2015 ESOS Guidelines Chapter 7, 8 & 9 – Sign-Off, Compliance & Appeals

This is the final chapter in our series of short posts summarising the quite complex ESOS guidelines (click on ?Comply with ESOS? to see the details). This one addresses the legalities to follow to complete your report – and how to appeal if you are not happy with any of the Environment Agency?s decisions.

  1. Director Sign-Off

This is by no means an easy ride. Confirmation of the work at individual or lead assessor level locks the company into the penalty cycle in the event there are significant irregularities. By signing off the assessment, the board level director(s) # agree that they have

  • Reviewed the enterprise?s ESOS recommendations
  • Believe the enterprise is within the scope of the scheme
  • Believe the enterprise is compliant with the scheme
  • Believe the information provided is correct

Having an internal assessor requires a second board-level signature.

  1. Compliance

You report compliance on the internet. This is free and you can do it at any time within the deadline. You can dip in and out of the process as many times as you wish, but must use the link in the receipting email. While this is something a board member must do, there is no reason why the lead assessor should not complete the basics. The online compliance notification addresses the following topics:

  • The ESOS contact person in the enterprise
  • Any aggregation / dis-aggregation during the period
  • The names and contact details of the lead assessor
  • The proportion of energy consumption per compliance route

The Environment Agency will acknowledge receipt. This does not constitute acceptance. You should keep the ESOS evidence pack in a safe place with at least one backup elsewhere.

  1. Compliance & Enforcement Issues

In the event the Environment Agency decides your enterprise has not met ESOS requirements, it may either (a) issue a compliance notice with instructions, or (b) apply one of the following civil penalties:

  • A fine of up to ?5,000 for failure to maintain records
  • A fine of up to ?50,000 for failure to undertake an energy audit
  • A fine of up to ?50,000 for a false or misleading statement

Any enterprise has the right of appeal against government decisions. In the case of ESOS, this is via:

  • The First-Tier Tribunal if your enterprise is England, Wales or off-shore based
  • The Scottish Minister if your enterprise is based in Scotland
  • The Planning Commission if your enterprise is Northern Ireland-based

The notice you appeal against will supply details of the appeal steps to take.

This blog and its companion chapters concerning the ESOS Guidelines as amended 2015 are with compliments of ecoVaro. We are the people who break ESOS data into manageable chunks of information, so that board-level directors have greater confidence in what they sign.

Check our similar posts

Month End Accounting the way it should Be Today

Month end accounting has always been a business critical exercise. Without the balance sheet, income statement, and other financial reports this exercise ultimately produces, management could not make informed decisions to keep the company in the right direction and at the ideal operational speed.

Now, in order to maintain optimal business velocity, month end activities have to be carried out as swiftly and as accurately as possible. Delays will only inhibit managers from reacting and effecting necessary adjustments in time. Inaccurate information, on the other hand, obviously lead to bad decisions.

But that’s not all. Never has the month end close been as demanding as it is today. Regulations like the Sarbanes-Oxley Act, Solvency II, Dodd-Frank Act, and others, which call for more stringent controls and more robust risk management practices, are now forcing companies to find better ways to face the end of the month.

Sticking to old month-end practices while striving to achieve regulation compliance can either cost a company more (if they add manpower) or simply bog it down (if they don’t). Among the worst of these practices is the use of spreadsheets.

These User Developed Applications (UDAs) are very susceptible to errors. (See spreadsheet risks)

What’s more, consolidating data from spreadsheets as well as carrying out reconciliations on them is very time consuming. These activities usually require data from outside sources – i.e. a workstation in a different department, building, or (in the case of really large corporations) geographical locations.

Furthermore, if one of these sources fail, the financial reports won’t be complete. This is not a far-fetched scenario, considering that spreadsheet storage and backup is typically carried out by the average end user. This leaves the spreadsheet data vulnerable to hard disk crashes, virus attacks, and unexpected disasters.

Thus, in order to produce accurate financial reports on time all the time, you need a financial/IT solution that offers optimal provisions for risk management, collaboration, backup, and business continuity. Learn about server-based solutions and discover a better way to carry out month end accounting.

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

How DevOps oils the Value Chain

DevOps ? a clipped compound of development and operations – is a way of working whereby software developers are in a team with project beneficiaries. A client centred approach extends the project plan to include the life cycle of the product or service, for which the software is developed.

We can then no longer speak of a software project for say Joe?s Accounting App. The software has no intrinsic value of its own. It follows that the software engineers are building an accounting app product. This is a small, crucially important distinction, because they are no longer in a silo with different business interests.

To take the analogy further, the developers are no longer contractors possibly trying to stretch out the process. They are members of Joe?s accounting company, and they are just as keen to get to market fast as Joe is to start earning income. DevOps uses this synergy to achieve the overarching business goal.

A Brief Introduction to OpsDev

You can skip this section if you already read this article. If not then you need to know that DevOps is a culture, not a working method. The three ?members? are the software developers, the beneficiaries, and a quality control mechanism. The developers break their task into smaller chunks instead of releasing the code to quality control as a single batch. As a result, the review process happens contiguously along these simplified lines.

Code QC Test ? ? ?
? Code QC Test ? ?
? ? Code QC Test ?
? ? ? Code QC Test
Colour Key Developers Quality Control Beneficiary

This is a marked improvement over the previously cumbersome method below.

Write the Code ? Test the Code ? Use the Code
? Evaluate, Schedule for Next Review ?

Working quickly and releasing smaller amounts of code means the OpsDev team learns quickly from mistakes, and should come to product release ahead of any competitor using the older, more linear method. The shared method of working releases huge resources in terms of user experience and in-line QC practices. Instead of being in a silo working on its own, development finds it has a richer brief and more support from being ?on the same side of the organisation?.

The Key Role that Application Program Interfaces Play

Application Program Interfaces, or API?s for short, are building blocks for software applications. Using proprietary software-bridges speeds this process up. A good example would be the PayPal applications that we find on so many websites today. API?s are not just for commercial sites, and they can reduce costs and improve efficiency considerably.

The following diagram courtesy of TIBCO illustrates how second-party applications integrate with PayPal architecture via an API fa?ade.

Working quickly and releasing smaller amounts of code means the OpsDev team learns quickly from mistakes, and should come to product release ahead of any competitor using the older, more linear method. The shared method of working releases huge resources in terms of user experience and in-line QC practices. Instead of being in a silo working on its own, development finds it has a richer brief and more support from being ?on the same side of the organisation?.

imgd2.jpg

The DevOps Revolution Continues ?

We close with some important insights from an interview with Jim Stoneham. He was general manager of the Yahoo Communities business unit, at the time Flickr became a part. ?Flickr was a codebase,? Jim recalls, ?that evolved to operate at high scale over 7 years – and continuing to scale while adding and refining features was no small challenge. During this transition, it was a huge advantage that there was such an integrated dev and ops team?

The ?maturity model? as engineers refer to DevOps status currently, enables developers to learn faster, and deploy upgrades ahead of their competitors. This means the client reaches and exceeds break-even sooner. DevOps lubricates the value chain so companies add value to a product faster. One reason it worked so well with Flickr, was the immense trust between Dev and Ops, and that is a lesson we should learn.

?We transformed from a team of employees to a team of owners. When you move at that speed, and are looking at the numbers and the results daily, your investment level radically changes. This just can’t happen in teams that release quarterly, and it’s difficult even with monthly cycles.? (Jim Stoneham)

Contact Us

  • (+353)(0)1-443-3807 – IRL
  • (+44)(0)20-7193-9751 – UK

Ready to work with Denizon?