Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Enhance and Streamline IT Processes

You can’t be assured of a competitive advantage by just buying the latest technology. Your top competitor can easily match that feat by simply spending as much on the same tools. To be always at least a step ahead, you’ll need to perform tweaks on your IT processes aligned with the strengths of your organisation.

IT solutions are like a pair of sneakers. If they fit perfectly, they’ll help you run the extra mile. If they don’t, you can develop blisters faster than you can reach a single mile.

In all our efforts to enhance and streamline your IT processes, we’ll start by looking at all your logistical advantages, limitations, and objectives to determine which technologies suit you best. Once we’ve obtained them, we’ll perform the appropriate customisation to make them perform optimally under the conditions unique to your organisation.

Below are just some of the enhancements we can apply to your organisation:

  • Put up application and systems monitoring to identify bottlenecks and underutilised resources in your IT infrastructure.
  • Propose areas where you can plough back the generated savings to further improve your ROI.
  • Take scalability into consideration when pushing for certain IT investments to ensure that the IT solution will work for your organisation not only today but even as your organisation grows.
  • Introduce mobile-capable enterprise-class IT solutions that allow seamless collaboration between team members working at different locations on the globe so that pressing matters can be resolved and decisions can be arrived at as quickly as possible.
  • Integrate Business Intelligence into your IT system so that massive collections of data can be processed into insightful information which managers can draw on to make intuitive decisions.
  • Introduce avant-garde solutions, like virtualisation and infrastructure sharing, which may require large scale changes but can also significantly reduce operational costs.

Find out how we can increase your efficiency even more:

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
2015 ESOS Guidelines Chapter 2 – Deadlines and Status Changes

The ESOS process is deadline driven and meeting key dates is a non-negotiable. The penalties for not complying / providing false or misleading information are ?50,000 each. Simply not maintaining adequate records could cost you ?5,000. The carrot on the end of the stick is the financial benefits you stand to gain.

Qualifying for inclusion under the ESOS umbrella depends on the status of your company in terms of employee numbers, turnover and balance sheet on 31 December 2014. Regardless of whether you meet the 2014 threshold or not, you must reconsider your situation on 31 December 2018, 2022 and 2026.

Compliance Period Qualification Date Compliance Period Compliance Date
1 31 December 2014 From 17 July 2014* to 5 December 2015 5 December 2015
2 31 December 2018 From 6 December 2015 to 5 December 2019 5 December 2019
3 31 December 2022 From 6 December 2019 to 5 December 2023 5 December 2023
4 31 December 2026 From 6 December 2023 to 5 December 2027 5 December 2027

Notes:

1. The first compliance period begins on the date the regulations became effective

2. Energy audits from 6 December 2011 onward may go towards the first compliance report

Changes in Organisation Status

If your organisation status changes after a qualification date when you met compliance thresholds, you are still bound to complete your ESOS assessment for that compliance period. This is regardless of any change in size or structure. Your qualification status then remains in force until the next qualification date when you must reconsider it.

Implementing Matrix Management

Matrix management is a culture change. More than the hierarchical structures, lines of responsibilities, modes of communication and channels of decision-making, it is a concept that needs to be planned ahead and managed appropriately over time.

Implementing matrix management to any organization can be confusing. It is essential to ensure that it fits right to your business strategies, skills and competencies. With this, realizing matrix management should not be taken lightly. Careful stages should be considered, instead.

Here are the steps to proper implementation of matrix management:

Consider Your Business Context

You need to evaluate your organisation to analyse what are your development needs with regards to skills, products, services and market environment. This will help you decide on what type of matrix structure you will apply in your organisation. Consider the following questions in building up your context:

  • What is our strategy?
  • Where are the demands in our business?
  • What are the structures that our competitors currently employ?
  • What are the talents that my people possess?
  • What are other business organizations doing?

Set Your Implementation Scope

Next, you need to define the parameter and set the scope of your implementation. What area in your business do you think matrix management will successfully work? There are several things that you need to consider in setting your scope. You have to make sure that it works well with your overall business strategies, that it can be excellently communicated and easily understood. Also, you must ensure that you acquire the necessary talents and skills in the business to deliver the new system of responsibilities.

Implement the New Structure

When you have already decided what structure type you will implement, you are ready to give it a go. You will need to establish new communication channels so you can monitor the progress and receive feedback effectively.

Here?s how to apply the matrix structure:

  • Highlight your development needs
  • Define roles based on outputs and not inputs
  • Line up procedures and systems to support the structure and the behaviour that comes with it.
  • Invest in training and development
  • Support the key people in the structure by coaching them to better adapt in changes
  • Communicate regularly
  • Monitor progress and make necessary adjustments

Review the Matrix Structure, Roles and Responsibilities

Organisations that successfully implement matrix management adapt to the changes in their environment. With this, they do regular evaluations to highlight the need for changes and revisions. The review can either focus on the structure only or to the entire process as a whole. The results can alter the structure, the roles involved and the responsibilities taken.

The process of implementing matrix management follows a step-by step method. Each stage is equally important with the rest. Hence, if you plan to exploit it in your organisation, you have to recognise the purpose of each step and follow it appropriately. Balance is the key. And when you achieve stability in matrix management, amidst the complex changes in the world of business, then your organisational success is just around the corner.

Ready to work with Denizon?