Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Large scale corporate transformation

Large scale corporate transformation are the necessary actions required to increase performance in an organisation. It leads to greater performance results and greater organisational growth. It is a lasting change and can range from getting new leaders to combining the functions of different departments. It can also involve the introduction of a new phase in the life of an organisation. Large scale corporate transformation can be measured using three variables. The first variable involves determining how deep the change penetrates to all levels of the organisation. The second variable measures how entrenched it becomes in the organisation while the third measure determines the percentage of the organisation covered in the change.

Corporate transformation is essential for a company that seeks to have a greater impact and a longer life in its business sector. The process requires time and resources. The whole establishment needs to support it for success. Not only does the top management need to back it, but stockholders and staff members also need to buy the idea. This is because when the process of corporate transformation hits a barrier, it will take the entire organisation to keep it on course and complete the process. Without the support of everyone, most organisations will not complete the process.

Business transformation in recent times has begun to combine finance, HR and IT departments into one functioning piece of an organisation. This has resulted in leaner, faster, and more efficient corporate entities that produce high results and has a greater impact in its overall functioning. These three key departments are the backbone of any organisation, and the combination of the three creates an efficient organisation that translates into high performance results.

One crucial aspect of large scale corporate transformation is IT transformation, which entails the entire overhaul of any organisation’s technology systems. It adopts a more efficient platform that enhances its overall operation. IT transformation involves the use of Service Oriented Architecture (SOA) and open systems. This process is the revamping of the existing technology used to support the organisation and is critical for aligning the business functions to the mission of the organization. It touches on the current hardware and software and how they can best be improved upon for greater results. This process is necessary in the entire business transformation.

The question that needs to be addressed is how any organisation can make this process successful. First, it requires the understanding that it is not just a goal to be achieved, but a new way of thinking embraced by the entire organisation. Secondly, the leadership in place needs to be fully involved and dedicated to the process and to realise that it takes time and effort to complete such a mission. There also needs to be flexibility and adaptability in order to learn from mistakes and keep moving forward. Constant communication is also critical to ensure that everyone involved understands the current stage and the next steps to be done. Change is the only constant and is necessary for progress and success.

2015 ESOS Guidelines Chapter 6 – Role of Lead Assessor

The primary role of the lead assessor is to make sure the enterprise?s assessment meets ESOS requirements. Their contribution is mandatory, with the only exception being where 100% of energy consumption received attention in an ISO 50001 that forms the basis of the ESOS report.

How to Find a Lead Assessor

An enterprise subject to ESOS must negotiate with a lead assessor with the necessary specialisms from one of the panels approved by the UK government. This can be a person within the organisation or an third party. If independent, then only one director of the enterprise need countersign the assessment report. If an employee, then two signatures are necessary. Before reaching a decision, consider

  • Whether the person has auditing experience in the sector
  • Whether they are familiar with the technology and the processes
  • Whether they have experience of auditing against a standard

The choice rests on the enterprise itself. The lead assessor performs the appointed role.

The Lead Assessor?s Role

The Lead Assessor?s main job is reviewing an ESOS assessment prepared by others against the standard, and deciding whether it meets the requirements. They may also contribute towards it. Typically their role includes:

  • Checking the calculation for total energy consumption across the entire enterprise
  • Reviewing the process whereby the 90% areas of significant consumption were identified
  • Confirming that certifications are in place for all alternate routes to compliance chosen
  • Checking that the audit reports meet the minimum criteria laid down by the ESOS system

Note: A lead assessor may partly prepare the assessment themselves, or simply verify that others did it correctly.

In the former instance a lead assessor might

  • Determine energy use profiles
  • Identify savings opportunities
  • Calculate savings measures
  • Present audit findings
  • Determine future methodology
  • Define sampling methods
  • Develop audit timetables
  • Establish site visit programs
  • Assemble ESOS information pack

Core Enterprise Responsibilities

The enterprise cannot absolve itself from responsibility for good governance. Accordingly, it remains liable for

  • Ensuring compliance with ESOS requirements
  • Selecting and appointing the lead assessor
  • Drawing attention to previous audit work
  • Agreeing with what the lead assessor does
  • Requesting directors to sign the assessment

The Environment Agency does not provide assessment templates as it believes this reduces the administrative burden on the enterprises it serves.

Month End Accounting the way it should Be Today

Month end accounting has always been a business critical exercise. Without the balance sheet, income statement, and other financial reports this exercise ultimately produces, management could not make informed decisions to keep the company in the right direction and at the ideal operational speed.

Now, in order to maintain optimal business velocity, month end activities have to be carried out as swiftly and as accurately as possible. Delays will only inhibit managers from reacting and effecting necessary adjustments in time. Inaccurate information, on the other hand, obviously lead to bad decisions.

But that’s not all. Never has the month end close been as demanding as it is today. Regulations like the Sarbanes-Oxley Act, Solvency II, Dodd-Frank Act, and others, which call for more stringent controls and more robust risk management practices, are now forcing companies to find better ways to face the end of the month.

Sticking to old month-end practices while striving to achieve regulation compliance can either cost a company more (if they add manpower) or simply bog it down (if they don’t). Among the worst of these practices is the use of spreadsheets.

These User Developed Applications (UDAs) are very susceptible to errors. (See spreadsheet risks)

What’s more, consolidating data from spreadsheets as well as carrying out reconciliations on them is very time consuming. These activities usually require data from outside sources – i.e. a workstation in a different department, building, or (in the case of really large corporations) geographical locations.

Furthermore, if one of these sources fail, the financial reports won’t be complete. This is not a far-fetched scenario, considering that spreadsheet storage and backup is typically carried out by the average end user. This leaves the spreadsheet data vulnerable to hard disk crashes, virus attacks, and unexpected disasters.

Thus, in order to produce accurate financial reports on time all the time, you need a financial/IT solution that offers optimal provisions for risk management, collaboration, backup, and business continuity. Learn about server-based solutions and discover a better way to carry out month end accounting.

Ready to work with Denizon?