Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Why Executives Fail & How to Avoid It

The ?Peter Principle? concerning why managers fail derives from a broader theory that anything that works under progressively more demanding circumstances will eventually reach its breaking point and fail. The Spanish philosopher Jos? Ortega y Gasset, who was decidedly anti-establishment added, “All public employees should be demoted to their immediately lower level, as they have been promoted until turning incompetent”.

The Peter Principle is an observation, not a panacea for avoiding it. In his book The Peter Principle Laurence J. Peter observes, “In a hierarchy every employee tends to rise to his level of incompetence … in time every post tends to be occupied by an employee who is incompetent to carry out its duties … Work is accomplished by those employees who have not yet reached their level of incompetence.”

Let’s find out what the drivers are behind a phenomenon that may be costing the economy grievously, what the warning signs are and how to try to avoid getting into the mess in the first place.

Drivers Supporting the Peter Principle

As early as 2009 Eva Rykrsmith made a valuable contribution in her blog 10 Reasons for Executive Failure when she observed that ?derailed executives? often find themselves facing similar problems following promotion to the next level:

The Two Precursors

  • They fail to establish effective relationships with their new peer group. This could be because the new member, the existing group, or both, are unable to adapt to the new arrangement.
  • They fail to build, and lead their own team. This could again be because they or their subordinates are unable to adapt to the new situation. There may be people in the team who thought the promotion was theirs.

The Two Outcomes

  • They are unable to adapt to the transition. They find themselves isolated from support groups that would otherwise have sustained them in their new role. Stress may cause errors of judgement and ineffective collaboration.
  • They fail to meet business objectives,?but blame their mediocre performance on critical touch points in the organization. They are unable to face reality. Either they resign, or they face constructive dismissal.

The Warning Signs of Failure

Eva Rykrsmith suggests a number of indicators that an individual is not coping with their demanding new role. Early signs may include:

  • Lagging energy and enthusiasm as if something deflated their ego
  • No clear vision to give to subordinates, a hands-off management style
  • Poor decision-making due to isolation from their teams? ideas and knowledge
  • A state akin to depression and acceptance of own mediocre performance

How to Avoid a ?Peter? in Your Organization

  • Use succession planning to identify and nurture people to fill key leadership roles in the future. Allocate them challenging projects, put them in think tanks with senior employees, find mentors for them, and provide management training early on. When their own manager is away, appoint them in an acting role. Ask for feedback from all concerned. If this is not positive, perhaps you are looking at an exceptional specialist, and not a manager, after all.
  • Consider the future, and not the past when interviewing for a senior management position. Ask about their vision for their part of the organization. How would they go about achieving it? What would the roles be of their subordinates in this? Ask yourself one very simple question; do they look like an executive, or are you thinking of rewarding loyalty.
  • How to Avoid Becoming a ?Peter??Perhaps you are considering an offer of promotion, or applying for an executive job. Becoming a ?Peter? at a senior level is an uncomfortable experience. It has cost the careers of many senior executives dearly. We all have our level of competence where we enjoy performing well. It would be pity to let blind ambition rob us of this, without asking thoughtful questions first. Executives fail when they over-reach themselves, it is not a matter of bad luck.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Virtualisation

Using an IT solution that can provide the fastest (but still reliable) disaster recovery process is essential for the success of any business continuity plan. Although virtualisation is still considered leading edge technology by many business continuity specialists, it definitely brings a promise that, once fulfilled, can result in the cheapest, fastest, and most comprehensive solution for business continuity.

One great advantage of virtualisation over traditional BC (Business Continuity) methods is the relatively cheaper cost needed to achieve a certain level of business continuity assurance. Thus, more companies will find it easier to reach their required minimum for BC assurance. By contrast, some BCPs (Business Continuity Plan) based on a physical environment require companies to invest more than what they are willing to in order to reach the same minimum level of assurance.

Virtual machines, which can already encapsulate your operating systems and their corresponding applications, can be transported as a file from one machine running a compatible hypervisor to another. This makes the business continuity tasks of backup, replication, and restoration simpler and faster.

As of 2008, about 54% of IT professionals in Europe were willing to implement virtualisation within a maximum of two years. Furthermore, the expected compound annual growth rate of installed virtualised servers from 2008 to 2012 is already pegged at 33%.

If you want your organisation to take advantage of the benefits of this revolutionary technology, we’d be more than willing to help you discover what it can do for you. Then once you decide to make that transition to virtualisation, we can guide you every step of the way.

  • As not all applications are suited for virtualisation (e.g. some are too demanding on I/O and memory access), we’ll start by reviewing your entire IT system to see which portions can be implemented on a virtualized environment.
  • Using virtualisation and replication, we can conduct disaster recovery tests using up-to-date data without interrupting operations in your main IT site. Running these tests will increase your team’s preparedness and will allow you to discover possible weak points.
  • Provide a simple but comprehensive protection and backup system that encapsulates not only data, but also system configurations and application installations. This kind of setup allows for faster and easier disaster recovery operations. Because of these same characteristics, you can enjoy zero downtime while performing scheduled maintenance operations.
  • Since virtual machines are hardware-independent and transparent to operating systems, we can help you run a mix of legacy and new systems as well as open source and proprietary systems, allowing for more flexibility in your BCP budgeting.

We can also assist you with the following:

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
What Kanban can do for Call Centre Response Times

When a Toyota industrial engineer named Taiichi Ohno was investigating ways to optimise production material stocks in 1953, it struck him that supermarkets already had the key. Their customers purchased food and groceries on a just-in-time basis, because they trusted continuity of supply. This enabled stores to predict demand, and ensure their suppliers kept the shelves full.

The Kanban system that Taiichi Ohno implemented included a labelling system. His Kanban tickets recorded details of the factory order, the delivery destination, and the process intended for the materials. Since then, Ohno?s system has helped in many other applications, especially where customer demand may be unpredictable.

Optimising Workflow in Call Centres
Optimising workflow in call centres involves aiming to have an agent pick up an incoming call within a few rings and deal with it effectively. Were this to be the case we would truly have a just-in-time business, in which operators arrived and left their stations according to customer demand. For this to be possible, we would need to standardise performance across the call centre team. Moving optimistically in that direction we would should do these three things:

  • Make our call centre operation nimble
  • Reduce the average time to handle calls
  • Decide an average time to answer callers

When we have done that, we are in a position to apply these norms to fluctuating call frequencies, and introduce ?kanbanned? call centre operators.

Making Call Centre Operations Nimble
The best place to start is to ask the operators and support staff what they think. Back in the 1960?s Robert Townsend of Avis Cars famously said, ?ask the people ? they know where the wheels are squeaking? and that is as true as ever.

  1. Begin by asking technical support about downtime frequencies, duration, and causes. Given the cost of labour and frustrated callers, we should have the fastest and most reliable telecoms and computer equipment we can find.
  1. Then invest in training and retraining operators, and making sure the pop-up screens are valuable, valid, and useful. They cannot do their job without this information, and it must be at least as tech-savvy as their average callers are.
  1. Finally, spruce up the call centre with more than a lick of paint to awaken a sense of enthusiasm and pride. Find time for occasional team builds and fun during breaks. Tele-operators have a difficult job. Make theirs fun!

Reducing Average Time to Handle Calls
Average length of contact is probably our most important metric. We should beware of shortening this at the cost of quality of interaction. To calculate it, use this formula:

Total Work Time + Total Hold Time + Total Post Call Time

Divided By

Total Calls Handled in that Period

Share recordings of great calls that highlight how your best operators work. Encourage role-play during training sessions so people learn by doing. Publish your average call-handling time statistics. Encourage individual operators to track how they are doing against these numbers. Make sure your customer information is up to date. While they must confirm core data, limit this so your operators can get down to their job sooner.

Decide a Target Time to Answer Calls
You should know what is possible in a matter of a few weeks. Do not attempt to go too tight on this one. It is better to build in say 10% slack that you can always trim in future. Once you have decided this, you can implement your Kanban system.

Introducing Kanban in Your Call Centre Operation
Monitor your rate of incoming calls through your contact centre, and adjust your operator-demand metric on an ongoing basis. Use this to calculate your over / under demand factor. Every operator should know the value on this Kanban ticket. It will tell them whether to speed up a little, or slow down a bit so they deliver the effort the call rate demands. It will also advise the supervisor when to call up reserves.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?