Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

How COBIT helps you achieve SOX Compliance

First released way back in 1996, COBIT has already been around for quite a while. One reason why it never took off was because companies were never compelled to use it ? until now. Today, many CEOs and CIOs are finding it to be a vital tool for achieving SOX compliance in IT.

Thanks to SOX, COBIT (Control Objectives for Information and related Technology) is now one of the most widely accepted source of guidance among companies who have IT integrated with their accounting/financial systems. It has also gained general acceptability with third parties and regulators. But how did this happen?

Role of control frameworks in SOX compliance

You see, the Sarbanes-Oxley Act, despite having clearly manifested the urgency of establishing effective internal controls, does not provide a road map for you to follow nor does it specify a yardstick to help you determine whether an acceptable mileage in the right direction has already been achieved.

In other words, if you were a CIO and you wanted to find guidance on what steps you had to take to achieve compliance, you wouldn’t be able to find the answers in the legislation itself.

That can be a big problem. Two of your main SOX compliance obligations as a CEO or CIO is to assume responsibility in establishing internal controls over financial reporting and to certify their effectiveness. After that, the external auditors are supposed to attest to your assertions. Obviously, there has to be a well-defined basis before you can make such assertions and auditors can attest to anything.

In the language of auditors, this ?well-defined basis? is known as a control framework. Simply put, once you certify the presence of adequate internal controls in your organisation, the external auditor will ask, ?What control framework did you use??

Knowing what control framework you employed will help external auditors determine how to proceed with their evaluations and tests. For your part, a control framework can serve as a guide to help you work towards specific objectives for achieving compliance. Both of you can use it as a common reference point before drawing any conclusions regarding your controls.

But there are many control frameworks out there. What should you use?

How SOX, COSO, and COBIT fit together

Fortunately, despite SOX?s silence regarding control frameworks, you aren’t left entirely to your own devices. You could actually take a hint from the SEC and PCAOB, two of the lead organisations responsible for implementing SOX. SEC and PCAOB point to the adoption of any widely accepted control framework.

In this regard, they both highly endorse COSO, a well-established internal control framework formulated by the Committee of Sponsoring Organisations of the Treadway Commission (COSO). Now, I must tell you, if you’re looking specifically for instructions pertaining to IT controls, you won’t find those in COSO either.

Although COSO is the most established control framework for enterprise governance and risk management you’ll ever find (and in fact, it’s what we recommend for your general accounting processes), it lacks many IT-related details. What is therefore needed for your IT processes is a framework that, in addition to being highly aligned with COSO, also provides more detailed considerations for IT.

This is where COBIT fits the bill.

How COBIT can contribute to your regulatory compliance endeavors

COBIT builds upon and adheres with COSO while providing a finer grain of detail focused on IT. You can even find a mapping between COBIT IT processes and COSO components within the COBIT document itself.

Designed with regulatory compliance in mind, COBIT lays down a clear path for developing policies and good practice for IT control, thus enabling you to bridge the gap between control requirements, technical issues, and business risks.

Some of the components you’ll find in COBIT include:

IT control objectives

These are statements defining specific desired results that, as a whole, characterise a well-managed IT process. They come in two forms for each COBIT-defined IT process: a high-level control objective and a number of detailed control objectives. These objectives will enable you to have a sense of direction by telling you exactly what you need to aim for.

Maturity models

These are used as benchmarks that give you a relative measurement stating where your level of management or control over an IT process or high-level control objective stands. It serves as a basis for setting as-is and to-be positions and enables support for gap analysis, which determines what needs to be done to achieve a chosen level. Basically, if a control objective points you to a direction, then its corresponding maturity model tells you how far in that direction you’ve gone.

RACI charts

These charts tell you who (e.g. CEO, CFO, Head of Operations, Head of IT Administration) should be Responsible, Accountable, Consulted, and Informed for each activity.

Goals and Metrics

These are sets of goals along with the corresponding metrics that allow you to measure against those goals. Goals and metrics are defined in three levels: IT goals and metrics, which define what business expects from IT; process goals and metrics, which define what the IT process should deliver to support It’s objectives; and activity goals and metrics, which measure how well the process is performing.

In addition to those, you’ll also find mappings of each process to the information criteria involved, IT resources that need to be leveraged, and the governance focus areas that are affected.

Everything is presented in a logical and manageable structure, so that you can easily draw connections between IT processes and business goals, which will in turn help you decide what appropriate governance and control is needed. Ultimately, COBIT can equip you with the right tools to maintain a cost-benefit balance as you work towards achieving SOX compliance.

How to create a custom form with Field Elite

A common requirement for most Field Service Workers is to complete various forms and paper based inspection checklists when visiting customer sites and remote area locations.  Often the data collected is often used in collaboration efforts across multiple teams and organisations. 

Using paper forms, binders, cameras, and filing cabinets can make this process complicated, frustrating, and often, near impossible.

If you consider that, even though we are entering the third decade of the new millennium and despite the proliferation of Smart Phones and Tablet computing an incredibly large percentage of field service teams are still making use of paper based systems!

Read more about the benefits of digital forms data collection

Field Elite Customised forms

Field Elite enables Field Service organisations to easily create their own customised forms which can be attached jobs. 

The creation of forms can be done using the Web Based Administration Portal which is provided as standard to all customers when signing up for an account.

To access the form builder from Side Navigation navigate Settings –> Form Templates –> Create Form


You will then be presented with Form Builder utility which will contain an Empty Default Form and a list of fields types you are able to insert.

There are a variety of fields you can use to create all manner of forms. There is no restriction on the number of fields or field types you can choose to create forms suitable for your purpose.

If you can think it you can create it

In the example, we’ll work through, we are going to create a Simple Conference Room Inspection  Report, to be used by Facility Managers to assist in carrying room inspection reports for conference centres.

To add fields to your form simply Drag and Drop the fields onto the form.

Once you have completed adding which fields you require to your form and you are satisfied with the layout.

Select Settings tab to provide a meaningful name for your form.

You can also select a Form Layout you wish for your form.  For the purpose of this post we are going to leave it as Vertical.

Once you are satisfied with your form you can select Save Form 


Once your form has been saved it will be available for selection when defining jobs in the system.

Summary

It is really easy to define custom forms using the Field Elite from templates module.  The Form Template module enables you to create any manner of forms your organisation may require.

What Heijunka is & How it Smooths Call Centre Production

The Japanese word Heijunka, pronounced hi-JUNE-kuh means ?levelling? in the sense of balancing workflows. It helps lean organizations shift priorities in the face of fluctuating customer demand. The goal is to have the entire operation working at the same pace throughout, by continuously adjusting the balance between predictability, flexibility, and stability to level out demand.

Henry Ford turned the American motor manufacturing industry upside down by mass-producing his iconic black motor cars on two separate production lines. In this photograph, body shells manufactured upstairs come down a ramp and drop onto a procession of cars almost ready to roll in 1913.

Smoothing Production in the Call Centre Industry

Call Centres work best in small teams, each with a supervisor to take over complex conversations. In the past, these tended to operate in silos with each group in semi-isolation representing a different set of clients. Calls came through to operators the instant the previous ones concluded. By the law of averages, inevitably one had more workload than the rest at a particular point in time as per this example.

Modern telecoms technology makes it possible to switch incoming lines to different call centre teams, provided these are multi-skilled. A central operator controls this manually by observing imbalanced workflows on a visual system called a Heijunka Box. The following example comes from a different industry, and highlights how eight teams share uneven demand for six products.

This departure from building handmade automobiles allowed Henry to move his workforce around to eliminate bottlenecks. For example, if rolls of seat leather arrived late he could send extra hands upstairs to speed up the work there, while simultaneously slowing chassis production. Ford had the further advantage of a virtual monopoly in the affordable car market. He made his cars at the rate that suited him best, with waiting lists extending for months.

A Modern, More Flexible Approach

Forces of open competition and the Six Sigma drive for as-close-to-zero defects dictates a more flexible approach, as embodied in this image published by the Six Sigma organisation. This represents an ideal state. In reality, one force usually has greater influence, for example decreasing stability enforces a more flexible approach.

Years ago, Japanese car manufacturer Toyota moved away from batching in favour of a more customer-centric approach, whereby buyers could customise orders from options held in stock for different variations of the same basic model. The most effective approach lies somewhere between Henry Ford?s inflexibility and Toyota?s openness, subject to the circumstances at the moment.

A Worked Factory Example

The following diagram suggests a practical Heijunka application in a factory producing three colours of identical hats. There are two machines for each option, one or both of which may be running. In the event of a large order for say blue hats, the company has the option of shifting some blue raw material to the red and green lines so to have the entire operation working at a similar rate.

Predictability, Flexibility, and Stability at Call Centre Service

The rate of incoming calls is a moving average characterised by spikes in demand. Since the caller has no knowledge whether high activity advisories are genuine, it is important to service them as quickly as possible. Lean process engineering provides technology to facilitate flexibility. Depending on individual circumstances, each call centre may have its own definition of what constitutes an acceptably stable situation.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?