Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Check our similar posts

Authentication and Access Control

Threats to your data can come from external or internal sources.

  1. There are individuals who don’t have the authorisation but are driven by malicious intentions to gain access to certain information. This may refer to individuals who already belong to your organisation (but don’t have the necessary access rights) as well as those who don’t.
  2. There are individuals who have both the authorisation and, unfortunately, the malicious intentions over certain information.
  3. Finally, there are individuals who have the authorisation, no malicious intentions, but have accidentally exposed the information in question to those without the proper authority.

While curbing threats 2 and 3 would require other methods, threat #1 can be countered if the right authentication and access control systems are in place.

Here’s what we can do for you:

  • Work with your key personnel to determine who gets access to what.
  • Help you decide whether a single factor or a two-factor authentication (2FA) is appropriate for your organisation and recommend which factors are most suitable. Login methods may include but are not limited to the following:
    • biometric devices
    • Kerberos tickets
    • mobile phones
    • passwords
    • PKI certificates
    • proximity cards
    • smart cards
    • tokens
  • Install the necessary infrastructure needed for the factors chosen. For instance, if you opt to use biometrics, then biometric scanners will be installed. We’ll make sure that the authentication terminals are situated in places where achieving optimal traffic and work flow has been taken into consideration.

Other defences we’re capable of putting up include:

Scrumming Down to Complete Projects

Everybody knows about rugby union scrums. For our purposes, perhaps it is best to view them as mini projects where the goal is to get the ball back to the fly-half no matter what the opposition does. Some scrums are set pieces where players follow planned manoeuvres. Loose / rolling scrums develop on the fly where the team responds as best according to the situation. If that sounds to you like software project management then read on, because there are more similarities?.

Isn’t Scrum Project Management the Same as Agile?

No it’s not, because Scrum is disinterested in customer liaison or project planning, although the team members may be happy to receive the accolades following success. In the same way that rugby players let somebody else decide the rules and arrange the fixtures, a software Scrum team just wants the action.

Scrum does however align closely ? dare I say interchangeably with Agile?s sprints. Stripping it of all the other stages frees the observer up to analyse it more closely in the context of a rough and tumble project, where every morning can begin with a backlog of revised requirements to back fit.

The 3 Main Phases of a Scrum

A Scrum is a single day in the life of a project, building onto what went before and setting the stage for what will happen the following day. The desired output is a block of component software that can be tested separately and inserted later. Scrumming is also a useful technique for managing any project that can be broken into discreet phases. The construction industry is a good example.

Phase 1 – Define the Backlog. A Scrum Team?s day begins with a 15 minute planning meeting where team members agree individual to-do lists called ?backlogs?.

Phase 2 – Sprint Towards the Goal. The team separates to allow each member to complete their individual lines of code. Little or no discussion is needed as this stage.

Phase 3 – Review Meeting. At the end of each working day, the team reconvenes to walk down what has been achieved, and check the interconnected functionality.

The 3 Main Phases of a Scrum ? Conclusions and Thoughts

Scrum is a great way to liberate a competent project team from unnecessary constraints that liberate creativity. The question you need to ask yourself as manager is, are you comfortable enough to watch proceedings from the side lines without rushing onto the field to grab the ball.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK
Field Service Organisations should use Digital Forms

For many Organisations, making use of paper based forms, is a common practice and method for collecting data and recording transactions. Whether it be for producing Quotations, Invoices or even getting sign off on completed jobs.

Paper based forms and documents have been the main stay of office communication and productivity for over 200 years. Paper-based forms are used to create anything from Invoices, Receipts, Purchase Orders, Contracts to the humble internal memo!

Paper-based forms radically improved productivity, efficiency and compliance by enabling people to create paper based instructions and enabling others to add additional information as required.

Over the past 3 decades or so, modern business environments have gradually been evolving towards the concept of the Paperless Office, resulting in the humble Paper based document migrating to a Digital Counterpart. The ease of availability of various Word Processing and Spreadsheet software products and cheap and easy data storage capacity have resulted in the Proliferation of thousands if not millions of files and documents being stored somewhere on the Company’s IT infrastructure.

People often create Digital Templates of forms that may be printed off and supplied to staff to complete using Pen and Paper or electronically. The data collation and reporting is often process

Often when conducting Operational Reviews, it is commonly found that the processing and analysing paper based forms is the least productive, efficient and profitable areas of business, although it is often vitally important.

Benefits of using digital forms for data collection

The ability to collect and analyse data effectively is increasingly important to businesses. Companies gather, examine, process and build reports on large volumes of data. Traditionally, they have deployed mail surveys, telephone interviews, door-to-door interviews as methods to collect information. With the ongoing digitisation, these procedures have become old fashioned.The digital transformation is changing many business operations at a high speed and a great deal of processes that were executed manually are now accomplished using digital methods.

Technology has had a major impact on how to approach data research and has provided researchers new tools that have transformed and improved data collection and analysis. The pace of change requires companies to be able to react quickly and adapt themselves to changing demands from customers and market conditions.

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?