Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

How Mid-South Metallurgical cut Energy Use by 22%

Mid-South in Murfreesboro, Tennessee operates a high-energy plant providing precision heat treatments for high-speed tools – and also metal annealing and straightening services. This was a great business to be in before the energy crisis struck. That was about the same time the 2009 recession arrived. In no time at all the market was down 30%.

Investors had a pile of capital sunk into Mid-South?s three facilities spread across 21,000 square feet (2,000 square meters) of enclosed space. Within them, a number of twenty-five horsepower compressors plus a variety of electric, vacuum and atmospheric furnaces pumped out heat 27/7, 52 weeks a year. After the company called in the U.S. Department of Energy for assistance, several possibilities presented.

Insulate the Barium Chloride Salt Baths

The barium chloride salt baths used in the heat treatment process and operating at 1600?F (870?C) were a natural choice, since they could not be cooled below 1200?F (650?C) when out of use without hardening the barium chloride and clogging up the system. The amount of energy taken to prevent this came down considerably after they covered and insulated them. The recurring annual electricity saving was $53,000.

Manage Electrical Demand & Power

The utility delivers 480 volts of power to the three plants that between them consume between 825- and 875-kilowatt hours depending on the season. Prior to the energy crisis Mid-South Metallurgical regarded this level of consumption as a given. Following on the Department of Energy survey the company replaced the laminar flow burner tips with cyclonic burner ones, and implemented a number of other modifications to enhance thermal efficiency further. The overall natural gas reduction was 20%.

Implement Large Scale Site Lighting Upgrade

The 24/7 nature of the business makes lighting costs a significant factor. Prior to the energy upgrade this came from 44 older-type 400-watt metal halide fixtures. By replacing these with 88 x 8-foot (2.5 meter) fluorescent fittings Mid-South lowered maintenance and operating costs by 52%

The Mid-South Metallurgical Trophy Cabinet

These three improvements cut energy use by 22%, reduced peak electrical demand by 21% and brought total energy costs down 18%. Mid-South continues to monitor energy consumption at each strategic point, as it continues to seek out even greater energy efficiency in conjunction with its people.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
ESOS Facts on a Page

The UK?s ESOS energy saving program stands for ?Energy Savings Opportunity Scheme?. Its purpose is to reduce demand – and hence fossil-based pollution at both ends of the supply chain. It currently applies to large UK companies only. However its guidelines are also valuable input to smaller firms voluntarily going greener.

The program threshold is 250 employees and / or turnover or at least ?UK50 million. This affects approximately 9,000 UK firms, with others below the threshold wondering whether the government plans to lower it. In essence, ESOS requires that qualifying businesses complete comprehensive audits of energy use and opportunities at least every fourth year.

The plan is carrot and stick. Compliant companies will probably uncover significant savings when they stop and measure. They may even unearth carbon credits they can sometime exchange for cash. Reactionary firms who try to duck the issue will feel Her Majesty?s wrath through stiff penalties. In time, they may find it harder to attract investors. If ESOS affects your company, then the wise thing could be complying by the first deadline of 5 December 2015.

To do so, you must conduct an energy audit and report it to the UK Environment Agency. This comprises

  1. Measuring total energy use across processes, transport and facilities
  2. Pie charting 90% of this to identify areas that are energy intensive
  3. Singling out cost-effective energy-saving projects in high use areas
  4. Submitting your report to the Environment Agency ahead of the deadline

ecoVaro recommends affected companies do not leave this to the last minute. While having ISO 50001 may exempt some from ESOS, the regulations are far from straightforward and it will take months to reach complete clarification. We would like to suggest a more balanced approach.

ESOS is a wonderful incentive to save energy costs while contributing to a better future for the kids. The Energy Savings Opportunity Scheme is precisely that. The cost of energy has crept up on us to the extent that we have to do something, government or no government.

Measuring energy consumption is as simple as installing meters at critical points in the flow, and you probably have many of them anyway. Once you have your data you no longer have to crunch the numbers. ecoVaro can do this for you and return the result in the form of handy graphs and spreadsheets.

Saving Energy Step 5 – Bringing it together

We hope you have been enjoying our series of short posts regarding saving energy, so what we use we can sustain. We have tried to make a dry subject interesting. After you read this post please comment, and tell us how it went. We are in the environment together. As the man who wrote ?No Man is an Island? said, ?if a clod be washed away somewhere by the sea, Europe is the less? and Europe was his entire world.

The 4 Steps we wrote about previously have a multiplier effect when we harness them together

  1. Having a management system diffuses office politics and pins accountability in a way that not even a worm could wriggle
  2. This defines the boundaries for senior managers and empowers them to implement practical improvements with confidence
  3. The results feed back into lower energy bills: this convinces the organisation that more is possible
  4. This dream filters through all levels of the organisation, as a natural team forms to make work and home a better place.

None of this would be possible without measuring energy consumption throughout the process, converting this into meaningful analytics, and playing ?what-if? scenarios against each other to determine where to start.

The 5th Step to Energy Saving that brings the other four together can double the individual benefits as innovative power flows between them. The monetary savings are impressive and provide capital to go even further. Why not allow us to help you manage what we measure together.

ecoVaro turns your numbers into meaningful analytics, makes suggestions, and stays with you so we can quantify your savings as you make them. We should talk about this soon.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?