Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Finding the Best Structure for Your Enterprise Development Team

An enterprise development team is a small group of dedicated specialists. They may focus on a new business project such as an IoT solution. Members of microteams cooperate with ideas while functioning semi-independently. These self-managing specialists are scarce in the job market. Thus, they are a relatively expensive resource and we must optimise their role.

Organisation?Size and Enterprise Development Team Structure

Organisation structure depends on the size of the business and the industry in which it functions. An enterprise development team for a micro business may be a few freelancers burning candles at both ends. While a large corporate may have a herd of full-timers with their own building. Most IoT solutions are born out of the efforts of microteams.

In this regard, Bill Gates and Mark Zuckerberg blazed the trail with Microsoft and Facebook. They were both college students at the time, and both abandoned their business studies to follow their dreams. There is a strong case for liberating developers from top-down structures, and keeping management and initiative at arm?s length.

The Case for Separating Microteams from the?Organisation

Microsoft Corporation went on to become a massive corporate, with 114,000 employees, and its founder Bill Gates arguably one of the richest people in the world. Yet even it admits there are limitations to size. In Chapter 2 of its Visual Studio 6.0 program it says,

‘today’s component-based enterprise applications are different from traditional business applications in many ways. To build them successfully, you need not only new programming tools and architectures, but also new development and project management strategies.?

Microsoft goes on to confirm that traditional, top-down structures are inappropriate for component-based systems such as IoT solutions. We have moved on from ?monolithic, self-contained, standalone systems,? it says, ?where these worked relatively well.?

Microsoft’s model for enterprise development teams envisages individual members dedicated to one or more specific roles as follows:

  • Product Manager ? owns the vision statement and communicates progress
  • Program Manager ? owns the application specification and coordinates
  • Developer ? delivers a functional, fully-complying solution to specification
  • Quality Assurer ? verifies that the design complies with the specification
  • User Educator ? develops and publishes online and printed documentation
  • Logistics Planner ? ensures smooth rollout and deployment of the solution

Three Broad Structures for Microteams working on IoT Solutions

The organisation structure of an enterprise development team should also mirror the size of the business, and the industry in which it functions. While a large one may manage small microteams of employee specialists successfully, it will have to ring-fence them to preserve them from bureaucratic influence. A medium-size organisation may call in a ?big six? consultancy on a project basis. However, an independently sourced micro-team is the solution for a small business with say up to 100 employees.

The Case for Freelancing Individuals versus Functional Microteams

While it may be doable to source a virtual enterprise development team on a contracting portal, a fair amount of management input may be necessary before they weld into a well-oiled team. Remember, members of a micro-team must cooperate with ideas while functioning semi-independently. The spirit of cooperation takes time to incubate, and then grow.

This is the argument, briefly, for outsourcing your IoT project, and bringing in a professional, fully integrated micro-team to do the job quickly, and effectively. We can lay on whatever combination you require of project managers, program managers, developers, quality assurers, user educators, and logistic planners. We will manage the micro-team, the process, and the success of the project on your behalf while you get on running your business, which is what you do best.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
How Armstrong World Industries is going Cradle-to-Cradle

The Cradle-to-Cradle concept holds that human effort must be biometric, in other words enrich the environment within which it functions as opposed to breaking it down. This means manufacturing must be holistic in the sense that everything is reusable and nothing is destroyed. Armstrong World Industries was the first global mineral ceiling tile manufacturer to achieve Cradle-to-Cradle certification. We decided to take a closer look at how they achieved this.

Armstrong Worldwide Industries has five plants in the UK alone. These produce an annual turnover of ?2.7 billion. They have been making ceilings for more than 150 years. Fifteen years ago and way ahead of the curve it started recycling, and has maintained a policy of not charging contractors for waste ever since. Along the way, it developed a product that can be re-used indefinitely.

The Challenge

Going green must also be commercially sustainable. In Armstrong?s case, it faced a rise in landfill tax from ?8 per tonne per year to ?80 per tonne per year. This turned the financial cost of waste from a nuisance to a threat. It calculated that recycling one tonne of ceiling materials would:

  • Eliminate 456kg of CO2 equivalents by saving 1,390 kWh of electricity
  • Preserve 11 tons of virgin material and save 1,892 gallons of potable water

They hoped to extend their own recycling project by asking demolition and strip-out contractors to join it, so they could reprocess their scrap as new batches of tiles too.

The Achievement

As things stand today, an Armstrong ceiling tile now contains an average of 82% recycled content. Indeed, if they could find more ceilings to recycle this could reach 100%. In the past two years alone, Armstrong Worldwide Industries UK has saved 130,399m? of greenfield from landfill, being the equivalent of 520 skips that would otherwise have cost contractors over ?88,000 to dispose of.

The Broader Context

Armstrong Worldwide Industries is a global leader in water management, and is bent on minimising its reliance on fossil for energy. It has implemented online measurement systems that feed data to its corporate environmental, health and safety system. This empowers it to produce reports, track corrective actions and measure progress towards its overall goal of being carbon neutral.

Next time you sit beneath an Armstrong Worldwide Industries panelled ceiling, spare a thought for how much ecoVaro consumption analytics could contribute to your bottom line (and how it would feel to be lighter on carbon too).

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Key Steps to Complying with ESOS

Energy Savings Opportunity Scheme has already been launched. In fact, it is by now in its initial phase. However, many businesses are still not aware of the new scheme, especially those who are covered by the qualifications for ESOS. To help them understand what they need to do in compliance to the energy efficiency strategy, here are key steps they can follow along the way.

Measure Overall Energy Consumption

The first step to complying with ESOS is to make an initial estimate of the business? energy consumption. This includes measuring the use of electricity, renewable energy, combustible fuels and all other forms of energy consumed whether in buildings, transports and industrial processes.

Three important factors to consider are the measurement units used, the reference period and quality of data. Energy units, such as MWh and GJ, or energy expenditure costs should be applied. Business enterprises should also do the initial measurement within a reference period of 12 months. Moreover, data collected should be verifiable at hand.

Identify Areas of Significant Energy Consumption

When the total energy consumption for all the activities and assets has already been estimated, it’s then time to identify what areas in the organisation comprise the significant portion of the overall energy usage. The areas recognised should cover at least 90% of the overall consumption. Meaning to say, ESOS participants have the chance to omit 10% of the energy consumption and instead focus on the 90%. This would ensure that subsequent energy audits will be cost-effective and proportionate.

Consider and Choose Compliance Routes

In order to comply with ESOS, qualified businesses should consider what compliance routes to take. These routes include taking series of energy audits, operating and implementing a certified ISO 50001 energy management system, acquiring Display Energy Certificates (DECs) and working with Green Deal assessments. Whichever route the business takes, one should maintain credible evidences, along with helpful documents, to certify their compliance.

Report the Compliance

Except when the large enterprise covers all the significant areas of energy consumption by means of ISO 50001 certification, one should appoint a lead assessor to supervise, conduct and review the organisation’s chosen ESOS compliance route. In this case, the approved assessments should then be signed off at board level to ensure that the conclusions and recommendations for energy savings are properly carried. To confirm their compliance, the business should submit a formal notification to the Environment Agency.

Because ESOS is not just an opportunity but also an obligation, it designated compliance bodies and gave them the authority to file civil penalties towards those who fail to comply with the scheme. Not only that, these appropriate authorities have the right to publish information about non-compliant enterprises including their name, details of non-compliance and corresponding penalty amount. Among these UK compliance bodies are Natural Resources Wales, Environment Agency in England, The Scottish Environment Protection Agency (SEPA) and Northern Ireland Environment Agency.

So, if you are covered with the ESOS qualifications, make sure to be informed. As the famous saying goes, ?Ignorance of the law excuses no one.? Likewise, awareness of ESOS is a responsibility every large business in UK should give importance to.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?