Disaster Recovery

Because information technology is now integrated in most businesses, a business continuity plan (BCP) cannot be complete without a corresponding disaster recovery plan (DRP). While a BCP encompasses everything needed – personnel, facilities, communications, processes and IT infrastructure – for a continuous delivery of products and services, a DRP is more focused on the IT aspects of the plan.

If you’re still not sure how big an impact loss of data can have, it’s time you pondered on the survival statistics of companies that incurred data losses after getting hit by a major disaster: 46% never recovered and 51% eventually folded after only two years.

Realising how damaging data loss can be to their entire business, most large enterprises allocate no less than 2% of their IT budget to disaster recovery planning. Those with more sensitive data apportion twice more than that.

A sound disaster recovery plan is hinged on the principles of business continuity. As such, our DRP (Disaster Recovery Plan) blueprints are aimed at getting your IT system up and running in no time. Here’s what we can do for you:

  • Since the number one turn-off against BCPs and DRPs are their price tags, we’ll make a thorough and realistic assessment of possible risks to determine what specific methods need to be applied to your organisation and make sure you don’t spend more than you should.
  • Provide an option for virtualisation to enjoy substantial savings on disaster recovery costs.
  • Provide various backup options and suggest schedules and practices most suitable for your daily transactions.
  • Offer data replication to help you achieve business continuity with the shortest allowable downtime.
  • Refer to your overall BCP to determine your organisation’s critical functions, services, and products as well as their respective priority rankings to know what corresponding IT processes need to be in place first.
  • Implement IT Security to your system to reduce the risks associated with malware and hackers.
  • Introduce best practices to make future disaster recovery efforts as seamless as possible.

We can also assist you with the following:

Check our similar posts

ESOS ? Why we must have it

The 9,000 big UK businesses directly affected by the new Energy Saving Opportunity Scheme could save UK?250 million between them, or an average UK?27,000 each, if they reduced electricity consumption by just 1%. The total amount is equal to the output of five power stations, at a time when Britain?s grid is under strain.
On 26 November 2014, UK Energy and Climate Change Secretary Ed Davey met with over 100 opinion makers from businesses, charities and universities at the Institute of Directors. The gist of what he presented was:

  • ?Britain?s big firms are spending around ?2.8 billion extra each year on inefficient energy technologies ? the equivalent output of nearly five power stations;
  • Now is the time to seize the opportunity with ESOS ? and organisations up and down the country are already gearing up to make changes to save energy, save money and save the environment.
  • If business did what business is supposed to do [that is innovate to make money] and act and invest, it will save ? and that’s the bottom line.?

The environmental benefits are as important although EcoVaro agrees with Ed Davey for taking a pecuniary approach. Businesses above the threshold of 250 staff and a balance sheet of UK?34 million would have not achieved their status unless they spent their money wisely.
The discussion panel included Rhian Kelly (Director of Business Environment at CBI), and Paul Ekins (Director UCL Institute for Sustainable Resources & Deputy Director of the UK Energy Research Centre). Hugh Jones, Managing Director, Advisory at the Carbon Trust responded to Ed Davey?s remarks by commenting:

  • ?At the Carbon Trust we have already engaged with hundreds of businesses on ESOS, helping to explain how they can achieve compliance while also making significant energy savings and cutting carbon.
  • Businesses often aren’t aware of opportunities in energy efficiency, or they don’t realise how attractive the paybacks can be. By requiring companies to understand exactly how they can make cost-effective investment in energy efficiency, they are far more likely to take action.
  • From the interest we have seen so far we expect ESOS to benefit British business by helping companies to reduce overheads and increase competitiveness.

The UK?s Energy Saving Opportunity Scheme ESOS is a gold mine of opportunities for big business, the environment and the population that breathes the air. Measurement of critical energy throughputs is the beginning of the process. EcoVaro is standing by to help you convert your data to meaningful information.

Can you do away with the Project Initiation Meeting?

Project initiation meetings are often skipped to fast-track projects. Once a sponsor is found, organisations go straight to project planning and execution. But based on our own experience, holding a project initiation meeting can actually eliminate many issues that may crop up in the future and hence may speed things up instead in the long run.

It is in the project initiation meeting where your project objectives and scope are clarified and all stakeholders are brought to the same page. Project sponsors and stakeholders will have to know in a nutshell what is needed from them, what the possible risks are, what different resources are required, and so on. So that, when it’s time to proceed to the next phase, everyone is already in-sync.

So what are taken up in such a meeting? Perhaps an actual example can help. Sometime in the past, we set out to work on an eCommerce website project. After conducting the project initiation meeting, these were some of the things we were able to accomplish:

  • Identified deliverables e.g. site design, interface to payment system, etc.
  • Come up with the project phases
  • Agreed what should be in and out of scope
  • Defined the acceptance test criteria
  • Identified possible risks
  • Identified the possible training and documentation work needed
  • Established whether any analysis was required, e.g. as with regards to payment interfaces
  • Formulated disaster recovery plans
  • Defined roles and responsibilities
  • Drafted timelines and due dates

Aren’t these covered in project planning? If the project is a big one, the answer is no. In a large project, project planning is a much more exhaustive activity. In a project initiation meeting, only the basic framework is defined.

Some questions may still remain unanswered after a project initiation meeting, but at least you already know what answers you need to look for. In the example we gave earlier, we left the meeting knowing that we needed:

  • a list of all necessary hardware to estimate the costs
  • to identify possible dependencies we might have with third parties
  • to identify what software had to be bought and what skills we needed to hire

When it was time to proceed to project planning, everyone involved already knew what direction we were taking. In effect, by not skipping the project initiation meeting, we were able to avoid many potential obstacles.

Shared Services ? Are They A Good Idea

Things happen fast in business and we need to stay on top. It does not seem long ago that some enterprises were still hands-on traders or artisans with a few youngsters to help out. People like that did not do admin and their accounting was a matter of making sure there was enough money in the jar.

When Wal-Mart’s Sam Walton took over his first shop in 1945 things had moved on from there, although he did still deal directly with his customers. When he died his legacy was 380,000 jobs, and a business larger than most economies. So there?s plenty we can learn from how he grew his business.

One of Sam?s secrets was his capacity to centralise what needed gathering together, while empowering store managers to think independently when it came to local conditions. His regional warehouses had individual outlets clustered around them within one day?s drive each. This shared service eliminated 90% of safety stock and released capital for expansion.

Wal-Mart took sharing services a step further in February 2006, when it centralised accounts payable, accounts receivable, general accounting and human resources administration at Wal-Mart Stores and Sam?s Clubs in the U.S. and Puerto Rico. The objective was to bring costs down, while allowing local managers more time to focus on their business plans and other initiatives. As a further spin-off, Wal-Mart was able to integrate its data on a single SAP platform and eliminate significant roadblocks.

This is an excellent example of sharing services by creating own centres of excellence.? Of course, this is not the only business possibility. Other corporates have successfully completely outsourced their support activities, and Wal-Mart has no doubt had a variety of similar offers too. But, is the Wal-Mart picture entirely rosy, or is there a catch?

The Association of Chartered Certified Accountants has indicated that top talent may be the loser globally. This is because the Wal-Mart model removes many challenges through standardisation, and offers less scope for internal promotion as a result. Language and cultural differences may also have a long-term detrimental effect on the way the departments work well together.

Local outsourcing ? this is the business model where several firms engage a shared service provider independently- may hence prove to be a more malleable option for smaller companies. It often makes more sense to hunt down made-to-order services. Offerings such as the professional support we offer on this site.

Ready to work with Denizon?