undertaking is a large undertaking (or a small or medium undertaking, as the case may be), it retains that status until it falls within the definition of a small or medium undertaking (or a large undertaking, as the case may be) for two consecutive accounting periods.?

Considering the ?50,000 penalty for not completing an assessment or making a false or misleading statement, it makes good sense for close misses to comply.

Joint Ventures and Participative Undertakings

If one element of a UK group qualifies for ESOS, then the others must follow suit with the highest one carrying responsibility. Franchisees are independent undertakings although they may collectively agree to participate. If trusts receive energy from a third party that must do an ESOS, then so must they. Private equity firms and private finance initiatives receive the same treatment as other enterprises. De-aggregations must be in writing following which separated ESOS accountability applies.

IT Risk and Control Solutions Specialists – Why you need them more than ever

Over the years, the capabilities of IT systems have certainly grown by leaps and bounds. But so have the risks that accompany them. Countless threats to IT systems now exist that are capable of seriously disrupting business operations. That’s why companies have to conduct assessments aimed at making sure their systems are still capable of functioning effectively, efficiently, and securely all the time.

If you think you’ve been lucky enough to be spared from these threats, then maybe it’s because you haven’t conducted a risk assessment on your IT system recently. All too often, we hear of CIOs who believed their IT system was in tip-top condition, only to be later caught off-guard by a critical system breakdown that would eventually cripple their business for days or weeks.

More information assets to look after

If, before, you only had to worry about regular office applications, workstations, a LAN and a server, today’s varied and more sophisticated information assets are more challenging to maintain.

In addition to network operating systems, database management systems, content management systems, email systems, virtualization platforms, document management systems, business intelligence applications, and accounting software, a typical enterprise may also have to look after firewalls, intrusion detection systems, storage and backup systems, and data loss prevention systems, to mention a few.

These understandably require the services of experts spanning a wide range of skill sets.

Rising threats to corporate identity and privacy

Individuals are no longer just the ones being preyed upon by identity thieves. Businesses can now be subject to corporate identity theft as well. You could wake up one day finding your business already accused of carrying out illegal activities, a big chunk of your money gone, and your directors? seats already occupied by complete strangers.

To make things worse, corporate threats aren’t just coming from the outside.

Threats to corporate privacy, for instance, can come from within the organisation itself. Sensitive information like trade secrets and financial data are often leaked out (purposely or inadvertently) by employees. This is largely caused by the ever growing number of options for communications and transferring data (e.g. emails, instant messaging, blogs, social networking sites, ftp, P2P, etc.).

Greater challenges in designing, developing, and implementing policies and programs

Laws and regulations like SOX and Solvency II, which have direct impacts on IT, are on the rise. That is why corporate policies and programs now require sweeping changes. You now have to be more deliberate in integrating IT when establishing governance, internal controls, change management, incident management, and performance management.

A solid understanding on widely accepted frameworks and good practices like COBIT, COSO, and CMMI will help you considerably in such undertakings. Using these frameworks as guidelines will not only help you keep your policies and programs attuned to the times, they will also keep you in compliance with regulations.

Increasing demand for disaster recovery and business continuity capabilities

Every time you have a down time, you increase the probability of losing your customers to competitors. The longer the down time, the greater that probability becomes. Therefore, when a major disruption strikes, you should be able to recover at the soonest. If possible, you should be able to deliver products and services as usual.

This of course requires spending to increase your disaster recovery (DR) and business continuity (BC) capabilities. Are you ready for it? Migrating your IT infrastructure from traditional systems to the latest technologies that are better equipped for BC/DR requires careful planning and implementation to ensure an optimal return on investment.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?