Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

A Business Case for Sharing

We blogged about sharing services in a decentralised business context recently, and explained why we think why these should be IT-Based for speedy delivery. This is not to say that all shared services projects worldwide have been resounding successes. This is often down to the lack of a solid business case up front. We decided to lay out the logic behind this process.

Management Overview ? The overview includes a clear definition of why the current situation is unacceptable, the anticipated benefits of sharing, and an implementation plan were it to go ahead. The project should not proceed until the stakeholders have considered and agreed on this.

Alternatives Considered ? The next stage is to get closer to the other options in order to determine whether an alternative might perhaps be preferable. Substitutes for shared services are often doing nothing, improving the current method, and outsourcing the service to a third party.

The Bottom Line in Business ? Sharing services comes at an initial cost of infrastructure changes, and the impact on human capital (the latter deserves its own blog). The following need careful consideration from the financial angle:

Numbers to Work Through

  • Manpower to design and roll the project out in parallel with the existing organisation.
  • Capital for creating facilities at the central point including civil works, furniture and equipment and IT infrastructure.
  • The costs of travel, feeding and accommodation. These can be significant depending on the time that implementation takes.
  • The opportunity loss of diverting key staff – and the cost of temporary replacements – if appointing line staff to the project team.
  • Crystal-clear project metrics including (a) the direct, realisable savings (b) the medium and long-term effects on profit and (c) where to deploy the savings

Risk Management

Shared services projects don’t go equally smoothly, although planning should reduce the risk to manageable levels. Nonetheless it is important to imagine potential snags, decide how to mitigate them and what the cost might be.

We believe in implementing shared services on a pilot basis in the business unit that eventually provides them. We recommend building these out to other branches only when new processes are working smoothly.

Moving On From a Decision

We recommend you revisit your management overview, the logic behind it, the assumptions you made, and the costs and benefits you envisage before deciding to go ahead

The final step in proving a business case is doable should be fleshing out your roadmap into a detailed operations plan with dependencies on a spreadsheet.

What Sub-Metering did for Nissan in Tennessee

When Nissan built its motor manufacturing plant in Smyrna 30 years ago, the 5.9 million square-foot factory employing over 8,000 people was state of art. After the 2005 hurricane season sky-rocketed energy prices, the energy team looked beyond efficient lighting at the more important aspect of utility usage in the plant itself. Let’s examine how they went about sub-metering and what it gained for them.

The Nissan energy team faced three challenges as they began their study. They had a rudimentary high-level data collection system (NEMAC) that was so primitive they had to transfer the data to spread-sheets to analyse it. To compound this, the engineering staff were focused on the priority of getting cars faster through the line. Finally, they faced the daunting task of making modifications to reticulation systems without affecting manufacturing throughput. But where to start?

The energy team chose the route of collaboration with assembly and maintenance people as they began the initial phase of tracking down existing meters and detecting gaps. They installed most additional equipment during normal service outages. Exceptions were treated as minor jobs to be done when convenient. Their next step was to connect the additional meters to their ageing NEMAC, and learn how to use it properly for the first time.

Although this was a cranky solution, it had the advantage of not calling for additional funding which would have caused delays. However operations personnel were concerned that energy-saving shutdowns between shifts and over weekends could cause false starts. ?We’ve already squeezed the lemon dry,? they seemed to say. ?What makes you think there?s more to come??

The energy team had a lucky break when they stumbled into an opportunity to prove their point early into implementation. They spotted a four-hourly power consumption spike they knew was worth examining. They traced this to an air dryer that was set to cyclical operation because it lacked a dew-point sensor. The company recovered the $1,500 this cost to fix, in an amazing 6 weeks.

Suitably encouraged and now supported by the operating and maintenance departments, the Smyrna energy team expanded their project to empower operating staff to adjust production schedules to optimise energy use, and maintenance staff to detect machines that were running without output value. The ongoing savings are significant and levels of shop floor staff motivation are higher.

Let’s leave the final word to the energy team facilitator who says, ?The only disadvantage of sub-metering is that now we can’t imagine doing without it.?

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
How to create a custom form with Field Elite

A common requirement for most Field Service Workers is to complete various forms and paper based inspection checklists when visiting customer sites and remote area locations.  Often the data collected is often used in collaboration efforts across multiple teams and organisations. 

Using paper forms, binders, cameras, and filing cabinets can make this process complicated, frustrating, and often, near impossible.

If you consider that, even though we are entering the third decade of the new millennium and despite the proliferation of Smart Phones and Tablet computing an incredibly large percentage of field service teams are still making use of paper based systems!

Read more about the benefits of digital forms data collection

Field Elite Customised forms

Field Elite enables Field Service organisations to easily create their own customised forms which can be attached jobs. 

The creation of forms can be done using the Web Based Administration Portal which is provided as standard to all customers when signing up for an account.

To access the form builder from Side Navigation navigate Settings –> Form Templates –> Create Form


You will then be presented with Form Builder utility which will contain an Empty Default Form and a list of fields types you are able to insert.

There are a variety of fields you can use to create all manner of forms. There is no restriction on the number of fields or field types you can choose to create forms suitable for your purpose.

If you can think it you can create it

In the example, we’ll work through, we are going to create a Simple Conference Room Inspection  Report, to be used by Facility Managers to assist in carrying room inspection reports for conference centres.

To add fields to your form simply Drag and Drop the fields onto the form.

Once you have completed adding which fields you require to your form and you are satisfied with the layout.

Select Settings tab to provide a meaningful name for your form.

You can also select a Form Layout you wish for your form.  For the purpose of this post we are going to leave it as Vertical.

Once you are satisfied with your form you can select Save Form 


Once your form has been saved it will be available for selection when defining jobs in the system.

Summary

It is really easy to define custom forms using the Field Elite from templates module.  The Form Template module enables you to create any manner of forms your organisation may require.

Ready to work with Denizon?