Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

2015 ESOS Guidelines Chapter 2 – Deadlines and Status Changes

The ESOS process is deadline driven and meeting key dates is a non-negotiable. The penalties for not complying / providing false or misleading information are ?50,000 each. Simply not maintaining adequate records could cost you ?5,000. The carrot on the end of the stick is the financial benefits you stand to gain.

Qualifying for inclusion under the ESOS umbrella depends on the status of your company in terms of employee numbers, turnover and balance sheet on 31 December 2014. Regardless of whether you meet the 2014 threshold or not, you must reconsider your situation on 31 December 2018, 2022 and 2026.

Compliance Period Qualification Date Compliance Period Compliance Date
1 31 December 2014 From 17 July 2014* to 5 December 2015 5 December 2015
2 31 December 2018 From 6 December 2015 to 5 December 2019 5 December 2019
3 31 December 2022 From 6 December 2019 to 5 December 2023 5 December 2023
4 31 December 2026 From 6 December 2023 to 5 December 2027 5 December 2027

Notes:

1. The first compliance period begins on the date the regulations became effective

2. Energy audits from 6 December 2011 onward may go towards the first compliance report

Changes in Organisation Status

If your organisation status changes after a qualification date when you met compliance thresholds, you are still bound to complete your ESOS assessment for that compliance period. This is regardless of any change in size or structure. Your qualification status then remains in force until the next qualification date when you must reconsider it.

8 Reasons why you Need to Undertake Technical and Application Assessments

Are your information assets enabling you to operate more cost-effectively or are they just drawing in more risks than you are actually aware of? Obviously, you now need to get a better picture of those assets to see if your IT investments are giving you the benefits you were expecting and to help you identify areas where improvements should be made.

The best way to get the answers to those questions is through technical and application assessments. In this post, we?ll identify 8 good reasons why it is now imperative to undertake such assessments.

1. Address known issues – Perhaps the most common reason that drives companies to undertake a technology/application assessment is to identify the causes of existing issues such as those related to data accessibility, hardware and software scalability, and performance.

2. Cut down liabilities and risks – Unless you know what and where the risks are, there is no way you can implement an appropriate risk mitigation strategy. A technology and application assessment will enable you to thoroughly test and examine your information systems to see where your business-critical areas and points of failure are and subsequently allow you to act on them.

3. Discover emerging risks – Some risks may not yet be as threatening as others. But it would certainly be reassuring to be aware if any exist. That way, you can either nip them in the bud or keep them monitored.

4. Comply with regulations – Regulations like SOX require you to establish adequate internal controls to achieve compliance. Other regulations call for the protection of personally identifiable information. Assessments will help you pinpoint processes that lack controls, identify data that need protection, and areas that don’t meet regulatory requirements. This will enable you to act accordingly and keep your company away from tedious, time-consuming and costly sanctions.

5. Enhance performance – Poor performance is not always caused by an ageing hardware or an overloaded infrastructure. Sometimes, the culprits are: unsuitable configuration settings, inappropriate security policies, or misplaced business logic. A well-executed assessment can provide enough information that would lead to a more cost-effective action plan and help you avoid an expensive but useless purchase.

6. Improve interoperability – Disparate technologies working completely separate from each other may be preventing you from realising the maximum potential of your entire IT ecosystem. If you can examine your IT systems, you may be able to discover ways to make them interoperate and in turn harness untapped capabilities of already existing assets.

7. Ensure alignment of IT with business goals – An important factor in achieving IT governance is the proper alignment of IT with business goals. IT processes need to be assessed regularly to ensure that this alignment continues to exist. If it does not, then necessary adjustments can be made.

8. Provide assurance to customers and investors – Escalating cases of data breaches and identity theft are making customers and investors more conscious with a company?s capability of preserving the confidentiality of sensitive information. By conducting regular assessments, you can show your customers and investors concrete steps for keeping sensitive information confidential.

FUJIFILM Cracks the Energy Code

FUJIFILM was in trouble at its Dayton, Tennessee plant in 2008 where it produced a variety of speciality chemicals for industrial use. Compressed-air breakdowns were having knock-on effects. The company decided it was time to measure what was happening and solve the problem. It hoped to improve reliability, cut down maintenance, and eliminate relying on nitrogen for back-up (unless the materials were flammable).

The company tentatively identified three root causes. These were (a) insufficient system knowledge within maintenance, (b) weak spare part supply chain, and (c) generic imbalances including overstated demand and underutilised supply. The maintenance manager asked the U.S. Department of Energy to assist with a comprehensive audit of the compressed air system.

The team began on the demand side by attaching flow meters to each of several compressors for five days. They noticed that – while the equipment was set to deliver 120 psi actual delivery was 75% of this or less. They found that demand was cyclical depending on the production phase. Most importantly, they determined that only one compressor would be necessary once they eliminated the leaks in the system and upgraded short-term storage capacity.

The project team formulated a three-stage plan. Their first step would be to increase storage capacity to accommodate peak demand; the second would be to fix the leaks, and the third to source a larger compressor and associated gear from a sister plant the parent company was phasing out. Viewed overall, this provided four specific goals.

  • Improve reliability with greater redundancy
  • Bring down system maintenance costs
  • Cut down plant energy consumption
  • Eliminate nitrogen as a fall-back resource

They reconfigured the equipment in terms of lowest practical maintenance cost, and moved the redundant compressors to stations where they could easily couple as back-ups. Then they implemented an online leak detection and repair program. Finally, they set the replacement compressor to 98 psi, after they determined this delivered the optimum balance between productivity and operating cost.

Since 2008, FUJIFILM has saved 1.2 million kilowatt hours of energy while virtually eliminating compressor system breakdowns. The single compressor is operating at relatively low pressure with attendant benefits to other equipment. It is worth noting that the key to the door was measuring compressed air flow at various points in the system.

ecoVaro specialises in analysing data like this on any energy type.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?