Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

EcoVaro ? ESOS Solution on a Cloud

The UK?s Energy Saving Opportunity Scheme ? and all others in the EU stable – is bound to generate huge quantities of data beyond the reach of processing on standalone computers. This leaves some companies in the mandatory sector between a rock and a hard place. They already have to divert scarce talent to draft compliance reports. Now they face purchasing equipment with big data processing power.

The more astute are turning to cloud computing solutions like EcoVaro in increasing numbers. They are also keen to benefit from remote secure backup. .

Increasing migration to public clouds has caused a growth in niche big data consultants. EcoVaro is one of these. We want to do more than simply open up a port and leave you to become familiar with our technology. We service a growing group of companies who want us to analyse their energy usage reports, and isolate the main demand drivers so they know where to start saving.

We are consumer-centric energy consultants with the emphasis on corporates and sme?s. We offer more than just big data processing facilities. We also help set up your dashboard and are full of practical ideas you can use to start trimming energy costs right away. So please treat us as your affordable energy partner who really wants to help.

Finally, contact EcoVaro for a discussion.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Month End Accounting the way it should Be Today

Month end accounting has always been a business critical exercise. Without the balance sheet, income statement, and other financial reports this exercise ultimately produces, management could not make informed decisions to keep the company in the right direction and at the ideal operational speed.

Now, in order to maintain optimal business velocity, month end activities have to be carried out as swiftly and as accurately as possible. Delays will only inhibit managers from reacting and effecting necessary adjustments in time. Inaccurate information, on the other hand, obviously lead to bad decisions.

But that’s not all. Never has the month end close been as demanding as it is today. Regulations like the Sarbanes-Oxley Act, Solvency II, Dodd-Frank Act, and others, which call for more stringent controls and more robust risk management practices, are now forcing companies to find better ways to face the end of the month.

Sticking to old month-end practices while striving to achieve regulation compliance can either cost a company more (if they add manpower) or simply bog it down (if they don’t). Among the worst of these practices is the use of spreadsheets.

These User Developed Applications (UDAs) are very susceptible to errors. (See spreadsheet risks)

What’s more, consolidating data from spreadsheets as well as carrying out reconciliations on them is very time consuming. These activities usually require data from outside sources – i.e. a workstation in a different department, building, or (in the case of really large corporations) geographical locations.

Furthermore, if one of these sources fail, the financial reports won’t be complete. This is not a far-fetched scenario, considering that spreadsheet storage and backup is typically carried out by the average end user. This leaves the spreadsheet data vulnerable to hard disk crashes, virus attacks, and unexpected disasters.

Thus, in order to produce accurate financial reports on time all the time, you need a financial/IT solution that offers optimal provisions for risk management, collaboration, backup, and business continuity. Learn about server-based solutions and discover a better way to carry out month end accounting.

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Ready to work with Denizon?