Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Disadvantages of Spreadsheets – Obstacles to Compliance in the Healthcare Industry

Most of the regulatory compliance issues we talked about concerning spreadsheets have been related to financial data. But there are other kinds of data that are stored in spreadsheets which may also cause regulatory problems in the future.

In the US, a legislation known as HIPAA or Health Insurance Portability and Accountability Act is changing the way health care establishments and practitioners handle patient records. The HIPAA Privacy Rule is aimed at protecting the privacy of individually identifiable health information a.k.a. protected health information (PHI).

Examples of PHI include common identifiers like a patient’s name, address, Social Security Number, and so on, which can be used to identify the patient. HIPAA covers a wide range of health care organisations and service providers, including: health plan payers, health care clearing houses, hospitals, doctors, dentists, etc.

To protect the confidentiality, integrity, and availability of PHI, covered entities are required to implement technical policies such as access controls, authentication, and audit controls. These can easily be implemented on server-based systems.

Sad to say, many health care organisations who have started storing data electronically still rely on spreadsheet-based systems. Those policies are hard to implement in spreadsheet-based systems, where files are handled by end-users who are overloaded with their main line of work (i.e. health care) and have very little concern for data security.

In some of these systems, spreadsheet files containing PHI may have multiple versions in different workstations. Chances are, none of these files have any access control or user authentication mechanism whatsoever. Thus, changes can easily be made without proper documentation as to who carried out the changes.

And because the files are normally easily accessible, unauthorised disclosures – whether done intentionally or accidentally – will always be a lingering threat. Remember that HIPAA covered entities who are caught disclosing PHI can be fined from $50,000 up to $500,000 plus jail time.

But that’s not all. Through the HITECH Act of 2009, business associates of covered entities will now have to comply with HIPAA standards as well. Business associates are those companies who are performing functions and services for covered entities.

Examples of business associates are accounting firms, law firms, consultants, and so on. They automatically need to comply with the standards the moment they too deal with PHI.

 

More Spreadsheet Blogs

 

Spreadsheet Risks in Banks

 

Top 10 Disadvantages of Spreadsheets

 

Disadvantages of Spreadsheets – obstacles to compliance in the Healthcare Industry

 

How Internal Auditors can win the War against Spreadsheet Fraud

 

Spreadsheet Reporting – No Room in your company in an age of Business Intelligence

 

Still looking for a Way to Consolidate Excel Spreadsheets?

 

Disadvantages of Spreadsheets

 

Spreadsheet woes – ill equipped for an Agile Business Environment

 

Spreadsheet Fraud

 

Spreadsheet Woes – Limited features for easy adoption of a control framework

 

Spreadsheet woes – Burden in SOX Compliance and other Regulations

 

Spreadsheet Risk Issues

 

Server Application Solutions – Don’t let Spreadsheets hold your Business back

 

Why Spreadsheets can send the pillars of Solvency II crashing down

?

Advert-Book-UK

amazon.co.uk

?

Advert-Book-USA

amazon.com

 

What Kanban can do for Call Centre Response Times

When a Toyota industrial engineer named Taiichi Ohno was investigating ways to optimise production material stocks in 1953, it struck him that supermarkets already had the key. Their customers purchased food and groceries on a just-in-time basis, because they trusted continuity of supply. This enabled stores to predict demand, and ensure their suppliers kept the shelves full.

The Kanban system that Taiichi Ohno implemented included a labelling system. His Kanban tickets recorded details of the factory order, the delivery destination, and the process intended for the materials. Since then, Ohno?s system has helped in many other applications, especially where customer demand may be unpredictable.

Optimising Workflow in Call Centres
Optimising workflow in call centres involves aiming to have an agent pick up an incoming call within a few rings and deal with it effectively. Were this to be the case we would truly have a just-in-time business, in which operators arrived and left their stations according to customer demand. For this to be possible, we would need to standardise performance across the call centre team. Moving optimistically in that direction we would should do these three things:

  • Make our call centre operation nimble
  • Reduce the average time to handle calls
  • Decide an average time to answer callers

When we have done that, we are in a position to apply these norms to fluctuating call frequencies, and introduce ?kanbanned? call centre operators.

Making Call Centre Operations Nimble
The best place to start is to ask the operators and support staff what they think. Back in the 1960?s Robert Townsend of Avis Cars famously said, ?ask the people ? they know where the wheels are squeaking? and that is as true as ever.

  1. Begin by asking technical support about downtime frequencies, duration, and causes. Given the cost of labour and frustrated callers, we should have the fastest and most reliable telecoms and computer equipment we can find.
  1. Then invest in training and retraining operators, and making sure the pop-up screens are valuable, valid, and useful. They cannot do their job without this information, and it must be at least as tech-savvy as their average callers are.
  1. Finally, spruce up the call centre with more than a lick of paint to awaken a sense of enthusiasm and pride. Find time for occasional team builds and fun during breaks. Tele-operators have a difficult job. Make theirs fun!

Reducing Average Time to Handle Calls
Average length of contact is probably our most important metric. We should beware of shortening this at the cost of quality of interaction. To calculate it, use this formula:

Total Work Time + Total Hold Time + Total Post Call Time

Divided By

Total Calls Handled in that Period

Share recordings of great calls that highlight how your best operators work. Encourage role-play during training sessions so people learn by doing. Publish your average call-handling time statistics. Encourage individual operators to track how they are doing against these numbers. Make sure your customer information is up to date. While they must confirm core data, limit this so your operators can get down to their job sooner.

Decide a Target Time to Answer Calls
You should know what is possible in a matter of a few weeks. Do not attempt to go too tight on this one. It is better to build in say 10% slack that you can always trim in future. Once you have decided this, you can implement your Kanban system.

Introducing Kanban in Your Call Centre Operation
Monitor your rate of incoming calls through your contact centre, and adjust your operator-demand metric on an ongoing basis. Use this to calculate your over / under demand factor. Every operator should know the value on this Kanban ticket. It will tell them whether to speed up a little, or slow down a bit so they deliver the effort the call rate demands. It will also advise the supervisor when to call up reserves.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Saving Energy Step 1 ? Implementing a Management System

There has been much hype down the years regarding whether management is art or science. Thankfully, where people are concerned the pendulum has swung away from standard times in sweatshops in the west. However, when it comes to measuring physical things like harvest per square meter and the amount of energy consumed there is no substitute for scientific measurement, and this implies a system.

Managing energy cost and consumption down is like any other strategy. American engineer / statistician / management consultant W. Edwards Demming may have passed on in 1993. However he was as right as ever when he said:

  1. When people and organizations focus primarily on quality, this tends to increase and costs fall over time.
  1. However, when people and organizations focus primarily on costs, costs tend to rise and quality declines over time.

Demming believed that 90% of organizational problems arise from systems we put in place ourselves. This can be because we are so accustomed to them that we fail to notice when they are no longer relevant. The currently prevailing laissez faire towards energy is a case in point. What is managed improves and what is not, deteriorates. We know this. Let us take a look at how to apply this principle to energy management.

First, you need to get the subject out the closet and talk about it. How often do you do this is your boardroom, and how does energy rank against other priorities? Good governance is about taking up a position and following through on it. Here is a handy checklist you may like to use.

  • Do we use a consistent language when we talk about energy? Is it electricity, or carbon emitted (or are we merely fretting over cost).
  • How well engaged are we as a company? Looking up and down and across the organization are there points where responsibility stops.
  • How well have we defined accountability? Do we agree on key performance areas and how to report on them.
  • Are we measuring energy use at each point of the business? When did we last challenge the assumption that ?we’re doing okay?.
  • Have we articulated our belief that quality is endless improvement, or are we simply chasing targets because someone says we should.

A management system is a program of policies, processes and methods to ensure achievement of goals. The next blog focuses on tools and techniques that support this effort.

Ready to work with Denizon?