Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

ESOS What is the Truth?

When the UK administration introduced its ESOS Energy Savings Opportunity Scheme reactions from business people followed a familiar theme.

  • Do nothing it will go away
  • The next Westminster will drop this
  • Another stealth tax. I don’t have time for this
  • Give the problem to admin and tell them to fix it

ecovaro decided to share three facts with you. These are

(1) ESOS is not a government money spinner

(2) all major political parties support it, and

(3) it is a cost-effective way to put money back in your pocket while feeling better about what business pumps into the environment.

Four More ESOS Facts

1. You Cannot Give the Problem to Admin ? Energy is technical. The lead belongs with your operations staff because they understand how your systems work. Some things are best outsourced though. ecovaro is here to help.

2. ESOS is Not Going to Go Away ? A company inside the regulation net must submit its first report by 6 December 2015. Non-compliance risks the following penalties:

  • ?5,000 for not maintaining adequate records
  • ?50,000 for not completing the assessment
  • ?50,000 for making a false or misleading statement

3. The Employee Count is the Annual Average – The employment criteria (unlike balance sheet and turnover) is the monthly average of full and part-time employees taken across the full financial year. The fact you have <250 employees in December 2015 when the first report is due does not necessarily let you off the hook.

4. The 6 December 2014 Report is No Big Deal ? When you think about it the administration is hardly likely to spend years wading through 9,000 detailed company energy plans. It has no authority to comment in any case. All that is required is for a senior director to confirm reading the document, and a lead assessor to agree it complies with the law.

Does this mean that ESOS is a damp squib? We do not think so, although some firms may take the low road. ecovaro believes the financial benefits will carry the process forward, and that the imperative to make the world a better place will do the rest.

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

What ISO 14001 Status did for Cummins Inc.

Cummins manufactures engines and power generation products, and has been a household name almost since inception in 1919. It sells its products in over 300 countries, through approximately 6,000 dealerships employing 40,000 people. Because its product line runs off fossil fuel it is under steady pressure to display a cleaner carbon footprint.

Cummins decided to go for the big one by qualifying for ISO 14001 certification. This is a subset of a family of standards relating to managing environmental impact while complying with all applicable legislation. In this sense, it is similar to the ISO 9000 quality management system, because it focuses on how products are produced (as opposed to how those products perform). Compliance with ISO 14001 was a doubly important goal, because it is part of the European Union?s Eco Management and Audit Scheme and fast becoming mandatory on suppliers to governments.

The qualification process follows the well-established principle of plan, do, check, act. It begins with gap analysis to detect materials and processes that affect the environment. This is followed by implementation of necessary changes affecting operations, documentation, emergency strategies and employee education. The third step involves measuring and monitoring performance. Finally, the project moves into a phase of ongoing maintenance, and continuous improvement as circumstances change.

In Cummins case, the project was almost worldwide and called for environmental, health and safety reporting throughout the organisation. The information was shared via a globally accessible document repository, and then processed centrally at the head office in Columbia, Indiana USA.

Measuring environmental performance almost inevitably has other benefits that make it doubly worthwhile. Speaking at the 2014 National Safety Council Congress after receiving the top award for excellence, Cummins chairman and ceo Tom Linebarger commented on a journey that was ?nothing short of amazing? yet wasn’t even a ?pathway to the finish line?.

?All of us feel like we have way more to do to make sure that our environment is as safe as it could be,? he added, ?so that our sustainability footprint is as good as it can be and that we continue to set more aggressive goals every year. That’s just how we think about it.? Linebarger concluded.

If you are taking your company on a journey to new heights of environmental excellence, then you should consider choosing ecoVaro as your travelling companion. We are environmental management specialists and have proprietary software geared to process your data. We also have a wealth of experience, and a treasure chest of roadmaps to help you achieve your goal.

Ready to work with Denizon?