Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

When Carrefour Pushed the Right Buttons

Retail giant Carrefour based in Boulogne Billancourt, France is big business in anybody?s numbers. Europe?s #1 retailer opened its first store in 1958 near a crossroads (Carrefour means ?crossroad? in French) and has largely not looked back since then. The slogan for the hypermarket chain with more than 1,500 outlets and close to a half million employees is ?choice and quality for everyone?. Our story begins when Carrefour decided these things belong at home too.

The company implemented a worldwide universal responsibility program firmly anchored on a tripod of goals for environmental, economic and social progress. Its first step was to appoint a five-person project team tasked with liaising with program delegates in all thirty countries in which it operates, and who had responsibility for driving these goals.

The team?s job was to make sure that policies, standards, procedures and key performance areas were common visions throughout Carrefour. By contrast, the local managers? were tasked with aligning these specifics to local conditions in terms of environmental, political and social issues. The project team checked the fit quarterly via video conferences.

The Triple Bottom Line Goals were woven through with Carrefour?s Seven Core Values, namely Freedom, Responsibility, Sharing, Respect, Integrity, Solidarity and Progress. Constant contact was maintained with staff and other stakeholders through ?awareness training? seminars and other dialogues. As the program took hold and flourished, it became evident that the retail giant needed help with managing the constant stream of metrics flowing in.

After reviewing options, Carrefour appointed a software provider to monitor progress against its primary focuses on energy, water, waste, refrigeration, paper, disposable checkout bags, hygiene & quality, management gender parity, disabled people and logistics. This enabled it to track progress online against past performance, and produce meaningful reports.

The Environmental Manager in the Corporate Sustainability Department waxed lyrical when he said, ?We believe that our sustainability strategy and software solution have powerfully improved collaboration, innovation, and overall performance?. He went on to describe how it was helping drive cost down and profitability up, while simultaneously growing brand.

Non-conformance costs can be high and run counter to the imperative to make a profit – while simultaneously ensuring a better world for our children?s children. In Carrefour?s case, having a consultant to measure progress was the key that unblocked the administrative bottleneck. Irish company Ecovaro does this for companies around the world. Click here. Discover what we will do for you.

2015 ESOS Guidelines Chapter 1 ? Who Qualifies

The base criteria are any UK undertaking that employs more than 250 people and/or has a turnover in excess of ?50 million and/or has a balance sheet total greater than ?43 million. There is little point in attempting to separate off high polluting areas. If one corporate group qualifies for ESOS, then all the others are obligated to take part too. The sterling equivalents of ?38,937,777 and ?33,486,489 were set on 31 December 2014 and apply to the first compliance period.

Representatives of Overseas Entities

UK registered branches of foreign entities are treated as if fully UK owned. They also have to sign up if any overseas corporate element meets the threshold no matter where in the world. The deciding factor is common ownership throughout the ESOS system. ecoVaro appreciates this. We have seen European companies dumping pollution in under-regulated countries for far too long.

Generic Undertakings that Could Comply

The common factor is energy consumption and the organisation’s type of work is irrelevant. The Environmental Agency has provided the following generic checklist of undertakings that could qualify:

Limited Companies Public Companies Trusts
Partnerships Private Equity Companies Limited Liability Partnerships
Unincorporated Associations Not-for-Profit Bodies Universities (Per Funding)

Organisations Close to Thresholds

Organisations that come close to, but do not quite meet the qualification threshold should cast their minds back to previous accounting periods, because ESOS considers current and previous years. The exact wording in the regulations states:

?Where, in any accounting period, an undertaking is a large undertaking (or a small or medium undertaking, as the case may be), it retains that status until it falls within the definition of a small or medium undertaking (or a large undertaking, as the case may be) for two consecutive accounting periods.?

Considering the ?50,000 penalty for not completing an assessment or making a false or misleading statement, it makes good sense for close misses to comply.

Joint Ventures and Participative Undertakings

If one element of a UK group qualifies for ESOS, then the others must follow suit with the highest one carrying responsibility. Franchisees are independent undertakings although they may collectively agree to participate. If trusts receive energy from a third party that must do an ESOS, then so must they. Private equity firms and private finance initiatives receive the same treatment as other enterprises. De-aggregations must be in writing following which separated ESOS accountability applies.

Business Turnaround Tip for a Successful MBO Turned Awry

When you acquire a company through an MBO, your hopes are always high. You know the business more than anyone else and you’ve got too much at stake to do a sloppy job. So how could things go wrong? Well sometimes they do. And if you don’t make a quick business turnaround, you could end up losing more than just your company.

If that management buyout was financed by a bank, then chances are you were required to invest a sizeable amount from your own pockets. I won’t be surprised if you even remortgaged your house for it.

Regardless of your source of funding, whether it was a bank, a venture capitalist or through a deferred consideration, the mere thought of losing your job and getting buried in enormous debt at the same time might be too much to bear. If you get too overwhelmed by your emotions and can’t think clearly, you’ll have to step out of the driver?s seat and have someone take over.

That someone can’t be a member of the management team that took part in the management buyout. Like you, he/she might be in panic mode as well. You need someone from the outside who has no emotional attachments to the company and hence can view the crisis from a clear perspective.

Here’s what’s needed:

Review and Plan

Take a closer look at all factors affecting your business: governance and organisational structures, employees, suppliers, systems and procedures, roles and responsibilities, etc. Identify potential risks and assess the likelihood of them affecting your business.

This will give a clearer picture of cause-and-effect relationships as well as the specific tasks on hand.

Thus, when it is time to draft a plan, you can do so from a well-informed standpoint. This will enable you to target specific areas of improvement and avoid pointless activities.

Assure all stakeholders

Once a watertight plan has been formulated, you will have to approach your stakeholders. They?ll need to know what your directions are. Once they’re all sold on the plan, you could implement our strategies unimpeded.

This is a very crucial part because a sceptical stakeholder can serve as a major stumbling block in our efforts to improve the situation. You need to convince your banks, sponsors, and investors in order to avoid additional financial obstacles. You need to convince your suppliers too. If they cut off or limit supply, you won’t be able to continue doing business.

Most of all, you need to persuade your staff and employees that the proposed major changes have to be carried out in order for the company to survive. You can’t run your operations without them on board.

Redesign and set up new systems and procedures

Any company requiring a turnaround will certainly have systems and procedures that are no longer working well in the current conditions and hence would require either major changes in key areas or a total revamp. You need to study personnel roles and responsibilities as well as systems and processes, including financial and IT systems, and supervise the implementation of necessary changes.

You will need to evaluate your existing IT architecture and determine how you can best maximise what you already have and propose what you think will work more efficiently for our proposed systems and procedures. Every piece of hardware or software recommended will take into consideration your present resources. There are many solutions out there, you just need to find the best fit.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?