Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

2015 ESOS Guidelines Chapter 2 – Deadlines and Status Changes

The ESOS process is deadline driven and meeting key dates is a non-negotiable. The penalties for not complying / providing false or misleading information are ?50,000 each. Simply not maintaining adequate records could cost you ?5,000. The carrot on the end of the stick is the financial benefits you stand to gain.

Qualifying for inclusion under the ESOS umbrella depends on the status of your company in terms of employee numbers, turnover and balance sheet on 31 December 2014. Regardless of whether you meet the 2014 threshold or not, you must reconsider your situation on 31 December 2018, 2022 and 2026.

Compliance Period Qualification Date Compliance Period Compliance Date
1 31 December 2014 From 17 July 2014* to 5 December 2015 5 December 2015
2 31 December 2018 From 6 December 2015 to 5 December 2019 5 December 2019
3 31 December 2022 From 6 December 2019 to 5 December 2023 5 December 2023
4 31 December 2026 From 6 December 2023 to 5 December 2027 5 December 2027

Notes:

1. The first compliance period begins on the date the regulations became effective

2. Energy audits from 6 December 2011 onward may go towards the first compliance report

Changes in Organisation Status

If your organisation status changes after a qualification date when you met compliance thresholds, you are still bound to complete your ESOS assessment for that compliance period. This is regardless of any change in size or structure. Your qualification status then remains in force until the next qualification date when you must reconsider it.

Authentication and Access Control

Threats to your data can come from external or internal sources.

  1. There are individuals who don’t have the authorisation but are driven by malicious intentions to gain access to certain information. This may refer to individuals who already belong to your organisation (but don’t have the necessary access rights) as well as those who don’t.
  2. There are individuals who have both the authorisation and, unfortunately, the malicious intentions over certain information.
  3. Finally, there are individuals who have the authorisation, no malicious intentions, but have accidentally exposed the information in question to those without the proper authority.

While curbing threats 2 and 3 would require other methods, threat #1 can be countered if the right authentication and access control systems are in place.

Here’s what we can do for you:

  • Work with your key personnel to determine who gets access to what.
  • Help you decide whether a single factor or a two-factor authentication (2FA) is appropriate for your organisation and recommend which factors are most suitable. Login methods may include but are not limited to the following:
    • biometric devices
    • Kerberos tickets
    • mobile phones
    • passwords
    • PKI certificates
    • proximity cards
    • smart cards
    • tokens
  • Install the necessary infrastructure needed for the factors chosen. For instance, if you opt to use biometrics, then biometric scanners will be installed. We’ll make sure that the authentication terminals are situated in places where achieving optimal traffic and work flow has been taken into consideration.

Other defences we’re capable of putting up include:

Enhance and Streamline IT Processes

You can’t be assured of a competitive advantage by just buying the latest technology. Your top competitor can easily match that feat by simply spending as much on the same tools. To be always at least a step ahead, you’ll need to perform tweaks on your IT processes aligned with the strengths of your organisation.

IT solutions are like a pair of sneakers. If they fit perfectly, they’ll help you run the extra mile. If they don’t, you can develop blisters faster than you can reach a single mile.

In all our efforts to enhance and streamline your IT processes, we’ll start by looking at all your logistical advantages, limitations, and objectives to determine which technologies suit you best. Once we’ve obtained them, we’ll perform the appropriate customisation to make them perform optimally under the conditions unique to your organisation.

Below are just some of the enhancements we can apply to your organisation:

  • Put up application and systems monitoring to identify bottlenecks and underutilised resources in your IT infrastructure.
  • Propose areas where you can plough back the generated savings to further improve your ROI.
  • Take scalability into consideration when pushing for certain IT investments to ensure that the IT solution will work for your organisation not only today but even as your organisation grows.
  • Introduce mobile-capable enterprise-class IT solutions that allow seamless collaboration between team members working at different locations on the globe so that pressing matters can be resolved and decisions can be arrived at as quickly as possible.
  • Integrate Business Intelligence into your IT system so that massive collections of data can be processed into insightful information which managers can draw on to make intuitive decisions.
  • Introduce avant-garde solutions, like virtualisation and infrastructure sharing, which may require large scale changes but can also significantly reduce operational costs.

Find out how we can increase your efficiency even more:

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?