Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

IT Transformation Defined

Businesses depend on IT to effectively manage business processes and to provide products and services to clients. As IT technologies advance, it is crucial that businesses update their hardware to remain competitive. But businesses should do more than simply upgrade their servers and should really strive to effect IT transformation.

What is IT Transformation?

IT transformation is the ongoing process of changing the way that a company uses IT to better align it with current business goals. Through the IT transformation process, businesses try to determine whether they are meeting mission-critical benchmarks through the incorporation of new IT technologies for corporate transformation.

For example, if one of the current business concerns is whether the company can improve customer service, the IT system will need to evolve in such a way that improves customer service in a measurable way.

Successfully Aligning the Technology to Business Goals

In order to successfully align the IT system with business goals, it is important to understand the newly integrated technologies to understand how they can change business processes. If a new feature is intended to make the server more secure, the management should know exactly how the feature will improve the security of the server and whether the new implementation is redundant.

Once the business objectives have been identified, IT transformation is carried out by changing both the software and hardware used by the company. An example would be the growing trend of server migration to the cloud. Cloud computing is the growing trend of making files and data accessible from anywhere. If an organisation believes that it can improve productivity through a server cloud migration, it will need a way to test this.

The IT Transformation Process

Given that IT transformation is directly related to the core business, the IT transformation process must begin by identifying which aspects of the company must be changed. Then, the company must determine?IT services that could potentially be integrated into the business in a way that will help the company achieve benchmarks. After the key decision-makers understand the IT network well enough to effectively implement it, the company must efficiently manage the transformation process. Then, after the IT has been integrated, the company must have a system in place to measure business transformation in a numerical way.

For example, when assessing customer satisfaction, one effective strategy would be to distribute customer satisfaction surveys that ask customers to rate their experiences on a scale of one to ten. The company can then measure the results of the customer satisfaction survey to determine whether the new IT implementations are accomplishing their intended goals.

If the expected benchmarks are not being met, the next step in the IT transformation process is to determine if there is a specific reason for that. Is there a way that the feature can be better integrated to achieve desired business objectives? Are there other features that can help the company better achieve its goals?

Upgrading a network can be an expensive process and it is important to identify early on which options are the most likely to benefit the company’s bottom line.

ESOS Guide for UK Manufacturers Available

The Engineering Employers’ Federation (EEF) is the UK’s largest sectoral structure. Its goal is to promote the interests of manufacturing, engineering and technology-based businesses in order to enhance their competitiveness.

EEF has positioned itself in London and Brussels in order to be in a position to lobby at EU and Westminster level. Part of its role is helping its members adapt to change and capitalise on it. When it discovered that a third of UK manufacturers must comply with ESOS (and 49% had not even heard of it) EEF decided it was time to publish a handbook for its members.

According to EEF’s head of climate and environment policy Gareth Stace, For the many manufacturers that have already taken significant steps to improve energy efficiency, ESOS can be viewed as a ?stock taking exercise?, ensuring that momentum is maintained and new measures are highlighted and taken when possible?.

He goes on to add that others that have not begun the process should view it as an ‘impetus’ to go head down and find the most cost-effective ways to slash energy costs. Ecovaro adds that they would also have the opportunity to reduce carbon emissions almost as a by-product.

Firms with more than 250 employees, over 250 million revenue or both must comply with ESOS across all UK sectors. In simplest terms, they must have conducted an energy audit by 5th December 2015, and logged their energy saving plan with the Environmental Agency that is Britain?s sustainability watchdog.

The Department of Energy & Climate Change (DEEC) that oversees it believes that large UK businesses are wasting ?2.8 billion a year on electricity they do not need. Clearly it makes sense to focus on larger targets; however EcoVaro believes those halfway to the threshold should voluntarily comply if cutting their energy bills by 25% sounds appealing.

We are able to assist with interpreting their energy audits. These are often a matter of installing sub-meters at distribution points, and reading these for a few representative months to establish a trend. Meters are inexpensive compared to electricity costs, and maintenance teams can install them during maintenance shutdowns.

Ecovaro helps these firms process the data into manageable summaries using cloud-based technology. This is on a pay-when-used basis, and hence considerably cheaper than acquiring the software, or appointing a consultant.

Why Executives Fail & How to Avoid It

The ?Peter Principle? concerning why managers fail derives from a broader theory that anything that works under progressively more demanding circumstances will eventually reach its breaking point and fail. The Spanish philosopher Jos? Ortega y Gasset, who was decidedly anti-establishment added, “All public employees should be demoted to their immediately lower level, as they have been promoted until turning incompetent”.

The Peter Principle is an observation, not a panacea for avoiding it. In his book The Peter Principle Laurence J. Peter observes, “In a hierarchy every employee tends to rise to his level of incompetence … in time every post tends to be occupied by an employee who is incompetent to carry out its duties … Work is accomplished by those employees who have not yet reached their level of incompetence.”

Let’s find out what the drivers are behind a phenomenon that may be costing the economy grievously, what the warning signs are and how to try to avoid getting into the mess in the first place.

Drivers Supporting the Peter Principle

As early as 2009 Eva Rykrsmith made a valuable contribution in her blog 10 Reasons for Executive Failure when she observed that ?derailed executives? often find themselves facing similar problems following promotion to the next level:

The Two Precursors

  • They fail to establish effective relationships with their new peer group. This could be because the new member, the existing group, or both, are unable to adapt to the new arrangement.
  • They fail to build, and lead their own team. This could again be because they or their subordinates are unable to adapt to the new situation. There may be people in the team who thought the promotion was theirs.

The Two Outcomes

  • They are unable to adapt to the transition. They find themselves isolated from support groups that would otherwise have sustained them in their new role. Stress may cause errors of judgement and ineffective collaboration.
  • They fail to meet business objectives,?but blame their mediocre performance on critical touch points in the organization. They are unable to face reality. Either they resign, or they face constructive dismissal.

The Warning Signs of Failure

Eva Rykrsmith suggests a number of indicators that an individual is not coping with their demanding new role. Early signs may include:

  • Lagging energy and enthusiasm as if something deflated their ego
  • No clear vision to give to subordinates, a hands-off management style
  • Poor decision-making due to isolation from their teams? ideas and knowledge
  • A state akin to depression and acceptance of own mediocre performance

How to Avoid a ?Peter? in Your Organization

  • Use succession planning to identify and nurture people to fill key leadership roles in the future. Allocate them challenging projects, put them in think tanks with senior employees, find mentors for them, and provide management training early on. When their own manager is away, appoint them in an acting role. Ask for feedback from all concerned. If this is not positive, perhaps you are looking at an exceptional specialist, and not a manager, after all.
  • Consider the future, and not the past when interviewing for a senior management position. Ask about their vision for their part of the organization. How would they go about achieving it? What would the roles be of their subordinates in this? Ask yourself one very simple question; do they look like an executive, or are you thinking of rewarding loyalty.
  • How to Avoid Becoming a ?Peter??Perhaps you are considering an offer of promotion, or applying for an executive job. Becoming a ?Peter? at a senior level is an uncomfortable experience. It has cost the careers of many senior executives dearly. We all have our level of competence where we enjoy performing well. It would be pity to let blind ambition rob us of this, without asking thoughtful questions first. Executives fail when they over-reach themselves, it is not a matter of bad luck.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?