Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

2015 ESOS Guidelines Chapter 7, 8 & 9 – Sign-Off, Compliance & Appeals

This is the final chapter in our series of short posts summarising the quite complex ESOS guidelines (click on ?Comply with ESOS? to see the details). This one addresses the legalities to follow to complete your report – and how to appeal if you are not happy with any of the Environment Agency?s decisions.

  1. Director Sign-Off

This is by no means an easy ride. Confirmation of the work at individual or lead assessor level locks the company into the penalty cycle in the event there are significant irregularities. By signing off the assessment, the board level director(s) # agree that they have

  • Reviewed the enterprise?s ESOS recommendations
  • Believe the enterprise is within the scope of the scheme
  • Believe the enterprise is compliant with the scheme
  • Believe the information provided is correct

Having an internal assessor requires a second board-level signature.

  1. Compliance

You report compliance on the internet. This is free and you can do it at any time within the deadline. You can dip in and out of the process as many times as you wish, but must use the link in the receipting email. While this is something a board member must do, there is no reason why the lead assessor should not complete the basics. The online compliance notification addresses the following topics:

  • The ESOS contact person in the enterprise
  • Any aggregation / dis-aggregation during the period
  • The names and contact details of the lead assessor
  • The proportion of energy consumption per compliance route

The Environment Agency will acknowledge receipt. This does not constitute acceptance. You should keep the ESOS evidence pack in a safe place with at least one backup elsewhere.

  1. Compliance & Enforcement Issues

In the event the Environment Agency decides your enterprise has not met ESOS requirements, it may either (a) issue a compliance notice with instructions, or (b) apply one of the following civil penalties:

  • A fine of up to ?5,000 for failure to maintain records
  • A fine of up to ?50,000 for failure to undertake an energy audit
  • A fine of up to ?50,000 for a false or misleading statement

Any enterprise has the right of appeal against government decisions. In the case of ESOS, this is via:

  • The First-Tier Tribunal if your enterprise is England, Wales or off-shore based
  • The Scottish Minister if your enterprise is based in Scotland
  • The Planning Commission if your enterprise is Northern Ireland-based

The notice you appeal against will supply details of the appeal steps to take.

This blog and its companion chapters concerning the ESOS Guidelines as amended 2015 are with compliments of ecoVaro. We are the people who break ESOS data into manageable chunks of information, so that board-level directors have greater confidence in what they sign.

Is Your Project Agile, a Scrum or a Kanban?

Few projects pan out the way we expect when starting out. This is normal in any creative planning phase. We half suspect the ones that follow a straight line are the exceptions to the rule. Urban legend has it; Edison made a thousand prototypes before his first bulb lit up, and then went on to comment, ?genius is 1% inspiration, 99% perspiration?. Later, he added that many of life’s failures are people who did not realise just how close they were to success when they gave up.

So be it to this day, and so be it with project planning too. There is no one size fits all approach when it comes to it. Agile, Scrum and Kanban each have their supporters and places where they do well. Project planning often works best when we use a sequential combination of them, appropriate to what is currently happening on the ground.

Of the three, Agile is by far the most comprehensive. It provides a structure that begins with project vision / conceptualisation, and goes as far as celebration when the job is over, and retrospective discussion afterwards. However, the emphasis on daily planning meetings may dent freethinking, and even smother it.

Scrum on the other hand says ?forget all that bureaucracy?. There is a job to do and today is the day we are going to do it. Although the core Agile teamwork is still there it ignores macro project planning, and could not be bothered with staying in touch with customers. If using Scrum, it is best to give those jobs to someone else.

The joker in the pack is Kanban, It believes that rules are there to substitute for thought, and that true progress only comes from responsible freedom. It belongs in mature organisations that have passed through Scrum and Agile phases and have embarked on a voyage towards perfection.

That said, there can be no substitute for human leadership, especially when defined as the social influence that binds the efforts of others towards a single task.

Migrating from CRM to Big Data

Big data moved to centre stage from being just another fad, and is being punted as the latest cure-all for information woes. It may well be, although like all transitions there are pitfalls. Denizon decided to highlight the major ones in the hope of fostering better understanding of what is involved.

Accurate data and interpretation of it have become increasingly critical. Ideas Laboratory reports that 84% of managers regard understanding their clients and predicting market trends essential, with accelerating demand for data savvy people the inevitable result. However Inc 5000 thinks many of them may have little idea of where to start. We should apply the lessons learned from when we implemented CRM because the dynamics are similar.

Be More Results Oriented

Denizon believes the key is focusing on the results we expect from Big Data first. Only then is it appropriate to apply our minds to the technology. By working the other way round we may end up with less than optimum solutions. We should understand the differences between options before committing to a choice, because it is expensive to switch software platforms in midstream. data lakes, hadoop, nosql, and graph databases all have their places, provided the solution you buy is scalable.

Clean Up Data First

The golden rule is not to automate anything before you understand it. Know the origin of your data, and if this is not reliable clean it up before you automate it. Big Data projects fail when executives become so enthused by results that they forget to ask themselves, ?Does this make sense in terms of what I expected??

Beware First Impressions

Big Data is just that. Many bits of information aggregated into averages and summaries. It does not make recommendations. It only prompts questions and what-if?s. Overlooking the need for the analytics that must follow can have you blindly relying on algorithms while setting your business sense aside.

Hire the Best Brains

Big Data?s competitive advantage depends on what human minds make with the processed information it spits out. This means tracing and affording creative talent able to make the shift from reactive analytics to proactive interaction with the data, and the customer decisions behind it.

If this provides a d?j? vu moment then you are not alone. Every iteration of the software revolution has seen vendors selling while the fish were running, and buyers clamouring for the opportunity. Decide what you want out first, use clean data, beware first impressions and get your analytics right. Then you are on the way to migrating successfully from CRM to Big Data.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?